Inspection Status: Approved
Inspection History: MECHANICAL - FINAL
| Date |
Description |
Inspector |
Results |
Comments |
| 10/24/2018 |
MECHANICAL - FINAL |
|
Approved |
REVIEW OF AIR BALANCE REPORT COMPLETED |
| 10/18/2018 |
MECHANICAL - FINAL |
|
Partial Approval |
Pending fire and Engineering finals Air Balance report and chlorination report to Bob Sherry 8 a.m. to 9:30 a.m |
| 10/17/2018 |
MECHANICAL - FINAL |
|
Not ready for Inspection |
Complete all inspections, provide air balance approval, hood exhaust to have 1500 deg. gasket at fan, remove lip of grease duct at fan connection causing damming of grease, AC-1 not properly leveled, condensate draining up hill, coat line sets on roof |
| 10/11/2018 |
MECHANICAL - FINAL |
|
Not ready for Inspection |
|