Permit: T18CM04776
Permit Details
Apply Date:
06/19/2018
Applicant:
TOM, RICHARD FE
Description:
STORAGE
Contractors:
- BETTER BUILT BUILDERS INC *
Permit Reviews
Permit Number - T18CM04776
Permit Status: C of o
Permit Description: STORAGE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/15/2019 | REVISION - - 2ND | 01/15/2019 | COMPLETED |
| 06/19/2018 | PLANS OK TO SUBMIT - COMM | 06/19/2018 | COMPLETED |
| 06/19/2018 | COMMERCIAL - NEW | 09/06/2018 | COMPLETED |
| 09/06/2018 | COMMERCIAL - NEW | 09/26/2018 | COMPLETED |
| 10/17/2018 | REVISION - - 1ST | 10/30/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM04776
Permit Status: C of o
Permit Description: STORAGE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/19/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T18CM04776
Permit Description: STORAGE
Total Completed Inspections - 35
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/28/2018 | PLUMBING - SEWER HCS CONNECT | DFLORES | Approved | |
| 09/28/2018 | PLUMBING - PROGRESS | DFLORES | Approved | |
| 10/30/2018 | ELECTRIC - UFER | ESTEVENS | Approved | |
| 11/02/2018 | BUILDING PRE-SLAB | DMCCARTHY | Approved | |
| 11/02/2018 | EXCAVATION/LAYOUT REBAR & ZON | DMCCARTHY | Approved | |
| 12/06/2018 | ELECTRIC - UNDERGROUND | DMCCARTHY | Approved | |
| 12/07/2018 | ELECTRIC - PROGRESS | ESTEVENS | Approved | Cancel by contractor due to rain |
| 12/13/2018 | REINFORCED MASONRY PRE-GROUT | TVALENCIA | Approved | |
| 01/14/2019 | PLUMBING - YARD WTR LINE/TEST | ESTEVENS | Approved | |
| 01/16/2019 | PLUMBING - INTERMEDIATE | DMCCARTHY | Approved | |
| 01/16/2019 | ELECTRIC - INTERMEDIATE | DMCCARTHY | Approved | |
| 01/16/2019 | FRAMING | DMCCARTHY | Approved | |
| 01/28/2019 | GAS CLEARANCE | ESTEVENS | Approved | |
| 01/30/2019 | TEP CLEARANCE - AM | TVALENCIA | Approved | CODE ECO |
| 02/01/2019 | MECHANICAL - ABOVE CEILING | TVALENCIA | Approved | |
| 02/01/2019 | ELECTRIC - ABOVE CEILING | TVALENCIA | Approved | |
| 02/01/2019 | BUILDING ABOVE CEILING | TVALENCIA | Approved | |
| 03/15/2019 | ELECTRIC - SERVICE UPGRADE | ESTEVENS | Approved | PER BUILDING FINAL |
| 03/15/2019 | MECHANICAL - PROGRESS | ESTEVENS | Approved | PER BUILDING FINAL |
| 03/15/2019 | MECHANICAL - INTERMEDIATE | ESTEVENS | Approved | PER BUILDING FINAL |
| 03/15/2019 | SITE - SEWER | ESTEVENS | Approved | PER BUILDING FINAL |
| 03/15/2019 | PLUMBING - GAS PRESS TEST FNL | ESTEVENS | Approved | PER BUILDING FINAL |
| 03/15/2019 | BUILDING - PROGRESS | ESTEVENS | Approved | PER BUILDING FINAL |
| 03/15/2019 | FIREWALL/FIREBARRIER/FIRESTOP | ESTEVENS | Approved | PER BUILDING FINAL |
| 03/15/2019 | ROOF NAILING | ESTEVENS | Approved | |
| 03/15/2019 | U VALUE FOR WINDOW | ESTEVENS | Approved | PER BUILDING FINAL |
| 03/15/2019 | CERTIFICATE OF OCCUPANCY | ESTEVENS | Approved | |
| 03/15/2019 | BUILDING - FINAL | ESTEVENS | Approved | |
| 03/15/2019 | FIRE - FINAL | CBASALDUA | Approved | |
| 03/15/2019 | BUILDING - FINAL | ESTEVENS | Approved | Pending other inspections |
| 03/15/2019 | MECHANICAL - FINAL | ESTEVENS | Approved | |
| 03/15/2019 | ELECTRIC - FINAL | ESTEVENS | Approved | |
| 04/12/2019 | PLUMBING - GAS PRESSURE TEST | ESTEVENS | Approved | PER BUILDING FINAL |
| 04/12/2019 | PLUMBING - FINAL | ESTEVENS | Approved | WATER REPORT REVIEWED ON 02/04/2019 |
| 04/12/2019 | ENGINEERING - FINAL | DROBERTS | Approved |