Inspection Status: Approved
Inspection History: MECHANICAL - ABOVE CEILING
| Date |
Description |
Inspector |
Results |
Comments |
| 11/12/2019 |
MECHANICAL - ABOVE CEILING |
|
Approved |
|
| 10/07/2019 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
OK above hard lids. |
| 10/04/2019 |
MECHANICAL - ABOVE CEILING |
|
Not ready for Inspection |
Work above hard lids still not ready, another failed inspection will result in a reinspection fee. |
| 10/02/2019 |
MECHANICAL - ABOVE CEILING |
|
Not ready for Inspection |
Work not complete. |
| 09/16/2019 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
OK to proceed with duct seal and duct wrap. |
| 09/13/2019 |
MECHANICAL - ABOVE CEILING |
|
Not ready for Inspection |
Complete work for inspection, OK to one side |
| 06/11/2019 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
South of B line. |
| 06/05/2019 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
1st and 2nd floor corridors and 2nd floor Multipurpose room, All above ceiling inspections ok to cover. Leave VAV tiles open. |
| 06/03/2019 |
MECHANICAL - ABOVE CEILING |
|
Cancelled |
Cancelled by Max |
| 05/29/2019 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
All above ceiling inspections from B line north on 1st floor, except stair corridor, ok to cover. Leave VAV tiles open. |