Permit: T13CM05791
Permit Details
Apply Date:
09/19/2013
Applicant:
RICHARD FE TOM
Description:
APARTMENTS
Contractors:
- SHEA CONNELLY DEVELOPMENT LLC
Permit Reviews
Permit Number - T13CM05791
Permit Status: C of o
Permit Description: APARTMENTS
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/10/2014 | REVISION - - 1ST | 03/11/2014 | COMPLETED |
| 04/20/2015 | REVISION - - 3RD | 04/21/2015 | COMPLETED |
| 06/05/2014 | WALK THRU - COMM | 06/05/2014 | COMPLETED |
| 06/05/2014 | REVISION - - 1ST | 06/11/2014 | COMPLETED |
| 07/14/2015 | REVISION - - 4TH | 12/18/2015 | COMPLETED |
| 09/19/2013 | PLANS OK TO SUBMIT - COMM | 09/20/2013 | COMPLETED |
| 09/23/2013 | COMMERCIAL - NEW | 10/24/2013 | COMPLETED |
| 10/24/2013 | RESUBMITTAL | 11/19/2013 | COMPLETED |
| 11/06/2014 | REVISION - - 1ST | 11/24/2014 | COMPLETED |
| 12/20/2013 | RESUBMITTAL | 03/10/2014 | COMPLETED |
| 12/21/2015 | REVISION - - 5TH | 12/21/2015 | COMPLETED |
| 12/30/2014 | REVISION - - 2ND | 01/05/2015 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T13CM05791
Permit Status: C of o
Permit Description: APARTMENTS
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 09/19/2013 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T13CM05791
Permit Description: APARTMENTS
Total Completed Inspections - 40
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/26/2014 | PLUMBING - ROUGH, SOIL | MRAMBER | Approved | IVRS - Inspection :* |
| 03/14/2014 | PLUMBING - PRE SLAB | MRAMBER | Approved | IVRS - Inspection :* |
| 03/14/2014 | ELECTRIC - UNDERGROUND | MRAMBER | Approved | IVRS - Inspection :* |
| 03/14/2014 | BUILDING PRE-SLAB | MRAMBER | Approved | IVRS - Inspection :* |
| 06/13/2014 | FIRE SPKLR - UG, PIPING, HYDRO | CBASALDU | Approved | |
| 06/16/2014 | PLUMBING - YARD WTR LINE/TEST | MRAMBER | Approved | IVRS - Inspection :* |
| 06/23/2014 | PLUMBING - SEWER HCS CONNECT | MRAMBER | Approved | IVRS - Inspection :* |
| 06/23/2014 | EXT METAL CLIPS/EXT SHEATHING | MRAMBER | Approved | IVRS - Inspection :* |
| 06/26/2014 | U VALUE FOR WINDOW | MRAMBER | Approved | IVRS - Inspection :* |
| 06/26/2014 | ROOF NAILING | MRAMBER | Approved | IVRS - Inspection :* |
| 07/17/2014 | STUCCO MESH | MRAMBER | Approved | IVRS - Inspection :* |
| 07/31/2014 | FRAMING | RCAMACHO | Approved | IVRS - Inspection :* MET WITH JOHN DELIVERED EMAIL ON CORRIDER WINDOWS FROM LEE RAY. SEE ATTACHED EMAIL |
| 08/28/2014 | FIRE SPKLR - OH PIPING & HYDRO | wmotto1 | Approved | |
| 08/28/2014 | FIRE SPKLR - UG PIPING FLUSH | wmotto1 | Approved | |
| 08/29/2014 | SITE - SEWER | MRAMBER | Approved | IVRS - Inspection :* |
| 08/29/2014 | PLUMBING - GAS PRESSURE TEST | MRAMBER | Approved | IVRS - Inspection :* |
| 08/29/2014 | STEM WALL/RETAINING WALL | MRAMBER | Approved | IVRS - Inspection :* |
| 08/29/2014 | EXCAVATION/LAYOUT REBAR & ZON | MRAMBER | Approved | IVRS - Inspection :* |
| 10/16/2014 | BUILDING - PROGRESS | MRAMBER | Approved | OK TO STOCK 1ST FLOOR |
| 10/16/2014 | BUILDING - PROGRESS | MRAMBER | Approved | IVRS - Inspection :* |
| 07/21/2015 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 07/21/2015 | PLUMBING - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
| 07/21/2015 | ELECTRIC - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
| 08/04/2015 | BUILDING ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
| 08/04/2015 | PLUMBING - PROGRESS | MRAMBER | Approved | IVRS - Inspection :* |
| 08/04/2015 | ELECTRIC - UFER | MRAMBER | Approved | IVRS - Inspection :* |
| 08/06/2015 | SHEET ROCK NAILING | MRAMBER | Approved | IVRS - Inspection :* |
| 09/23/2015 | FIRE - FINAL | CSCHULTZ | Approved | Had a meeting with contractor on site about F.D. key boxes where to install, advise them to install one by main front gate to clubhouse (facing park road) with keys to clubhouse and man gate to apartments install key box by access gate on north side next to apartments (facing Alvord rd.). Also advise them to install riser room signs on doors to riser in the clubhouse x2 and on riser room door for apartments and FDC sign over FDC's. Advise them to install fire lane signs on access road facing park rd. NEED FIRE ALARM FINAL T14BU00971 |
| 09/23/2015 | FIRE SPKLR - FINAL | CSCHULTZ | Approved | Had a meeting with contractor on site about F.D. key boxes where to install, advise them to install one by main front gate to clubhouse (facing park road) with keys to clubhouse and man gate to apartments install key box by access gate on north side next to apartments (facing Alvord rd.). Also advise them to install riser room signs on doors to riser in the clubhouse x2 and on riser room door for apartments and FDC sign over FDC's. Advise them to install fire lane signs on access road facing park rd. |
| 11/18/2015 | TEP CLEARANCE - AM | MRAMBER | Approved | TEC SENT 25 UNITS |
| 12/15/2015 | OUTDOOR LIGHTING FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 12/15/2015 | ELECTRIC - OUTDOOR LIGHTING | MRAMBER | Approved | IVRS - Inspection :* |
| 12/16/2015 | FIREWALL/FIREBARRIER/FIRESTOP | MRAMBER | Approved | IVRS - Inspection :* |
| 12/16/2015 | PLUMBING - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 12/16/2015 | ELECTRIC - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 12/30/2015 | BUILDING - FINAL | MRAMBER | Approved | 1. 1ST FLOOR T.C.O. OK FOR STOCKING OF FURN. AND SUPPLIES SEE C.O.T. B.O. FOR T.C.O. |
| 12/30/2015 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 12/30/2015 | PLUMBING - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 12/30/2015 | ELECTRIC - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 01/21/2016 | FIRE - ALARM FINAL | jvincent | Approved | approved by CB on 12/30/15 |