Permit: T10CM01889
Permit Details
Apply Date:
07/09/2010
Applicant:
N/A
Description:
TUSD SCHOOL
Contractors:
- SUNDT CONSTRUCTION
- TUCSON UNIFIED SCHOOL DIST #1 ** APA
Permit Reviews
Permit Number - T10CM01889
Permit Status: C of o
Permit Description: TUSD SCHOOL
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/14/2011 | 3RD PARTY REVIEW - REVISION/OTHER | 05/24/2011 | COMPLETED |
| 03/21/2011 | 3RD PARTY REVIEW - REVISION/OTHER-2ND | 03/21/2011 | COMPLETED |
| 05/17/2011 | 3RD PARTY REVIEW - REVISION/OTHER-2ND | 05/24/2011 | COMPLETED |
| 07/14/2010 | 3RD PARTY REVIEW-COMMERCIAL | 08/24/2010 | COMPLETED |
| 08/24/2010 | POST 3RD PARTY REVIEW | 09/14/2010 | COMPLETED |
| 09/14/2010 | POST 3RD PARTY REVIEW | 10/12/2010 | COMPLETED |
| 10/12/2010 | RESUBMITTAL | 10/15/2010 | COMPLETED |
| 12/07/2011 | 3RD PARTY REVIEW - REVISION/OTHER | 12/07/2011 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T10CM01889
Permit Status: C of o
Permit Description: TUSD SCHOOL
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 07/09/2010 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T10CM01889
Permit Description: TUSD SCHOOL
Total Completed Inspections - 44
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/22/2010 | ELECTRIC - UFER | RHOLLAND | Approved | IVRS - Inspection :* 1) OK #4 TO REBAR AND 20' IN TRENCH |
| 12/07/2010 | PLUMBING - ROUGH, SOIL | RLEDONNE | Approved | IVRS - Inspection :* 1) INSIDE BLDG SLAB ROUGH SOIL OK 2) CLEANOUT TEST THRU |
| 12/08/2010 | STEM WALL/RETAINING WALL | MHENSON | Approved | IVRS - Inspection :* 1) ALL EXCEPT ROOM 618 WEST WALL, 637 EAST WALL SOUTH 1/2 62" NORTH WALL, 622 SOUTH WALL EAST 1/2, 619 SOUTH AND WEST WALL |
| 12/09/2010 | EXCAVATION/LAYOUT REBAR & ZON | MHENSON | Approved | IVRS - Inspection :* 1) SPECIAL INSPECTED EPOXY ONLY |
| 12/10/2010 | FIRE SPKLR - UG, PIPING, HYDRO | LTHOMAS | Approved | |
| 12/17/2010 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* 1) RISERS BETWEEN CWS/R AND HWS/R BLDG 6 & 5 TEST OK-OK TO INSULATE 2) CWS/R AND HWS/R RISERS BETWEEN BLDGS 6 & 7 PRESS TEST OK, OK TO INSULATE FITTINGS AND BACKFILL AFTER PHOTOS ONLY |
| 12/29/2010 | ELECTRIC - UNDERGROUND | RHOLLAND | Approved | IVRS - Inspection :* 1) OK 42 FLOOR BOXES |
| 01/04/2011 | PLUMBING - PRE SLAB | RLEDONNE | Approved | IVRS - Inspection :* |
| 01/11/2011 | BUILDING PRE-SLAB | MHENSON | Approved | IVRS - Inspection :* 1) INSTALL CORNER BARS ? ? ? |
| 01/31/2011 | PLUMBING - YARD WTR LINE/TEST | RLEDONNE | Approved | IVRS - Inspection :* |
| 02/18/2011 | FIRE SPKLR - UG PIPING FLUSH | LTHOMAS | Approved | |
| 05/04/2011 | REINFORCED MASONRY PRE-GROUT | MHENSON | Approved | IVRS - Inspection :* |
| 05/13/2011 | PLUMBING - BACK WATER VALVE | RRICH | Approved | IVRS - Inspection :* |
| 07/07/2011 | EXT METAL CLIPS/EXT SHEATHING | MHENSON | Approved | IVRS - Inspection :* |
| 07/26/2011 | SITE - SEWER | RRICH | Approved | IVRS - Inspection :* |
| 07/26/2011 | PLUMBING - SEWER HCS CONNECT | RRICH | Approved | IVRS - Inspection :* |
| 07/27/2011 | ROOF NAILING | MHENSON | Approved | IVRS - Inspection :* |
| 08/12/2011 | FIRE SPKLR - OH PIPING & HYDRO | DSIWARSKI | Approved | 5030 Approved by AHJ State Fire Marshal G. Chavez. |
| 08/22/2011 | NPPO - FINAL | RLEDONNE | Approved | NA TO THIS ACTIVITY. |
| 08/22/2011 | STUCCO MESH | JBURGE | Approved | IVRS - Inspection :* |
| 08/23/2011 | RIGHT OF WAY - FINAL | MCASTRO | Approved | |
| 08/23/2011 | SIGN - FINAL | RLEDONNE | Approved | NA TO THIS ACTIVITY. |
| 08/24/2011 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* |
| 08/29/2011 | FRAMING | MHENSON | Approved | IVRS - Inspection :* |
| 09/06/2011 | SHEET ROCK NAILING | MHENSON | Approved | IVRS - Inspection :* |
| 09/26/2011 | PLUMBING - ABOVE CEILING | RRICH | Approved | IVRS - Inspection :* |
| 09/29/2011 | BUILDING - PROGRESS | MHENSON | Approved | IVRS - Inspection :* |
| 10/07/2011 | MECHANICAL - HYDRONIC PIPING | MRAMBER | Approved | IVRS - Inspection :* 1) DUCT ABOVE CEILING OK TO COVER 2) HYDRO ABOVE CEILING OK TO COVER |
| 10/07/2011 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
| 10/12/2011 | U VALUE FOR WINDOW | MHENSON | Approved | IVRS - Inspection :* |
| 10/13/2011 | PLUMBING - INTERMEDIATE | RRICH | Approved | IVRS - Inspection :* |
| 10/25/2011 | OUTDOOR LIGHTING FINAL | DSANTACR | Approved | IVRS - Inspection :* |
| 10/25/2011 | ELECTRIC - OUTDOOR LIGHTING | DSANTACR | Approved | IVRS - Inspection :* |
| 10/28/2011 | FIRE SPKLR - FINAL | DSIWARSKI | Approved | Per State Fire Marshal G. Chavez Blg #6 is not ready for inspection. |
| 11/02/2011 | BUILDING ABOVE CEILING | MHENSON | Approved | IVRS - Inspection :* |
| 11/02/2011 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
| 11/07/2011 | ELECTRIC - FINAL | RHOLLAND | Approved | IVRS - Inspection :* 1) OK LABELS AND PANEL SCHEDULE |
| 11/09/2011 | FIRE - ALARM FINAL | DSIWARSKI | Approved | Approved per State Fire Marshal (AHJ) G. Chavez |
| 11/14/2011 | FIRE - FINAL | DSIWARSKI | Approved | Approved per State Fire Marshal G. Chavez. |
| 11/15/2011 | LANDSCAPE - FINAL | DROBERTS | Approved | ALL CERTIFICATION LETTERS WILL BE PROVIDED FOR THIS SITE PRIOR OR DURING THE FINAL GRADING INSPECTION. |
| 12/12/2011 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
| 12/12/2011 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection :* |
| 12/13/2011 | BUILDING - FINAL | MHENSON | Approved | IVRS - Inspection :* |
| 12/15/2011 | ENGINEERING - FINAL | RLEDONNE | Approved | COMPLET NOTES FROM 11-15-2011 AND 11-23-2011 BEFORE CALLING FOR FINAL. |