Permit: T13CM02142
Permit Details
Apply Date:
04/11/2013
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
RETAIL
Architects:
- GOLDSTEIN GENE
Contractors:
- RELIANCE COMMERCIAL CONSTRUCTION
Permit Reviews
Permit Number - T13CM02142
Permit Status: C of o
Permit Description: RETAIL
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/11/2013 | COMMERCIAL - TI | 04/18/2013 | COMPLETED |
04/18/2013 | OTHER | 04/18/2013 | COMPLETED |
04/19/2013 | WALK THRU - COMM | 04/19/2013 | COMPLETED |
04/24/2013 | OTHER | 05/23/2013 | COMPLETED |
07/11/2013 | REVISION - - 1ST | 08/27/2013 | COMPLETED |
08/27/2013 | REVISION - - 2ND | 08/28/2013 | COMPLETED |
08/28/2013 | REVISION - - 2ND | 08/28/2013 | COMPLETED |
08/28/2013 | REVISION - - 2ND | 08/28/2013 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T13CM02142
Permit Description: RETAIL
Total Completed Inspections - 32
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/24/2013 | PLUMBING - PRE SLAB | BBENEDON | Approved | IVRS - Inspection :* |
07/24/2013 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | IVRS - Inspection :* |
08/26/2013 | FRAMING | RMYERS | Approved | IVRS - Inspection :* |
08/29/2013 | SHEET ROCK NAILING | MRAMBER | Approved | IVRS - Inspection :* |
10/04/2013 | MECHANICAL - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
10/15/2013 | PLUMBING - YARD WTR LINE/TEST | RCAMACHO | Approved | IVRS - Inspection :* |
10/18/2013 | PLUMBING - GAS PRESSURE TEST | DSANTACR | Approved | APPROVED PER NOTES BY RAY CAMACHO 10/15/13 |
10/18/2013 | MECHANICAL - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* |
10/18/2013 | PLUMBING - GAS PRESSURE TEST | DSANTACR | Approved | IVRS - Inspection :* |
10/18/2013 | PLUMBING - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
10/18/2013 | BUILDING ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
10/24/2013 | FIRE SPKLR - FINAL | CSCHULTZ | Approved | |
10/25/2013 | PLUMBING - PROGRESS | DSANTACR | Approved | IVRS - Inspection :* |
10/25/2013 | ELECTRIC - OUTDOOR LIGHTING | DSANTACR | Approved | IVRS - Inspection :* |
10/25/2013 | ELECTRIC - PROGRESS | DSANTACR | Approved | IVRS - Inspection :* |
10/25/2013 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
11/01/2013 | PLUMBING - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
11/04/2013 | MECHANICAL - FINAL | DSANTACR | Approved | OK SMOKE DETECTOR/FIRE ALARM/ AC SHUTDOWN AS WITNESSED BY TFD, CARL SCHULTZ |
11/04/2013 | MECHANICAL - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
11/04/2013 | RIGHT OF WAY - FINAL | JC | Approved | |
11/04/2013 | FIRE - ALARM FINAL | CSCHULTZ | Approved | |
11/04/2013 | NPPO - FINAL | RLEDONNE | Approved | |
11/04/2013 | LANDSCAPE - FINAL | RLEDONNE | Approved | |
11/04/2013 | SIGN - FINAL | RLEDONNE | Approved | |
11/05/2013 | ENGINEERING - FINAL | RLEDONNE | Approved | |
11/21/2013 | ELECTRIC - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
11/21/2013 | FIRE - FINAL | wmotto | Approved | |
11/22/2013 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | |
11/22/2013 | ELECTRIC - UNDERGROUND | DSANTACR | Approved | |
11/22/2013 | ELECTRIC - UFER | DSANTACR | Approved | |
11/22/2013 | PLUMBING - INTERMEDIATE | LHANLY | Approved | |
11/22/2013 | BUILDING - FINAL | LHANLY | Approved |