Permit: T16CM01050
Permit Details
Apply Date:
02/12/2016
Applicant:
ALBERTO NAVARRO
Description:
HALL/RESTAURANT
Contractors:
- LA CIMA CONSTRUCTION COMPANY L L C
Permit Reviews
Permit Number - T16CM01050
Permit Status: C of o
Permit Description: HALL/RESTAURANT
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/12/2016 | PLANS OK TO SUBMIT - COMM | 02/12/2016 | COMPLETED |
| 03/17/2016 | 3RD PARTY REVIEW - COMMERCIAL | 03/17/2016 | COMPLETED |
| 03/17/2016 | POST 3RD PARTY REVIEW | 03/18/2016 | COMPLETED |
| 06/20/2016 | 3RD PARTY REVIEW - REVISION/OTHER | 06/24/2016 | COMPLETED |
| 07/29/2016 | REVISION - - 1ST | 10/12/2016 | COMPLETED |
| 10/12/2016 | 3RD PARTY REVIEW - REVISION/OTHER | 10/14/2016 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T16CM01050
Permit Status: C of o
Permit Description: HALL/RESTAURANT
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 02/12/2016 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T16CM01050
Permit Description: HALL/RESTAURANT
Total Completed Inspections - 29
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/31/2016 | STEM WALL/RETAINING WALL | MRAMBER | Approved | IVRS - Inspection :* |
| 04/12/2016 | EXCAVATION/LAYOUT REBAR & ZON | DROBERTS | Approved | LOOKED AT THE FOOTER ON THE SOUTH EASTER COURNER OF THE NEW ADDITION, THE CREW WILL BE POURING THIS PORTION OF THE WORK LATER THIS MORNING. |
| 07/21/2016 | BUILDING PRE-SLAB | ramber | Approved | all ok except doweling at existing slab |
| 07/21/2016 | BUILDING PRE-SLAB | MRAMBER | Approved | IVRS - Inspection :* |
| 07/26/2016 | REINFORCED MASONRY PRE-GROUT | ESTEVEN1 | Approved | IVRS - Inspection :* |
| 08/02/2016 | ROOF NAILING | RCAMACHO | Approved | IVRS - Inspection :* |
| 08/02/2016 | FRAMING | RCAMACHO | Approved | IVRS - Inspection :* |
| 08/29/2016 | ELECTRIC - INTERMEDIATE | RCAMACHO | Approved | EXCEPT CIRCUIT 34 D EXIT SIGNS AND NOTE 12 110 OUTLET ON ROOF |
| 08/29/2016 | ELECTRIC - INTERMEDIATE | RCAMACHO | Approved | IVRS - Inspection :* |
| 09/07/2016 | ELECTRIC - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
| 10/27/2016 | BUILDING - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 11/08/2016 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 11/14/2016 | ENGINEERING - FINAL | RLEDONNE | Approved | GC NOT ON SITE MET WITH OWNER WENT OVER SITE . THEY NEED TO POVIDE REVIONS FOR ALL CHAGES TO AP PLANS. |
| 12/02/2016 | SHEET ROCK NAILING | ESTEVEN1 | Approved | APPROVED. CEILING |
| 03/16/2017 | BUILDING ABOVE CEILING | mramber1 | Approved | |
| 03/16/2017 | U VALUE FOR WINDOW | mramber1 | Approved | |
| 03/16/2017 | MECHANICAL - ABOVE CEILING | mramber1 | Approved | |
| 05/05/2017 | FIRE SPKLR - UG, PIPING, HYDRO | JPEEL_DAVIS | Approved | APPROVED ON T16BU01176 |
| 05/05/2017 | FIRE SPKLR - UG PIPING FLUSH | JPEEL_DAVIS | Approved | APPROVED ON T16BU01176 |
| 05/05/2017 | FIRE SPKLR - OH PIPING & HYDRO | JPEEL_DAVIS | Approved | APPROVED ON T16BU01176 |
| 05/05/2017 | FIRE SPKLR - FINAL | JPEEL_DAVIS | Approved | APPROVED ON T16BU01176 |
| 05/19/2017 | MECHANICAL - FINAL | NORTH | Approved | PARTIAL FINAL PENDING ENGINEERING FINAL/ |
| 05/19/2017 | ELECTRIC - FINAL | NORTH | Approved | |
| 10/18/2017 | NPPO - FINAL | RDLD | Approved | |
| 10/18/2017 | SIGN - FINAL | RDLD | Approved | |
| 10/18/2017 | LANDSCAPE - FINAL | RDLD | Approved | |
| 12/08/2017 | FIRE - ALARM FINAL | GDAURIA | Approved | APPROVED ON T16FC00349 |
| 12/18/2017 | FIRE - FINAL | GDAURIA | Approved | APPROVED ON T16FC00349 |
| 03/06/2018 | RIGHT OF WAY - FINAL | CF/IM | Approved |