Permit: T11CM02343
Permit Details
Apply Date:
07/26/2011
Applicant:
METRO PERMIT EXPRESS, INC *C
Description:
TI:OFFICE
Architects:
- MORROW, KEVIN THOMAS
Contractors:
- CHESTNUT CONSTRUCTION CORPORATIO
Permit Reviews
Permit Number - T11CM02343
Permit Status: C of o
Permit Description: TI:OFFICE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/22/2012 | REVISION - - 2ND | 02/22/2012 | COMPLETED |
07/26/2011 | PLANS OK TO SUBMIT - COMM | 07/26/2011 | COMPLETED |
07/26/2011 | COMMERCIAL - TI | 08/15/2011 | COMPLETED |
08/15/2011 | RESUBMITTAL | 08/22/2011 | COMPLETED |
08/22/2011 | RESUBMITTAL | 08/22/2011 | COMPLETED |
12/09/2011 | REVISION - - 1ST | 12/20/2011 | COMPLETED |
12/20/2011 | REVISION - - 1ST | 12/20/2011 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T11CM02343
Permit Status: C of o
Permit Description: TI:OFFICE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
07/26/2011 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T11CM02343
Permit Description: TI:OFFICE
Total Completed Inspections - 30
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/19/2011 | PLUMBING - ROUGH, SOIL | RRICH | Approved | IVRS - Inspection :* |
09/21/2011 | PLUMBING - PRE SLAB | RRICH | Approved | IVRS - Inspection :* |
09/27/2011 | ELECTRIC - UNDERGROUND | DSANTACR | Approved | IVRS - Inspection :* |
10/07/2011 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
10/17/2011 | BUILDING - PROGRESS | GDABBS | Approved | IVRS - Inspection :* 1) EXCAVATION AND REBAR AT GENERATOR PAD |
10/24/2011 | SHEET ROCK NAILING | MHENSON | Approved | |
10/25/2011 | FRAMING | MHENSON | Approved | |
10/25/2011 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* 1) OK EXCEPT CLEAN ROOM AREAS, UNISTRUT GRID NOT COMPLETE YET |
10/25/2011 | BUILDING ABOVE CEILING | MHENSON | Approved | IVRS - Inspection :* 1) SOUTH SIDE OF CHOIR LINK AREA LEFT |
10/25/2011 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
10/26/2011 | ELECTRIC - PROGRESS | DSANTACR | Approved | IVRS - Inspection :* 1) CONTRACTOR TO LOCK OUT/TAG OUT 2) ONLY AUTHORIZED PERSONS TO HAVE ACCESS TO EQUIPMENT |
10/27/2011 | FIRE SPKLR - FINAL | WMOTTO | Approved | |
10/27/2011 | RIGHT OF WAY - FINAL | MCASTRO | Approved | |
10/27/2011 | SIGN - FINAL | RLEDONNE | Approved | N/A TO THIS ACTIVITY |
10/27/2011 | TEP CLEARANCE - AM | JWEATHER | Approved | RECN CLEARED FOR #100, 150 (2 METERS) AND HOUSE PANEL PER D. SANTACRUZ |
10/28/2011 | NPPO - FINAL | RLEDONNE | Approved | NA TO THIS ACTIVITY. |
10/28/2011 | LANDSCAPE - FINAL | RLEDONNE | Approved | NA TO THIS ACTIVITY. |
10/28/2011 | ENGINEERING - FINAL | RLEDONNE | Approved | REMOVE ALL MATERIALS AND EQUIPMENT FROM OUT SIDE OF BUILDING. |
10/31/2011 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* 1) CLEAN ROOM AREA IS GOING TO BE IN 2ND PHASE, ALL OTHER AREAS COMPLETED 2) BALANCE REPORT (PARTIAL) INDICATES ALL EXH. AND O.S.A. OK, NO OTHER LIFE SAFETY ISSUES OBSERVED, SEE BLDG INSPECTOR FOR TEM C OF O |
10/31/2011 | FIRE - FINAL | DSIWARSKI | Approved | 1. Fire sprinkler annunal inspection required. 2. Fire Marshal is ok to approve a Temp CofO per building inspector.. |
10/31/2011 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
11/04/2011 | PLUMBING - ABOVE CEILING | RMYERS | Approved | IVRS - Inspection :* 1) CLOSET FLANGES OK |
11/04/2011 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection :* |
11/16/2011 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* 1) OK PARTIAL FINAL FOR #149,150,166,167 RESTROOM AND SHOWER |
11/16/2011 | PLUMBING - FINAL | RRICH | Approved | IVRS - Inspection :* 1) ALL AREAS OK, EXCEPT CLEAN ROOM |
11/17/2011 | BUILDING - FINAL | MHENSON | Approved | IVRS - Inspection :* 1) NEW RESTROOMS OK |
12/28/2011 | EXCAVATION/LAYOUT REBAR & ZON | MHENSON | Approved | |
02/09/2012 | MECHANICAL - HYDRONIC PIPING | MRAMBER | Approved | IVRS - Inspection :* |
02/24/2012 | PLUMBING - PROGRESS | RMYERS | Approved | |
02/24/2012 | SITE - SEWER | RMYERS | Approved |