Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T15CM08230
Permit Details
Apply Date:
11/23/2015
Applicant:
N/A
Description:
TI; AIRPORT UPGRADES
Contractors:
- SUNDT CONSTRUCTION INC
Permit Reviews
Permit Number - T15CM08230
Permit Status: L of c
Permit Description: TI; AIRPORT UPGRADES
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/02/2016 | COMMERCIAL - TI | 03/29/2016 | COMPLETED |
03/29/2016 | RESUBMITTAL | 04/28/2016 | COMPLETED |
04/28/2016 | RESUBMITTAL | 05/17/2016 | COMPLETED |
11/23/2015 | PLANS OK TO SUBMIT - COMM | 02/02/2016 | COMPLETED |
12/19/2016 | REVISION - - 1ST | 12/19/2016 | COMPLETED |
12/19/2016 | REVISION - - 1ST | 04/23/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T15CM08230
Permit Status: L of c
Permit Description: TI; AIRPORT UPGRADES
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
11/23/2015 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T15CM08230
Permit Description: TI; AIRPORT UPGRADES
Total Completed Inspections - 42
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/11/2016 | PLUMBING - ROOF DRAINS | MRAMBER | Approved | IVRS - Inspection :* |
11/18/2016 | ELECTRIC - PROGRESS | MRAMBER | Approved | IVRS - Inspection :* |
11/22/2016 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | TSA offices ok to occupy |
11/22/2016 | ELECTRIC - ABOVE CEILING | MRAMBER | Approved | TSA offices ok to occupy |
11/22/2016 | BUILDING - PROGRESS | MRAMBER | Approved | TSA offices ok to occupy |
11/22/2016 | FIRE SPKLR - OH PIPING & HYDRO | jvincent | Approved | PA, OH, TSA west offices. |
11/29/2016 | BUILDING ABOVE CEILING | ESTEVEN1 | Approved | TSA OFFICES(2) BEHIND SOUTHWEST AIRLINES |
12/07/2016 | MECHANICAL - HYDRONIC PIPING | mramber1 | Approved | L2F and L2D check point "a" hydro test ok , ok to insulate |
12/08/2016 | PLUMBING - ROUGH, SOIL | mramber1 | Approved | L-2F dom. and DWV ok |
12/15/2016 | ELECTRIC - INTERMEDIATE | mramber1 | Approved | TSA breakroom ok |
12/15/2016 | FRAMING | mramber1 | Approved | TSA breakroom ok |
12/15/2016 | FIREWALL/FIREBARRIER/FIRESTOP | mramber1 | Approved | check point B ok |
12/21/2016 | SHEET ROCK NAILING | MRAMBER | Approved | IVRS - Inspection :* |
09/26/2017 | ELECTRIC - CONSTRUCTION POWER | mramber1 | Approved | |
10/19/2017 | PLUMBING - INTERMEDIATE | mramber1 | Approved | |
10/27/2017 | TEP CLEARANCE - AM | MRAMBER | Approved | INCR |
11/06/2017 | PLUMBING - ABOVE CEILING | mramber1 | Approved | old fly bar area |
11/06/2017 | STUCCO MESH | mramber1 | Approved | |
10/29/2018 | FIRE SPKLR - FINAL | JENNIFER PEE | Approved | PER JENNIFER PEEL-DAVIS |
10/29/2018 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | |
10/29/2018 | PLUMBING - PROGRESS | MRAMBER | Approved | |
10/29/2018 | PLUMBING - GAS PRESSURE TEST | MRAMBER | Approved | |
10/29/2018 | OUTDOOR LIGHTING FINAL | MRAMBER | Approved | |
10/29/2018 | ELECTRIC - FINAL | MRAMBER | Approved | |
10/29/2018 | ELECTRIC - OUTDOOR LIGHTING | MRAMBER | Approved | |
10/29/2018 | ELECTRIC - SERVICE UPGRADE | MRAMBER | Approved | |
10/29/2018 | ELECTRIC - TEMP POWER FOR TEST | MRAMBER | Approved | |
10/29/2018 | ELECTRIC - TEMPORARY SERVICE | MRAMBER | Approved | |
10/29/2018 | ELECTRIC - UNDERGROUND | MRAMBER | Approved | |
10/29/2018 | ELECTRIC - UFER | MRAMBER | Approved | |
10/29/2018 | U VALUE FOR WINDOW | MRAMBER | Approved | |
10/29/2018 | EXT METAL CLIPS/EXT SHEATHING | MRAMBER | Approved | |
10/29/2018 | REINFORCED MASONRY PRE-GROUT | MRAMBER | Approved | |
10/29/2018 | BUILDING PRE-SLAB | MRAMBER | Approved | |
10/29/2018 | STEM WALL/RETAINING WALL | MRAMBER | Approved | |
10/29/2018 | EXCAVATION/LAYOUT REBAR & ZON | MRAMBER | Approved | |
10/29/2018 | ENGINEERING - FINAL | BBENEDON | Approved | |
11/05/2018 | FIRE - FINAL | JPEELDAVIS | Approved | |
12/03/2018 | FIRE - ALARM FINAL | JPEELDAVIS | Approved | |
12/03/2018 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETED |
12/03/2018 | PLUMBING - FINAL | RSHERRY | Approved | REVIEW OF WATER DISINFECTION REPORT COMPLETED |
12/04/2018 | BUILDING - FINAL | MRAMBER | Approved | fire final APPROVED,plumbing final APPROVED, mechanical finalAPPROVED, provided all certs and docs. |