Inspection Status: Approved
Inspection History: MECHANICAL - HYDRONIC PIPING
Permit Number - T15CM08230
Inspection Description - MECHANICAL - HYDRONIC PIPING
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/29/2018 | MECHANICAL - HYDRONIC PIPING | Approved | ||
05/15/2017 | MECHANICAL - HYDRONIC PIPING | Partial Approval | TSA training room ok to tie in at existing | |
05/08/2017 | MECHANICAL - HYDRONIC PIPING | Partial Approval | AHU-4, HWS&R from AH to VAVS ok | |
02/23/2017 | MECHANICAL - HYDRONIC PIPING | Partial Approval | 1- hydro completed at check point "A" 2- CW at AH-4 ok on test |
|
12/07/2016 | MECHANICAL - HYDRONIC PIPING | Partial Approval | L2F and L2D check point "a" hydro test ok , ok to insulate | |
11/22/2016 | MECHANICAL - HYDRONIC PIPING | Partial Approval | TSA offices ok to occupy | |
10/27/2016 | MECHANICAL - HYDRONIC PIPING | Partial Approval | IVRS - Inspection :* | |
10/27/2016 | MECHANICAL - HYDRONIC PIPING | Partial Approval | AHU-3 hydro ok | |
10/21/2016 | MECHANICAL - HYDRONIC PIPING | Partial Approval | IVRS - Inspection :* | |
10/21/2016 | MECHANICAL - HYDRONIC PIPING | Partial Approval | concourse 'B'- 4 vav boxes hydro ok, ok to insulate back to AHU | |
10/17/2016 | MECHANICAL - HYDRONIC PIPING | Partial Approval | IVRS - Inspection :* | |
09/28/2016 | MECHANICAL - HYDRONIC PIPING | Partial Approval | L2A TO L2E- ISOLATION VALVES TO BRANCH INCLUDING VAV's. | |
09/16/2016 | MECHANICAL - HYDRONIC PIPING | Partial Approval | L2H TO L2H MONOCOAT INSTALL ABOVE CEILING, TICKET AREA. | |
09/13/2016 | MECHANICAL - HYDRONIC PIPING | Partial Approval | IVRS - Inspection :* | |
09/13/2016 | MECHANICAL - HYDRONIC PIPING | Partial Approval | 1-2- 2.5" hhw to L2H existing to L2D ok on hydro test 2-existing hangers and supports require monocoat to be replaced |
|
08/15/2016 | MECHANICAL - HYDRONIC PIPING | Partial Approval | IVRS - Inspection :* | |
08/15/2016 | MECHANICAL - HYDRONIC PIPING | Partial Approval | hydro test ok main AA tie in to existing to G.L. 108 , no branch test at this time | |
07/29/2016 | MECHANICAL - HYDRONIC PIPING | Partial Approval | IVRS - Inspection :* |