Permit: T10CM00251

Parcel: 106101650


Addresses:

3910 N SUN TRAN BL


Inspection Status: Approved

Inspection History: ENGINEERING - FINAL

Permit Number - T10CM00251

Inspection Description - ENGINEERING - FINAL

Inspection Status - Approved

Date Description Inspector Results Comments
01/11/2012 ENGINEERING - FINAL Approved
12/06/2011 ENGINEERING - FINAL Partial Approval 1) COMPLETE HC RAMP ALONG NORTH SIDE OF NEW BLDG
2) INSTALL SCUPPER ALONG NORTH SIDE OF BLDG, WHERE ROOF DRAIN DROPS STORM WATER ONTO THE SIDEWALK
3) COMPLETE ALL LANDSCAPE ROCK INSTALL
11/29/2011 ENGINEERING - FINAL Not ready for Inspection 1) INSTALL HC PARKING SIGNS.
2) INSTALL BIKE PARKING.
3) INSTALL SCUPPER FOR ROOF DRAIN ALONG THE NORTH SIDE OF THE BLDG IN ORDER TO ROUTE STORM WATER UNDER THE SIDEWALK.
4) SATISFY ALL THE REQUIREMENTS UNDER THE GRADING PERMIT # T09BU01625
5) PROVIDE A CERT STATEMENT FROM THE ENGINEER OF RECORD STATING THAT THE SITE WORK WAS SUBSTATIALLY COMPLETED PER THE APPROVED GRADING PLAN.
10/18/2011 ENGINEERING - FINAL Denied PRIOR TO FINAL APPROVAL FOR ENGINEERING:
1) COMPLETE LANDSCAPING PER PLAN
2) COMPLETE ALL STORM WATER DRAINAGE PER PLAN (SWALES, SCUPPERS...ECT)
3) INSTALL ALL HC RAMPS SHOWN
4) COMPLETE ALL SIDEWALKS
5) ENSURE MAIN ROOF DRAINS FLOW UNDER ADJACENT SIDEWALKS
6) REMOVE ALL CONSTRUCTION DEBRIS AND EQUIPMENT
7) ENSURE PEDESTRIAN ACCESS POINTS MEET ALL SLOPE REQUIREMENTS TO INCLUDE ADAAG/ANSI REQUIREMENTS.
8) PROVIDE A CERT STATEMENT FROM THE ENG OF RECORD STATING THAT ALL SITE WORK WAS SUBSTANTIALY COMPLETED PER THE APPROVE PLANS