Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date |
Description |
Inspector |
Results |
Comments |
| 08/30/2019 |
PLUMBING - ROUGH, SOIL |
|
Approved |
|
| 08/29/2019 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
phase 2 underground from (C.L4 to C.L8) Restrooms, Exam rooms & Lab ok to backfill. |
| 08/28/2019 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
Phase 2 changing area and janitor area OK to backfill |
| 08/27/2019 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
Exam rooms at C.L 10.2 and C thru E, C.L. 9 and B thru D. Pharmacy C.L. 2.8 and D thru E. Ok to backfill. |
| 04/02/2019 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
Approved for mop sink and 2 exam rooms. Second phase partial waste line in phase 1 area. |
| 10/22/2018 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
1st floor underground plumbing. Underground phase from B line to V line and from 13 line to 6 line |