Permit: T11CM01588
Permit Details
Apply Date:
05/24/2011
Applicant:
KEVIN HALL
Description:
ADDITION: TO EXISTING COX EQUIPMENT BUILDING
Contractors:
- MARATHON RESOURCES INC ,
Permit Reviews
Permit Number - T11CM01588
Permit Status: C of o
Permit Description: ADDITION: TO EXISTING COX EQUIPMENT BUILDING
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/24/2011 | PLANS OK TO SUBMIT - SITE | 05/24/2011 | COMPLETED |
| 05/24/2011 | SITE | 07/18/2011 | COMPLETED |
| 07/18/2011 | RESUBMITTAL - SITE | 08/15/2011 | COMPLETED |
| 08/10/2011 | PLANS OK TO SUBMIT - COMM | 08/10/2011 | COMPLETED |
| 08/10/2011 | COMMERCIAL - NEW | 08/29/2011 | COMPLETED |
| 08/15/2011 | RESUBMITTAL - SITE | 08/26/2011 | COMPLETED |
| 08/26/2011 | REVISION - SITE | 09/22/2011 | COMPLETED |
| 08/30/2011 | RESUBMITTAL - TI ALL | 09/13/2011 | COMPLETED |
| 09/13/2011 | RESUBMITTAL | 09/22/2011 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T11CM01588
Permit Status: C of o
Permit Description: ADDITION: TO EXISTING COX EQUIPMENT BUILDING
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 05/24/2011 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T11CM01588
Permit Description: ADDITION: TO EXISTING COX EQUIPMENT BUILDING
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/27/2011 | STEM WALL/RETAINING WALL | GDABBS | Approved | IVRS - Inspection :* |
| 11/01/2011 | EXCAVATION/LAYOUT REBAR & ZON | GDABBS | Approved | IVRS - Inspection :* |
| 11/01/2011 | BUILDING PRE-SLAB | GDABBS | Approved | IVRS - Inspection :* |
| 11/23/2011 | PLUMBING - PROGRESS | RRICH | Approved | (2) 1" CONDENSATES FROM 10' INTERIOR TO DRYWELLS NORTH SIDE. (2) 1 1/2" CONDENSATES STUB UPS NORTH EXTERIOR TO DRYWELL PER PLAN. |
| 12/28/2011 | SITE - SEWER | BBENEDON | Approved | IVRS - Inspection :* |
| 12/29/2011 | ELECTRIC - INTERMEDIATE | RMORENO | Approved | IVRS - Inspection :* 1) PANELS FOR POWER ENERGIZED ALL OK |
| 12/29/2011 | ELECTRIC - ABOVE CEILING | RMORENO | Approved | IVRS - Inspection :* |
| 02/03/2012 | ELECTRIC - FINAL | RMORENO | Approved | IVRS - Inspection :* |
| 02/29/2012 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* |
| 02/29/2012 | PLUMBING - FINAL | BBENEDON | Approved | IVRS - Inspection :* |
| 02/29/2012 | PLUMBING - YARD WTR LINE/TEST | BBENEDON | Approved | IVRS - Inspection :* |
| 02/29/2012 | PLUMBING - PRE SLAB | BBENEDON | Approved | IVRS - Inspection :* |
| 02/29/2012 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | IVRS - Inspection :* |
| 03/02/2012 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
| 03/02/2012 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
| 03/05/2012 | LANDSCAPE - FINAL | DROBERTS | Approved | |
| 03/05/2012 | U VALUE FOR WINDOW | JBURGE | Approved | |
| 03/05/2012 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* |
| 03/05/2012 | BUILDING - PROGRESS | JBURGE | Approved | IVRS - Inspection :* |
| 03/05/2012 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* |
| 03/05/2012 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
| 03/05/2012 | FRAMING | JBURGE | Approved | IVRS - Inspection :* |
| 03/08/2012 | FIRE SPKLR - FINAL | WMOTTO | Approved |