Permit: T16CM08564
Permit Details
Apply Date:
11/14/2016
Applicant:
TOM, RICHARD FE
Description:
ANIMAL WELFARE CENTER
Architects:
- TOM, RICHARD FE
Contractors:
- DIVERSIFIED DESIGN AND CONSTRUCT
Permit Reviews
Permit Number - T16CM08564
Permit Status: C of o
Permit Description: ANIMAL WELFARE CENTER
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/18/2017 | RESUBMITTAL - TI ALL | 02/21/2017 | COMPLETED |
02/23/2017 | RESUBMITTAL | 03/03/2017 | COMPLETED |
04/25/2017 | REVISION - - 1ST | 04/26/2017 | COMPLETED |
06/20/2017 | REVISION - - 2ND | 06/21/2017 | COMPLETED |
06/21/2017 | REVISION - - 3RD | 06/21/2017 | COMPLETED |
11/14/2016 | PLANS OK TO SUBMIT - COMM | 11/15/2016 | COMPLETED |
11/15/2016 | COMMERCIAL - NEW | 01/09/2017 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T16CM08564
Permit Status: C of o
Permit Description: ANIMAL WELFARE CENTER
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
11/14/2016 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T16CM08564
Permit Description: ANIMAL WELFARE CENTER
Total Completed Inspections - 48
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/30/2017 | PLUMBING - SEWER HCS CONNECT | BSTEVENS | Approved | ADMIN HCS OK TO BACKFILL |
06/06/2017 | ELECTRIC - UFER | BSTEVENS | Approved | UFER AT MAINTENANCE BLD AND BLD C OK |
06/07/2017 | PLUMBING - YARD WTR LINE/TEST | BSTEVENS | Approved | |
06/12/2017 | STEM WALL/RETAINING WALL | BSTEVENS | Approved | MAINTENANCE BLD AND BLD 2 WEST OK TO GROUT |
06/20/2017 | EXCAVATION/LAYOUT REBAR & ZON | BSTEVENS | Approved | MAINTENANCE BLD. SLAB OK TO POUR. |
07/28/2017 | BUILDING PRE-SLAB | BSTEVENS | Approved | BUILDING 'D' OK TO POUR |
09/22/2017 | EXT METAL CLIPS/EXT SHEATHING | BSTEVENS | Approved | ADMIN WEST SHEAR OK TO COVER |
09/27/2017 | REINFORCED MASONRY PRE-GROUT | BSTEVENS | Approved | MAINTENANCE BUILDING TOP OF WALL OK |
10/26/2017 | SHEET ROCK NAILING | BSTEVENS | Approved | SHEARWALL SW3 IN BUILDING 'A' OK TO TAPE. ADMIN WEST ALL OK TO TAPE. |
10/26/2017 | FRAMING | BSTEVENS | Approved | SEE SHEETROCK NOTES |
11/16/2017 | BUILDING ABOVE CEILING | DQUINN | Approved | BLDG. D BATHROOMS AND XRAY OK TO COVER |
11/16/2017 | PLUMBING - ABOVE CEILING | DQUINN | Approved | BLDG. D BATHROOMS AND XRAY OK TO COVER. |
11/16/2017 | MECHANICAL - ABOVE CEILING | DQUINN | Approved | BLDG. D BATHROOMS AND XRAY CEILING OK TO COVER. |
11/16/2017 | MECHANICAL - ABOVE CEILING | DQUINN | Approved | |
11/27/2017 | ELECTRIC - UNDERGROUND | BSTEVENS | Approved | LIGHT POLE BASES ALL OK TO POUR |
11/30/2017 | ELECTRIC - INTERMEDIATE | BSTEVENS | Approved | IN WALL ELECTRIC IN MAINTENANCE BUILDING OK TO COVER |
12/01/2017 | ELECTRIC - PROGRESS | BSTEVENS | Approved | CLEAR ECO |
12/04/2017 | TEP CLEARANCE - AM | BSTEVENS | Approved | ECO |
12/06/2017 | PLUMBING - ROUGH, SOIL | BSTEVENS | Approved | HAIR INTERCEPTOR AT BUILDING 'B' OK TO BACKFILL |
12/07/2017 | PLUMBING - GAS PRESSURE TEST | BSTEVENS | Approved | FINAL GAS TEST BUILDING 'C' |
12/07/2017 | PLUMBING - INTERMEDIATE | BSTEVENS | Approved | WATER IN BUILDING 'C' OK |
12/21/2017 | ELECTRIC - ABOVE CEILING | BSTEVENS | Approved | BUILDING 'A' ONLY OK TO PLACE CEILING TILE |
01/05/2018 | GAS CLEARANCE | BSTEVENS | Approved | |
01/24/2018 | MECHANICAL - INTERMEDIATE | BSTEVENS | Approved | |
01/24/2018 | SITE - SEWER | BSTEVENS | Approved | |
01/24/2018 | PLUMBING - ROOF DRAINS | BSTEVENS | Approved | |
01/24/2018 | ELECTRIC - OUTDOOR LIGHTING | BSTEVENS | Approved | |
01/24/2018 | ELECTRIC - CONSTRUCTION POWER | BSTEVENS | Approved | |
01/24/2018 | ELECTRIC - TEMPORARY SERVICE | BSTEVENS | Approved | |
01/24/2018 | BUILDING - PROGRESS | BSTEVENS | Approved | |
01/24/2018 | FIREWALL/FIREBARRIER/FIRESTOP | BSTEVENS | Approved | |
01/24/2018 | U VALUE FOR WINDOW | BSTEVENS | Approved | |
01/24/2018 | STUCCO MESH | BSTEVENS | Approved | |
01/24/2018 | ROOF NAILING | BSTEVENS | Approved | |
02/26/2018 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETED FOR BUILDINGS 2 AND 3 (KENNELS) AND BUILDINGS 4, 5, AND 6 (MEDICAL, MAINTENANCE, AND BEHAVIOR) |
02/26/2018 | PLUMBING - FINAL | RSHERRY | Approved | REVIEW OF WATER CHLORINATION REPORT COMPLETE |
02/26/2018 | MECHANICAL - FINAL | BSTEVENS | Approved | PENDING APPROVAL OF CHLORINATION AND AIR BALANCE REPORTS |
02/26/2018 | PLUMBING - FINAL | BSTEVENS | Approved | PENDING APPROVAL OF CHLORINATION AND AIR BALANCE REPORTS |
02/26/2018 | ELECTRIC - FINAL | BSTEVENS | Approved | |
03/01/2018 | FIRE - ALARM FINAL | JPEELDAVIS | Approved | |
03/05/2018 | OUTDOOR LIGHTING FINAL | BSTEVENS | Approved | |
03/26/2018 | FIRE - FINAL | JPEELDAVIS | Approved | Gate does not fail in the open position. Per Chief Carsten we are going to allow this for the protection of the animals. Gate will need to be maintained with the battery back up at all times. Fire service contracts are in place. Approval for C of O. |
03/26/2018 | FIRE SPKLR - FINAL | JPEELDAVIS | Approved | Gate does not fail in the open position. Per Chief Carsten we are going to allow this for the protection of the animals. Gate will need to be maintained with the battery back up at all times. Fire service contracts are in place. Approval for C of O. |
03/27/2018 | CERTIFICATE OF OCCUPANCY | CLAYTON | Approved | |
03/27/2018 | ENGINEERING - FINAL | CLAYTON | Approved | WALK THE SITE WITH DIVERSIFIED TO SEE THAT ALL OF THE PREVIOUS WORK HAD BEEN COMPLETED. AT THIS TIME THERE IS ONLY MINOR WORK THAT NEEDS TO BE COMPLETE WITHIN THE INTERIOR. THIS WORK WILL BE COMPLETED IN THE NEXT 2 DAYS, AND IT CONSIST OF MAINLY INSTALLATION OF SOD AND SURFACE TREATMENTS. |
03/27/2018 | CERTIFICATE OF OCCUPANCY | BSTEVENS | Approved | ALL WORK ON THE BUILDING IS COMPLETED AND APPROVED. THERE ARE SOME MINOR ASPECTS OF THE DEVELOPMENT PACKAGE THAT WILL BE COMPLETED WITHIN TWO WEEKS. BASED ON THESE FACTS, I RECOMMEND APPROVAL OF CERTIFICATE OF OCCUPANCY. |
03/27/2018 | BUILDING - FINAL | BSTEVENS | Approved | ALL WORK ON THE BUILDING IS COMPLETED AND APPROVED. THERE ARE SOME MINOR ASPECTS OF THE DEVELOPMENT PACKAGE THAT WILL BE COMPLETED WITHIN TWO WEEKS. BASED ON THESE FACTS, I RECOMMEND APPROVAL OF CERTIFICATE OF OCCUPANCY. |
03/27/2018 | ENGINEERING - FINAL | DROBERTS | Approved | WALK THE SITE WITH DIVERSIFIED TO SEE THAT ALL OF THE PREVIOUS WORK HAD BEEN COMPLETED. AT THIS TIME THERE IS ONLY MINOR WORK THAT NEEDS TO BE COMPLETE WITHIN THE INTERIOR. THIS WORK WILL BE COMPLETED IN THE NEXT 2 DAYS, AND IT CONSIST OF MAINLY INSTALLATION OF SOD AND SURFACE TREATMENTS. |