Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T10CM00251
Permit Details
Apply Date:
02/01/2010
Applicant:
N/A
Description:
ADMINISTRATION BLDG- 2 STORY
Architects:
- GRIGSBY, DAVID CECIL
Contractors:
- WITHERS CONSTRUCTION L C , D L
Permit Reviews
Permit Number - T10CM00251
Permit Status: C of o
Permit Description: ADMINISTRATION BLDG- 2 STORY
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/01/2010 | PLANS OK TO SUBMIT - COMM | 02/01/2010 | COMPLETED |
02/01/2010 | COMMERCIAL NEW | 03/11/2010 | COMPLETED |
03/15/2010 | RESUBMITTAL - TI ALL | 04/12/2010 | COMPLETED |
04/12/2010 | RESUBMITTAL - TI ALL | 04/21/2010 | COMPLETED |
04/21/2010 | RESUBMITTAL | 08/26/2010 | COMPLETED |
10/06/2010 | REVISION - - 1ST | 10/06/2010 | COMPLETED |
10/06/2010 | REVISION - - 1ST | 11/30/2010 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T10CM00251
Permit Status: C of o
Permit Description: ADMINISTRATION BLDG- 2 STORY
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
02/01/2010 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T10CM00251
Permit Description: ADMINISTRATION BLDG- 2 STORY
Total Completed Inspections - 47
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/18/2010 | ELECTRIC - UFER | DSANTACR | Approved | IVRS - Inspection :* |
11/01/2010 | PLUMBING - PROGRESS | BBENEDON | Approved | IVRS - Inspection :* 1) ENTER OFF SMOOT TO ACCESS TRAILER 2) USE CLEAN FILL 3) RED LINE PLANS PRIOR TO ANY INSPECTIONS |
11/01/2010 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | IVRS - Inspection :* |
11/04/2010 | PLUMBING - YARD WTR LINE/TEST | BBENEDON | Approved | IVRS - Inspection :* |
12/14/2010 | EXCAVATION/LAYOUT REBAR & ZON | AQUIROZ | Approved | IVRS - Inspection :* 1) 2 F6 FOOTERS AND 1 F-7 FOOTER |
12/15/2010 | ELECTRIC - UNDERGROUND | DSANTACR | Approved | IVRS - Inspection :* 1) OK EXTENSIONS OF 2 1/2 AND 1" CONDUITS FROM RM #110 TO TUNNEL |
12/22/2010 | REINFORCED MASONRY PRE-GROUT | AQUIROZ | Approved | IVRS - Inspection :* |
02/11/2011 | PLUMBING - PRE SLAB | RMYERS | Approved | IVRS - Inspection :* |
04/06/2011 | PLUMBING - ROOF DRAINS | RMYERS | Approved | IVRS - Inspection :* 1) RAIN WATER LEADERS AND OVER FLOW DRAINS OK 2) PLEASE POST YOUR ADDRESS |
06/06/2011 | TEP CLEARANCE - AM | JWEATHER | Approved | TEC CLEARED FOR "PAD MOUNT TRANSFORMER BLDG #7" PER R. HOLLANDER |
08/18/2011 | PLUMBING - ABOVE CEILING | RMYERS | Approved | IVRS - Inspection :* LOCATE P.O.C OF PUMPED WASTE AND PROVIDE ACCESS FOR INSPECTION |
08/30/2011 | MECHANICAL - HYDRONIC PIPING | AQUIROZ | Approved | IVRS - Inspection :* |
09/20/2011 | BUILDING ABOVE CEILING | AQUIROZ | Approved | IVRS - Inspection :* |
10/17/2011 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection :* |
10/17/2011 | PLUMBING - GAS PRESSURE TEST | RMYERS | Approved | IVRS - Inspection :* |
10/18/2011 | NPPO - FINAL | MRUSSO | Approved | |
10/18/2011 | SIGN - FINAL | MRUSSO | Approved | |
10/19/2011 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
10/19/2011 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
12/02/2011 | PLUMBING - SEWER HCS CONNECT | RMYERS | Approved | IVRS - Inspection :* |
12/02/2011 | PLUMBING - GAS PRESS TEST FNL | RMYERS | Approved | IVRS - Inspection :* |
12/02/2011 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection :* |
12/05/2011 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
12/05/2011 | OUTDOOR LIGHTING FINAL | RHOLLAND | Approved | IVRS - Inspection :* |
12/05/2011 | ELECTRIC - OUTDOOR LIGHTING | RHOLLAND | Approved | IVRS - Inspection :* |
12/05/2011 | ELECTRIC - PROGRESS | RHOLLAND | Approved | IVRS - Inspection :* |
12/05/2011 | ELECTRIC - TEMPORARY SERVICE | RHOLLAND | Approved | IVRS - Inspection :* |
12/05/2011 | ELECTRIC - ABOVE CEILING | RHOLLAND | Approved | IVRS - Inspection :* |
12/05/2011 | ELECTRIC - INTERMEDIATE | RHOLLAND | Approved | IVRS - Inspection :* |
12/06/2011 | FIRE - FINAL | WMOTTO | Approved | |
12/06/2011 | FIRE SPKLR - FINAL | WMOTTO | Approved | |
12/06/2011 | FIRE SPKLR - UG, PIPING, HYDRO | WMOTTO | Approved | |
12/06/2011 | ENGINEERING - FINAL | MRUSSO | Approved | 1) COMPLETE HC RAMP ALONG NORTH SIDE OF NEW BLDG 2) INSTALL SCUPPER ALONG NORTH SIDE OF BLDG, WHERE ROOF DRAIN DROPS STORM WATER ONTO THE SIDEWALK 3) COMPLETE ALL LANDSCAPE ROCK INSTALL |
12/06/2011 | LANDSCAPE - FINAL | MRUSSO | Approved | |
12/07/2011 | RIGHT OF WAY - FINAL | P.Whiddon | Approved | |
12/08/2011 | CERTIFICATE OF OCCUPANCY | AQUIROZ | Approved | 1) OK TEMP C OF O |
12/08/2011 | ELECTRIC - FINAL | RHOLLAND | Approved | IVRS - Inspection :* 1) RECEIVED EM LIGHTING TEST 2) OK GFCI'S |
12/08/2011 | BUILDING - FINAL | AQUIROZ | Approved | NEED TO COMPLETE HC RAMP AND PROVIDE ENGINEERING FINAL. OK TCO |
12/08/2011 | STEM WALL/RETAINING WALL | AQUIROZ | Approved | |
12/08/2011 | BUILDING PRE-SLAB | AQUIROZ | Approved | |
12/08/2011 | ROOF NAILING | AQUIROZ | Approved | |
12/08/2011 | FRAMING | AQUIROZ | Approved | |
12/08/2011 | U VALUE FOR WINDOW | AQUIROZ | Approved | |
12/08/2011 | SHEET ROCK NAILING | AQUIROZ | Approved | |
12/08/2011 | BUILDING - PROGRESS | AQUIROZ | Approved | |
12/08/2011 | ELECTRIC - TEMP POWER FOR TEST | LHANLY | Approved | |
12/08/2011 | ELECTRIC - FINAL | LHANLY | Approved | LISTING INFORMATION FOR SHUTTERS AND DOORS ACCEPTED |