Inspection Status: Approved
Inspection History: ELECTRIC - PROGRESS
| Date |
Description |
Inspector |
Results |
Comments |
| 03/15/2019 |
ELECTRIC - PROGRESS |
|
Approved |
PER BUILDING FINAL |
| 01/23/2019 |
ELECTRIC - PROGRESS |
|
Partial Approval |
Rebar and ufer for two light poles |
| 12/07/2018 |
ELECTRIC - PROGRESS |
|
Cancelled |
Cancel by contractor due to rain |
| 10/04/2018 |
ELECTRIC - PROGRESS |
|
Partial Approval |
PHONE AND ELECTRIC SECONDARY CONDUITS OK TO BACKFILL FROM SWITCHGEAR WEST. |