Permit: T13CM06642
Permit Details
Apply Date:
10/31/2013
Applicant:
STICKLEY DESIGN GROUP
Description:
TI: RETAIL
Architects:
- STICKLEY DESIGN GROUP
Contractors:
- CHESTNUT CONSTRUCTION CORPORATIO
Permit Reviews
Permit Number - T13CM06642
Permit Status: C of o
Permit Description: TI: RETAIL
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
10/31/2013 | COMMERCIAL - TI | 11/01/2013 | COMPLETED |
11/08/2013 | REVISION - - 1ST | 11/08/2013 | ACTIVE |
Outstanding Activity Conditions
Permit Number - T13CM06642
Permit Status: C of o
Permit Description: TI: RETAIL
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
10/31/2013 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T13CM06642
Permit Description: TI: RETAIL
Total Completed Inspections - 26
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/12/2013 | ELECTRIC - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
11/12/2013 | FRAMING | JMILITEL | Approved | IVRS - Inspection :* |
11/13/2013 | SHEET ROCK NAILING | JMILITEL | Approved | OK TO TAPE & SHEETROCK BATHROOM |
11/13/2013 | PLUMBING - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
11/13/2013 | SHEET ROCK NAILING | JMILITEL | Approved | IVRS - Inspection :* |
11/22/2013 | BUILDING ABOVE CEILING | BBENEDON | Approved | IVRS - Inspection :* |
11/22/2013 | ELECTRIC - ABOVE CEILING | BBENEDON | Approved | IVRS - Inspection :* |
11/22/2013 | PLUMBING - PRE SLAB | BBENEDON | Approved | IVRS - Inspection :* |
11/25/2013 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | IVRS - Inspection :* |
11/25/2013 | MECHANICAL - ABOVE CEILING | BBENEDON | Approved | IVRS - Inspection :* |
11/25/2013 | PLUMBING - ABOVE CEILING | BBENEDON | Approved | IVRS - Inspection :* |
11/29/2013 | NPPO - FINAL | DROBERTS | Approved | |
11/29/2013 | SIGN - FINAL | DROBERTS | Approved | |
11/29/2013 | LANDSCAPE - FINAL | DROBERTS | Approved | |
11/29/2013 | ENGINEERING - FINAL | DROBERTS | Approved | |
11/29/2013 | FIRE SPKLR - FINAL | wmotto | Approved | |
11/29/2013 | RIGHT OF WAY - FINAL | TW | Approved | |
12/26/2013 | ELECTRIC - SERVICE UPGRADE | JMILITEL | Approved | IVRS - Inspection :* |
12/27/2013 | TEP CLEARANCE - AM | JMILITEL | Approved | ECO |
12/27/2013 | FIRE - FINAL | CSCHULTZ | Approved | 1. Need to keep rear exit corridor clear of all storage at all times - contractor clear all storage in corridor at time of inspection. 2. Slide bolt locks are not allowed on egress or exit door at any time - contractor remove slid bolt lock from corridor exit door. |
12/27/2013 | PLUMBING - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
12/27/2013 | ELECTRIC - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
12/31/2013 | MECHANICAL - INTERMEDIATE | BBENEDON | Approved | PER MECH FINAL - BBENEDON |
12/31/2013 | BUILDING - FINAL | BBENEDON | Approved | IVRS - Inspection :* |
12/31/2013 | MECHANICAL - FINAL | BBENEDON | Approved | IVRS - Inspection :* |
12/31/2013 | PLUMBING - PROGRESS | BBENEDON | Approved | IVRS - Inspection :* |