Permit: T17CM00366
Permit Details
Apply Date:
01/17/2017
Applicant:
N/A
Description:
NEW 7 STORY HOUSING WITH PRKING GARAGE AND COMMUNITY SPACE
Architects:
- MIRTO, JON MICHAEL
Contractors:
- TOFEL CONSTRUCTION LLC
Permit Reviews
Permit Number - T17CM00366
Permit Status: C of o
Permit Description: NEW 7 STORY HOUSING WITH PRKING GARAGE AND COMMUNITY SPACE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/04/2018 | 3RD PARTY REVIEW - REVISION/OTHER-2ND | 01/08/2018 | COMPLETED |
| 01/17/2017 | PLANS OK TO SUBMIT - COMM | 01/18/2017 | COMPLETED |
| 01/19/2017 | 3RD PARTY REVIEW - COMMERCIAL | 02/21/2017 | COMPLETED |
| 02/12/2018 | 3RD PARTY REVIEW - REVISION/OTHER | 02/15/2018 | COMPLETED |
| 02/21/2017 | POST 3RD PARTY REVIEW | 12/27/2017 | COMPLETED |
| 08/29/2018 | 3RD PARTY REVIEW - REVISION/OTHER-2ND | 09/06/2018 | ACTIVE |
| 12/27/2017 | 3RD PARTY REVIEW - REVISION/OTHER | 01/08/2018 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T17CM00366
Permit Description: NEW 7 STORY HOUSING WITH PRKING GARAGE AND COMMUNITY SPACE
Total Completed Inspections - 44
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/05/2017 | ELECTRIC - UNDERGROUND | mramber1 | Approved | secondaries from switch gear to bldg. foorprint ok, fire pump U.G. ok, UFER placement ok |
| 09/07/2017 | PLUMBING - ROUGH, SOIL | DROBERTS | Approved | CREWS WORKING ON INSTALLING 8" STORMDRAIN LINES |
| 09/29/2017 | BUILDING PRE-SLAB | mramber1 | Approved | cancelled |
| 11/28/2017 | EXCAVATION/LAYOUT REBAR & ZON | mramber1 | Approved | level 6 columns,stemwalls ok |
| 12/13/2017 | PLUMBING - INTERMEDIATE | mramber1 | Approved | DWV level 1 & 2 ok |
| 05/07/2018 | EXT METAL CLIPS/EXT SHEATHING | mramber1 | Approved | |
| 05/07/2018 | PLUMBING - ROOF DRAINS | mramber1 | Approved | |
| 06/14/2018 | SITE - SEWER | mramber1 | Approved | |
| 06/25/2018 | MECHANICAL - ABOVE CEILING | ESTEVEN1 | Approved | APPROVED |
| 06/25/2018 | PLUMBING - ABOVE CEILING | ESTEVEN1 | Approved | APPROVED |
| 06/25/2018 | ELECTRIC - ABOVE CEILING | ESTEVEN1 | Approved | APPROVED |
| 06/29/2018 | PLUMBING - GAS PRESSURE TEST | mramber1 | Approved | |
| 08/15/2018 | PLUMBING - MD GAS/PRECONST MTG | mramber1 | Approved | |
| 08/30/2018 | TEP CLEARANCE - AM | MRAMBER | Approved | ECO |
| 09/07/2018 | GAS CLEARANCE | MRAMBER | Approved | |
| 09/28/2018 | BUILDING ABOVE CEILING | MRAMBER | Approved | 1st and 2nd floor elevator ok to rock. |
| 12/11/2018 | MECHANICAL - INTERMEDIATE | RCAMACHO | Approved | per Matt Ramber |
| 12/11/2018 | PLUMBING - SEWER HCS CONNECT | RCAMACHO | Approved | per Matt Ramber |
| 12/11/2018 | PLUMBING - GAS PRESS TEST FNL | RCAMACHO | Approved | per Matt Ramber |
| 12/11/2018 | ELECTRIC - OUTDOOR LIGHTING | RCAMACHO | Approved | per Matt Ramber |
| 12/11/2018 | ELECTRIC - PROGRESS | RCAMACHO | Approved | per Matt Ramber |
| 12/11/2018 | ELECTRIC - CABLE DROP | RCAMACHO | Approved | per Matt Ramber |
| 12/11/2018 | ELECTRIC - INTERMEDIATE | RCAMACHO | Approved | per Matt Ramber |
| 12/11/2018 | ELECTRIC - UFER | RCAMACHO | Approved | per Matt Ramber |
| 12/11/2018 | SHEET ROCK NAILING | RCAMACHO | Approved | per Matt Ramber |
| 12/11/2018 | U VALUE FOR WINDOW | RCAMACHO | Approved | per Matt Ramber |
| 12/11/2018 | STUCCO MESH | RCAMACHO | Approved | per Matt Ramber |
| 12/11/2018 | ROOF NAILING | RCAMACHO | Approved | per Matt Ramber |
| 12/11/2018 | REINFORCED MASONRY PRE-GROUT | RCAMACHO | Approved | per Matt Ramber |
| 12/11/2018 | STEM WALL/RETAINING WALL | RCAMACHO | Approved | per Matt Ramber |
| 12/18/2018 | FIRE - FINAL | gdauria | Approved | Completed |
| 12/18/2018 | RIGHT OF WAY - FINAL | cfarren | Approved | wing and sidewalk work is complete and in spec - they will also get a new lid for one of the boxes in the same area as it is warped - |
| 12/18/2018 | OUTDOOR LIGHTING FINAL | RCAMACHO | Approved | |
| 12/18/2018 | ELECTRIC - FINAL | RCAMACHO | Approved | |
| 12/18/2018 | FRAMING | RCAMACHO | Approved | |
| 12/20/2018 | PLUMBING - BACK WATER VALVE | JGARCIA | Approved | APPROOVED PER BUILDING FINAL |
| 12/20/2018 | ZONING - FINAL | RSALDAT | Approved | Zoning Final approved. |
| 12/20/2018 | BUILDING - FINAL | JGARCIA | Approved | Fire and Engineering Finals confirmed |
| 12/20/2018 | PLUMBING - FINAL | JGARCIA | Approved | PCRWRD Approval and Water report received 12.19.18 |
| 12/20/2018 | MECHANICAL - FINAL | JGARCIA | Approved | AIR BALANCE REPORT RECIEVED 12.19.18 |
| 12/20/2018 | NPPO - FINAL | BBENEDON | Approved | |
| 12/20/2018 | SIGN - FINAL | BBENEDON | Approved | |
| 12/20/2018 | LANDSCAPE - FINAL | BBENEDON | Approved | |
| 12/20/2018 | ENGINEERING - FINAL | BBENEDON | Approved | OK for CofO |