Permit: T17CM09232
Permit Details
Status:
C of o
Type:
MULTI FAMILY NEW
Address:
485 S STONE AV BLDG#2
Address NEW:
485 S STONE AV BLDG#2
Apply Date:
12/14/2017
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
HOTEL
Architects:
- PAGE REPP
Contractors:
- MW MORRISSEY CONSTRUCTION LLC
Permit Reviews
Permit Number - T17CM09232
Permit Status: C of o
Permit Description: HOTEL
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/03/2018 | COMMERCIAL - NEW | 02/27/2018 | COMPLETED |
| 01/10/2019 | REVISION - - 2ND | 03/12/2019 | COMPLETED |
| 03/08/2018 | RESUBMITTAL - TI ALL | 04/20/2018 | COMPLETED |
| 03/12/2019 | REVISION - - 2ND | 05/23/2019 | COMPLETED |
| 04/20/2018 | RESUBMITTAL | 12/05/2018 | COMPLETED |
| 05/23/2019 | REVISION - - 3RD | 05/23/2019 | COMPLETED |
| 12/11/2018 | REVISION - - 1ST | 12/11/2018 | COMPLETED |
| 12/14/2017 | PLANS OK TO SUBMIT - COMM | 12/19/2017 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T17CM09232
Permit Description: HOTEL
Total Completed Inspections - 39
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/16/2018 | PLUMBING - ROUGH, SOIL | MHASSAN | Approved | |
| 11/16/2018 | ELECTRIC - UNDERGROUND | MHASSAN | Approved | |
| 11/16/2018 | ELECTRIC - UFER | MHASSAN | Approved | stub up okay |
| 11/16/2018 | STEM WALL/RETAINING WALL | MHASSAN | Approved | |
| 11/16/2018 | EXCAVATION/LAYOUT REBAR & ZON | MHASSAN | Approved | |
| 12/03/2018 | PLUMBING - PRE SLAB | MHASSAN | Approved | building 2 okay |
| 12/03/2018 | BUILDING PRE-SLAB | MHASSAN | Approved | building 2 okay |
| 01/22/2019 | REINFORCED MASONRY PRE-GROUT | RCAMACHO | Approved | |
| 02/12/2019 | PLUMBING - BACK WATER VALVE | MHASSAN | Approved | |
| 03/21/2019 | ROOF NAILING | ESTEVENS | Approved | |
| 03/21/2019 | EXT METAL CLIPS/EXT SHEATHING | ESTEVENS | Approved | |
| 04/02/2019 | MECHANICAL - INTERMEDIATE | MHASSAN | Approved | |
| 04/02/2019 | ELECTRIC - INTERMEDIATE | MHASSAN | Approved | |
| 07/24/2019 | TEP CLEARANCE - PM | JBURGE | Approved | CODE ECO |
| 07/24/2019 | ELECTRIC - CONSTRUCTION POWER | JBURGE | Approved | Ok to energize for construction power, secondary lines in place to transformer (to be set by TEP). |
| 09/18/2019 | MECHANICAL - PROGRESS | JBURGE | Approved | |
| 09/18/2019 | MECHANICAL - FINAL | JBURGE | Approved | |
| 09/18/2019 | ELECTRIC - SERVICE UPGRADE | JBURGE | Approved | |
| 09/18/2019 | PLUMBING - FINAL | JBURGE | Approved | |
| 09/18/2019 | PLUMBING - PROGRESS | JBURGE | Approved | |
| 09/18/2019 | PLUMBING - GAS PRESS TEST FNL | JBURGE | Approved | |
| 09/18/2019 | PLUMBING - GAS PRESSURE TEST | JBURGE | Approved | |
| 09/18/2019 | PLUMBING - INTERMEDIATE | JBURGE | Approved | |
| 09/18/2019 | OUTDOOR LIGHTING FINAL | JBURGE | Approved | |
| 09/18/2019 | ELECTRIC - FINAL | JBURGE | Approved | |
| 09/18/2019 | ELECTRIC - OUTDOOR LIGHTING | JBURGE | Approved | |
| 09/18/2019 | ELECTRIC - PROGRESS | JBURGE | Approved | |
| 09/18/2019 | BUILDING - PROGRESS | JBURGE | Approved | |
| 09/18/2019 | U VALUE FOR WINDOW | JBURGE | Approved | |
| 09/18/2019 | SHEET ROCK NAILING | JBURGE | Approved | |
| 09/18/2019 | FRAMING | JBURGE | Approved | |
| 09/24/2019 | FIRE SPKLR - FINAL | MRoss | Approved | |
| 09/24/2019 | RIGHT OF WAY - FINAL | Bravin | Approved | No inspection needed |
| 09/24/2019 | NPPO - FINAL | BBENEDON | Approved | Will inspect these under the development package permit. |
| 09/24/2019 | SIGN - FINAL | BBENEDON | Approved | Will inspect these under the development package permit. |
| 09/24/2019 | LANDSCAPE - FINAL | BBENEDON | Approved | Will inspect these under the development package permit. |
| 10/07/2019 | FIRE - FINAL | MRoss | Approved | |
| 12/05/2019 | ENGINEERING - FINAL | BBENEDON | Approved | |
| 12/23/2019 | BUILDING - FINAL | JCLAXTON | Approved |