Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - INTERMEDIATE
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/18/2019 | PLUMBING - INTERMEDIATE | Approved | ||
| 04/24/2019 | PLUMBING - INTERMEDIATE | Partial Approval | Pending verification of ADA shower diverter location | |
| 04/23/2019 | PLUMBING - INTERMEDIATE | Not ready for Inspection | work now complete comply with previous | |
| 04/22/2019 | PLUMBING - INTERMEDIATE | Denied | 1- Shall provide a vent for all of the second floor shower drains. 2- Shall provide 18 inches of frontal clearance for 1st floor 3 inch clean out. 3- Retest the system. |
|
| 04/19/2019 | PLUMBING - INTERMEDIATE | Partial Approval | PVC piping under test OK | |
| 02/12/2019 | PLUMBING - INTERMEDIATE | Not ready for Inspection | sewer HCS OK |