Permit: T10CM02634
Permit Details
Apply Date:
09/21/2010
Applicant:
N/A
Description:
TRANSMISSION SHOP
Architects:
- CATALANO, VINCENT VICTOR
Contractors:
- SILVER WEST INC ,
Permit Reviews
Permit Number - T10CM02634
Permit Status: C of o
Permit Description: TRANSMISSION SHOP
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/06/2012 | REVISION - - 3RD | 02/06/2012 | ACTIVE |
| 04/04/2011 | RESUBMITTAL - SITE ALL | 04/28/2011 | COMPLETED |
| 05/02/2011 | RESUBMITTAL - SITE ALL | 05/26/2011 | COMPLETED |
| 05/31/2011 | RESUBMITTAL - SITE | 06/02/2011 | COMPLETED |
| 06/02/2011 | RESUBMITTAL - SITE | 06/03/2011 | COMPLETED |
| 06/06/2011 | REVISION - - 1ST | 11/18/2011 | COMPLETED |
| 09/21/2010 | PLANS OK TO SUBMIT - SITE | 09/21/2010 | COMPLETED |
| 09/22/2010 | SITE | 02/09/2011 | COMPLETED |
| 11/18/2011 | REVISION - - 2ND | 12/30/2011 | COMPLETED |
| 12/30/2011 | REVISION - - 2ND | 12/30/2011 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T10CM02634
Permit Status: C of o
Permit Description: TRANSMISSION SHOP
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 09/21/2010 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T10CM02634
Permit Description: TRANSMISSION SHOP
Total Completed Inspections - 11
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/27/2011 | RIGHT OF WAY - FINAL | MCASTRO | Approved | |
| 12/12/2011 | NPPO - FINAL | RLEDONNE | Approved | |
| 12/16/2011 | LANDSCAPE - FINAL | RLEDONNE | Approved | |
| 12/29/2011 | ENGINEERING - FINAL | DROBERTS | Approved | MET ON-SITE WITH THE OWNER, HE HAS ASKED TO CHANGE SOME OF THE THINGS ON THE APPROVED PLANS. I HAVE ASKED THAT HE GO DOWNTOWN AND SEE THE REVIEWERS AND SEE IF HIS REQUEST ARE EVEN POSSIBLE TO MAKE ON THIS SITE. WE LOOKED AT THE MOVEMENT OF THE BOLLARDS ALONG THE EAST SIDE OF THE PROJECT AND IN AN AREA EAST OF THE BUILDING ADJACENT TO THE PEDESTRIAN WALKWAY. |
| 01/05/2012 | ZONING - FINAL | RLEDONNE | Approved | |
| 01/17/2012 | EXCAVATION/LAYOUT REBAR & ZON | AQUIROZ | Approved | IVRS - Inspection :* |
| 01/25/2012 | BUILDING - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |
| 01/25/2012 | STEM WALL/RETAINING WALL | AQUIROZ | Approved | IVRS - Inspection :* |
| 01/25/2012 | BUILDING PRE-SLAB | AQUIROZ | Approved | IVRS - Inspection :* |
| 01/26/2012 | FRAMING | AQUIROZ | Approved | |
| 02/03/2012 | CERTIFICATE OF OCCUPANCY | AQUIROZ | Approved |