Permit: T17CM09101
Permit Details
Apply Date:
12/11/2017
Applicant:
A23 STUDIOS/ MATT WILLIAMS
Description:
TI: SALON
Architects:
- A23 STUDIOS
Contractors:
- DIVISION II CONSTRUCTION COMPANY
Permit Reviews
Permit Number - T17CM09101
Permit Status: C of o
Permit Description: TI: SALON
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/19/2018 | 3RD PARTY REVIEW - COMMERCIAL TI | 03/29/2018 | COMPLETED |
| 03/29/2018 | POST 3RD PARTY REVIEW | 08/13/2018 | COMPLETED |
| 12/04/2018 | 3RD PARTY REVIEW - REVISION/OTHER | 12/19/2018 | COMPLETED |
| 12/11/2017 | PLANS OK TO SUBMIT - COMM | 12/11/2017 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM09101
Permit Status: C of o
Permit Description: TI: SALON
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 12/11/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T17CM09101
Permit Description: TI: SALON
Total Completed Inspections - 27
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/02/2018 | BUILDING - PROGRESS | BJONES | Approved | room 106 pier footings F3 and F4 per plan |
| 10/05/2018 | EXCAVATION/LAYOUT REBAR & ZON | MRAMBER | Approved | |
| 11/20/2018 | ELECTRIC - PROGRESS | DMCCARTHY | Approved | |
| 12/11/2018 | ELECTRIC - ABOVE CEILING | RCAMACHO | Approved | Work not complete enough to inspect |
| 12/11/2018 | FRAMING | RCAMACHO | Approved | |
| 12/17/2018 | MECHANICAL - ABOVE CEILING | DMCCARTHY | Approved | eave out drywall to air handlers |
| 12/19/2018 | PLUMBING - ABOVE CEILING | ESTEVENS | Approved | |
| 12/19/2018 | PLUMBING - INTERMEDIATE | ESTEVENS | Approved | |
| 12/19/2018 | ELECTRIC - INTERMEDIATE | ESTEVENS | Approved | |
| 12/27/2018 | MECHANICAL - INTERMEDIATE | DMCCARTHY | Approved | |
| 12/27/2018 | PLUMBING - PROGRESS | DMCCARTHY | Approved | |
| 12/27/2018 | PLUMBING - SEWER HCS CONNECT | DMCCARTHY | Approved | call permits office WillDan is the plan reviewer |
| 12/27/2018 | BUILDING ABOVE CEILING | DMCCARTHY | Approved | |
| 01/03/2019 | ELECTRIC - UNDERGROUND | RCAMACHO | Approved | 2 x 4" secondaries from transformer to future switchgear |
| 01/17/2019 | ELECTRIC - SERVICE UPGRADE | RCHANDLER | Approved | |
| 01/18/2019 | TEP CLEARANCE - AM | RCHANDLER | Approved | INCR |
| 02/25/2019 | FIRE SPKLR - FINAL | CBASALDUA | Approved | |
| 02/25/2019 | PLUMBING - FINAL | RCHANDLER | Approved | |
| 02/25/2019 | SHEET ROCK NAILING | RCHANDLER | Approved | |
| 02/25/2019 | PLUMBING - FINAL | RCHANDLER | Approved | Pending chlorination report approval. |
| 02/25/2019 | ELECTRIC - FINAL | RCHANDLER | Approved | |
| 02/25/2019 | ENGINEERING - FINAL | BBENEDON | Approved | |
| 02/25/2019 | PLUMBING - FINAL | RSHERRY | Approved | REVIEW OF WATER DISINFECTION REPORT COMPLETED |
| 02/28/2019 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETED |
| 04/05/2019 | FIRE - FINAL | gsereno1 | Approved | |
| 04/05/2019 | FIRE - ALARM FINAL | gsereno1 | Approved | |
| 04/08/2019 | BUILDING - FINAL | ESTEVENS | Approved |