Inspection Status: Approved
Inspection History: PLUMBING - FINAL
| Date |
Description |
Inspector |
Results |
Comments |
| 10/24/2018 |
PLUMBING - FINAL |
|
Approved |
REVIEW OF WATER CHLORINATION REPORT COMPLETED |
| 10/18/2018 |
PLUMBING - FINAL |
|
Partial Approval |
Pending fire and Engineering finals Air Balance report and chlorination report to Bob Sherry 8 a.m. to 9:30 a.m |
| 10/17/2018 |
PLUMBING - FINAL |
|
Not ready for Inspection |
Sterilization report approval required, 3 comp sink to have separate drains, coat all exterior PVC |
| 10/11/2018 |
PLUMBING - FINAL |
|
Partial Approval |
ice machine drain pipes or in floor sink, also pending water report |