Permit: T15CM08230

Parcel: 140420120


Addresses:

7005 S PLUMER AV


Inspection Status: Approved

Inspection History: MECHANICAL - HYDRONIC PIPING

Permit Number - T15CM08230

Inspection Description - MECHANICAL - HYDRONIC PIPING

Inspection Status - Approved

Date Description Inspector Results Comments
10/29/2018 MECHANICAL - HYDRONIC PIPING Approved
05/15/2017 MECHANICAL - HYDRONIC PIPING Partial Approval TSA training room ok to tie in at existing
05/08/2017 MECHANICAL - HYDRONIC PIPING Partial Approval AHU-4, HWS&R from AH to VAVS ok
02/23/2017 MECHANICAL - HYDRONIC PIPING Partial Approval 1- hydro completed at check point "A"
2- CW at AH-4 ok on test
12/07/2016 MECHANICAL - HYDRONIC PIPING Partial Approval L2F and L2D check point "a" hydro test ok , ok to insulate
11/22/2016 MECHANICAL - HYDRONIC PIPING Partial Approval TSA offices ok to occupy
10/27/2016 MECHANICAL - HYDRONIC PIPING Partial Approval IVRS - Inspection :*
10/27/2016 MECHANICAL - HYDRONIC PIPING Partial Approval AHU-3 hydro ok
10/21/2016 MECHANICAL - HYDRONIC PIPING Partial Approval IVRS - Inspection :*
10/21/2016 MECHANICAL - HYDRONIC PIPING Partial Approval concourse 'B'- 4 vav boxes hydro ok, ok to insulate back to AHU
10/17/2016 MECHANICAL - HYDRONIC PIPING Partial Approval IVRS - Inspection :*
09/28/2016 MECHANICAL - HYDRONIC PIPING Partial Approval L2A TO L2E- ISOLATION VALVES TO BRANCH INCLUDING VAV's.
09/16/2016 MECHANICAL - HYDRONIC PIPING Partial Approval L2H TO L2H MONOCOAT INSTALL ABOVE CEILING, TICKET AREA.
09/13/2016 MECHANICAL - HYDRONIC PIPING Partial Approval IVRS - Inspection :*
09/13/2016 MECHANICAL - HYDRONIC PIPING Partial Approval 1-2- 2.5" hhw to L2H existing to L2D ok on hydro test
2-existing hangers and supports require monocoat to be replaced
08/15/2016 MECHANICAL - HYDRONIC PIPING Partial Approval IVRS - Inspection :*
08/15/2016 MECHANICAL - HYDRONIC PIPING Partial Approval hydro test ok main AA tie in to existing to G.L. 108 , no branch test at this time
07/29/2016 MECHANICAL - HYDRONIC PIPING Partial Approval IVRS - Inspection :*