Permit: T10CM00917
Permit Details
Apply Date:
04/07/2010
Applicant:
N/A
Description:
BLDG#3:LSS
Contractors:
- ASHTON COMPANY INC CONTRACTORS *T
Permit Reviews
Permit Number - T10CM00917
Permit Status: C of o
Permit Description: BLDG#3:LSS
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/30/2010 | COMMERCIAL TI | 07/09/2010 | COMPLETED |
07/09/2010 | RESUBMITTAL - TI ALL | 09/10/2010 | COMPLETED |
08/02/2011 | REVISION - - 1ST | 09/15/2011 | COMPLETED |
09/10/2010 | RESUBMITTAL | 12/17/2010 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T10CM00917
Permit Status: C of o
Permit Description: BLDG#3:LSS
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
04/07/2010 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T10CM00917
Permit Description: BLDG#3:LSS
Total Completed Inspections - 31
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/21/2011 | PLUMBING - PRE SLAB | RRICH | Approved | IVRS - Inspection :* |
07/15/2011 | PLUMBING - SEWER HCS CONNECT | RRICH | Approved | IVRS - Inspection :* 1) 4" SDR 35 FROM NEW MANHOLE AT NORTHWEST CORNER OF LSS TO 4" SADDLE TAP ON EXISTING CLAY 2) WATER TEST 3) PROVIDE CITY APPROVED PLAN OF THIS INSTALLATION-APPROVED PLAN PAGE OC-201 SHOWS EXISTING MANHOLE FOR TERMINATION POINT |
07/26/2011 | PLUMBING - ROUGH, SOIL | RRICH | Approved | IVRS - Inspection :* 1) COATING INSTALLED NEW MANHOLE NOTE #9 OC-201 WITH HOLIDAYS TEST 2) LSS EXTERIOR PIPING INSPECTED ON PERMIT #T10CM00802 ALL EXTERIOR OK |
08/09/2011 | PLUMBING - YARD WTR LINE/TEST | RMYERS | Approved | IVRS - Inspection :* 1) YARDWATER TO #3 OSS OK 2) NEED TO SEE BLDG CONNECTION 3) PRESSURE TEST OK-OK TO COVER |
08/11/2011 | ELECTRIC - UNDERGROUND | DSANTACR | Approved | IVRS - Inspection :* |
08/24/2011 | REINFORCED MASONRY PRE-GROUT | MHENSON | Approved | IVRS - Inspection :* |
09/09/2011 | BUILDING PRE-SLAB | MHENSON | Approved | IVRS - Inspection :* |
09/09/2011 | STEM WALL/RETAINING WALL | MHENSON | Approved | IVRS - Inspection :* |
09/09/2011 | EXCAVATION/LAYOUT REBAR & ZON | MHENSON | Approved | IVRS - Inspection :* |
10/14/2011 | ROOF NAILING | MHENSON | Approved | IVRS - Inspection :* 1) OK TO INSTALL METAL ROOFING |
10/14/2011 | FRAMING | MHENSON | Approved | IVRS - Inspection :* |
10/27/2011 | PLUMBING - INTERMEDIATE | RRICH | Approved | IVRS - Inspection :* 1) DRAIN WASTE AND VENT LSS OK EXCEPT FOR 2-4" P-TRAPS WITH VENTING FOR ABOVE SLAB |
12/06/2011 | ELECTRIC - PROGRESS | DSANTACR | Approved | IVRS - Inspection :* |
12/06/2011 | ELECTRIC - TEMPORARY SERVICE | DSANTACR | Approved | IVRS - Inspection :* |
12/06/2011 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
12/06/2011 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* |
12/06/2011 | ELECTRIC - UFER | DSANTACR | Approved | IVRS - Inspection :* |
01/10/2012 | BUILDING - PROGRESS | JBURGE | Approved | IVRS - Inspection :* |
01/10/2012 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* |
01/10/2012 | STUCCO MESH | JBURGE | Approved | IVRS - Inspection :* |
01/10/2012 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
01/17/2012 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
01/23/2012 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
01/23/2012 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection :* |
01/31/2012 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
02/01/2012 | FIRE - FINAL | WMOTTO | Approved | |
02/01/2012 | NPPO - FINAL | RLEDONNE | Approved | |
02/01/2012 | LANDSCAPE - FINAL | RLEDONNE | Approved | |
02/01/2012 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* |
02/02/2012 | SIGN - FINAL | RLEDONNE | Approved | NA TO THIS ACTIVITY. |
02/13/2012 | ENGINEERING - FINAL | RLEDONNE | Approved |