Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/14/2018 | PLANS OK TO SUBMIT - COMM | 03/15/2018 | COMPLETED |
03/22/2018 | 3RD PARTY REVIEW - COMMERCIAL | 04/24/2018 | COMPLETED |
04/24/2018 | POST 3RD PARTY REVIEW | 10/25/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM01942
Permit Status: C of o
Permit Description: RESTAURANT
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
03/14/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T18CM01942
Permit Description: RESTAURANT
Total Completed Inspections - 46
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/19/2018 | ELECTRIC - UFER | RCAMACHO | Approved | |
06/19/2018 | BUILDING PRE-SLAB | RCAMACHO | Approved | |
06/19/2018 | STEM WALL/RETAINING WALL | RCAMACHO | Approved | |
07/11/2018 | ROOF NAILING | mramber1 | Approved | |
07/13/2018 | EXT METAL CLIPS/EXT SHEATHING | mramber1 | Approved | |
07/13/2018 | FRAMING | mramber1 | Approved | |
07/13/2018 | PLUMBING - INTERMEDIATE | mramber1 | Approved | |
07/13/2018 | PLUMBING - ROOF DRAINS | mramber1 | Approved | |
07/24/2018 | PLUMBING - YARD WTR LINE/TEST | ESTEVEN1 | Approved | FROM THE WATER METER TO COPPER INSIDE BUILDING. |
07/27/2018 | STUCCO MESH | RCAMACHO | Approved | |
07/30/2018 | SHEET ROCK NAILING | BJONES1 | Approved | IVRS - Inspection :* |
08/03/2018 | ELECTRIC - INTERMEDIATE | RCAMACHO | Approved | |
08/15/2018 | ELECTRIC - UNDERGROUND | BJONES1 | Approved | IVRS - Inspection :* 2- 4" PVC AND 1- 1" PVC |
08/31/2018 | MECHANICAL - HOODS | RCAMACH1 | Approved | IVRS - Inspection :* |
08/31/2018 | ELECTRIC - PROGRESS | RCAMACH1 | Approved | IVRS - Inspection :* |
08/31/2018 | ELECTRIC - CABLE DROP | RCAMACH1 | Approved | IVRS - Inspection :* |
09/04/2018 | TEP CLEARANCE - AM | RCAMACHO | Approved | ECO |
09/18/2018 | PLUMBING - GAS PRESSURE TEST | MRAMBER1 | Approved | IVRS - Inspection :* |
09/18/2018 | U VALUE FOR WINDOW | MRAMBER1 | Approved | IVRS - Inspection :* |
09/18/2018 | REINFORCED MASONRY PRE-GROUT | MRAMBER1 | Approved | IVRS - Inspection :* |
09/26/2018 | EXCAVATION/LAYOUT REBAR & ZON | ESTEVENS | Approved | SAUNA TUBES FOR LIGHTING AND MENU BOARDS 3/4” and 1 inch conduit run to lighting poles and signs. |
09/26/2018 | PLUMBING - SEWER HCS CONNECT | BJONES | Approved | HCS AND GREASE INTERCEPTOR |
09/26/2018 | MECHANICAL - ABOVE CEILING | RCAMACHO | Approved | |
09/26/2018 | PLUMBING - ABOVE CEILING | RCAMACHO | Approved | |
09/26/2018 | ELECTRIC - ABOVE CEILING | RCAMACHO | Approved | |
09/26/2018 | BUILDING ABOVE CEILING | RCAMACHO | Approved | |
09/28/2018 | PLUMBING - GAS PRESS TEST FNL | ESTEVENS | Approved | |
09/28/2018 | PLUMBING - MD GAS/PRECONST MTG | ESTEVENS | Approved | |
09/28/2018 | PLUMBING - GAS PRESS TEST FNL | ESTEVENS | Approved | |
09/28/2018 | PLUMBING - MD GAS/PRECONST MTG | ESTEVENS | Approved | |
10/04/2018 | FIRE - KITCHEN EXH HOOD FINAL | CBASALDUA | Approved | |
10/11/2018 | PLUMBING - ROUGH, SOIL | ESTEVENS | Approved | Approved by Bill Jones on September 10, 2018 |
10/11/2018 | MECHANICAL - INTERMEDIATE | ESTEVENS | Approved | Approved by Ray on September 25, 2018 |
10/11/2018 | ELECTRIC - FINAL | ESTEVENS | Approved | |
10/17/2018 | BUILDING - PROGRESS | IVR USER | Approved | IVRS - AP canceled |
10/17/2018 | OUTDOOR LIGHTING FINAL | MRAMBER | Approved | |
10/17/2018 | ELECTRIC - OUTDOOR LIGHTING | MRAMBER | Approved | |
10/17/2018 | ELECTRIC - CONSTRUCTION POWER | MRAMBER | Approved | |
10/18/2018 | MECHANICAL - HOOD SYSTEMS | rcamacho | Approved | |
10/24/2018 | PLUMBING - FINAL | RSHERRY | Approved | REVIEW OF WATER CHLORINATION REPORT COMPLETED |
10/24/2018 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETED |
10/25/2018 | BUILDING - FINAL | RCAMACHO | Approved | |
10/25/2018 | PLUMBING - PROGRESS | RCAMACHO | Approved | |
10/25/2018 | MECHANICAL - PROGRESS | RCAMACHO | Approved | |
10/25/2018 | FIRE - FINAL | J.V | Approved | |
10/25/2018 | ENGINEERING - FINAL | bbenedo1 | Approved |