Permit: T18CM02298
Permit Details
Apply Date:
03/27/2018
Applicant:
SHAMBACH, ROBIN ADELE
Description:
MEDICAL OFFICE CLINIC
Contractors:
- LLOYD CONSTRUCTION COMPANY INC ,
Permit Reviews
Permit Number - T18CM02298
Permit Status: C of o
Permit Description: MEDICAL OFFICE CLINIC
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/27/2018 | PLANS OK TO SUBMIT - COMM | 03/28/2018 | COMPLETED |
04/02/2018 | COMMERCIAL - TI | 05/14/2018 | COMPLETED |
05/16/2018 | RESUBMITTAL | 06/15/2018 | COMPLETED |
06/20/2018 | RESUBMITTAL | 07/18/2018 | COMPLETED |
12/11/2018 | REVISION - - 1ST | 12/11/2018 | COMPLETED |
12/11/2018 | REVISION - - 1ST | 12/28/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM02298
Permit Status: C of o
Permit Description: MEDICAL OFFICE CLINIC
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
03/27/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T18CM02298
Permit Description: MEDICAL OFFICE CLINIC
Total Completed Inspections - 43
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/18/2018 | ELECTRIC - TEMPORARY SERVICE | MHASSAN | Approved | APPROVAL IS FOR TEMPORARY FEEDERS. OK TO CLEAR ELECTRIC, RECN. CALLED IT INTO TEP AFTER HOURS. |
08/21/2018 | TEP CLEARANCE - AM | DFLORES | Approved | RECN |
10/19/2018 | ELECTRIC - UNDERGROUND | GWEST | Approved | Building interior electrical conduit is approved |
10/22/2018 | PLUMBING - ROUGH, SOIL | GWEST | Approved | 1st floor underground plumbing. Underground phase from B line to V line and from 13 line to 6 line |
11/26/2018 | EXCAVATION/LAYOUT REBAR & ZON | MHASSAN | Approved | changed to PA due to more inspections |
12/12/2018 | STEM WALL/RETAINING WALL | BJONES | Approved | Mech Yd in closure #5 32”OC w/ 2#5s Top and mid height with clean outs. |
12/19/2018 | BUILDING PRE-SLAB | BJONES | Approved | Second Floor Pour |
12/28/2018 | BUILDING - PROGRESS | BJONES | Approved | Bar Joist Deferred Submittal Approved by Eric on 12-19-18 changed to PA upon DQUINN'S req to reopen |
01/28/2019 | SITE - SEWER | DQUINN | Approved | Ok to back fill |
02/27/2019 | PLUMBING - INTERMEDIATE | BJONES | Approved | Water line test in building at 100 psi |
02/27/2019 | PLUMBING - YARD WTR LINE/TEST | BJONES | Approved | |
02/27/2019 | PLUMBING - ROOF DRAINS | bjones | Approved | |
05/02/2019 | ELECTRIC - SERVICE UPGRADE | GWEST | Approved | 277/480; 2000 amp main breaker TEP Clearance, ECO TEP was called (Roman-message 11:50 AM) for Saturday changeover |
09/20/2019 | PLUMBING - PROGRESS | DMUNIZ | Approved | Ok to insulate and Sheetrock. |
09/20/2019 | ELECTRIC - INTERMEDIATE | DMUNIZ | Approved | |
11/07/2019 | PLUMBING - ABOVE CEILING | MRAMBER | Approved | |
11/07/2019 | BUILDING ABOVE CEILING | MRAMBER | Approved | |
11/07/2019 | ELECTRIC - ABOVE CEILING | MRAMBER | Approved | |
11/12/2019 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | |
11/12/2019 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | |
11/21/2019 | FIRE - FINAL | CBASALDUA | Approved | |
11/21/2019 | FIRE - ALARM FINAL | CBASALDUA | Approved | |
11/21/2019 | FIRE SPKLR - FINAL | CBASALDUA | Approved | |
11/22/2019 | FIREWALL/FIREBARRIER/FIRESTOP | DQUINN | Approved | |
11/22/2019 | EXT METAL CLIPS/EXT SHEATHING | MRAMBER | Approved | |
11/22/2019 | ROOF NAILING | MRAMBER | Approved | |
11/22/2019 | FRAMING | MRAMBER | Approved | |
11/22/2019 | U VALUE FOR WINDOW | MRAMBER | Approved | |
11/22/2019 | FIREWALL/FIREBARRIER/FIRESTOP | MRAMBER | Approved | Second layer elevator shaft and fire caulking not inspected. |
11/22/2019 | ELECTRIC - OUTDOOR LIGHTING | MRAMBER | Approved | |
11/22/2019 | ELECTRIC - PROGRESS | MRAMBER | Approved | |
11/22/2019 | ELECTRIC - UFER | MRAMBER | Approved | |
11/22/2019 | ELECTRIC - CONSTRUCTION POWER | MRAMBER | Approved | |
11/29/2019 | PLUMBING - MEDICAL GAS/FINAL | DMUNIZ | Approved | |
11/29/2019 | PLUMBING - MEDICAL GAS/TEST | DMUNIZ | Approved | |
11/29/2019 | ELECTRIC - FINAL | DMUNIZ | Approved | |
11/29/2019 | CERTIFICATE OF OCCUPANCY | DMUNIZ | Approved | |
11/29/2019 | MECHANICAL - FINAL | DMUNIZ | Approved | |
11/29/2019 | PLUMBING - MD GAS/PRECONST MTG | DMUNIZ | Approved | |
11/29/2019 | PLUMBING - FINAL | DMUNIZ | Approved | |
12/20/2019 | OUTDOOR LIGHTING FINAL | DMUNIZ | Approved | |
12/20/2019 | BUILDING - FINAL | DMUNIZ | Approved | |
12/20/2019 | ENGINEERING - FINAL | RELDONNE | Approved |