Permit: T09CM02318
Permit Details
Apply Date:
08/31/2009
Applicant:
N/A
Description:
NEW POOL HOUSE
Contractors:
- H S L CONSTRUCTION SERVICES L L C
Permit Reviews
Permit Number - T09CM02318
Permit Status: C of o
Permit Description: NEW POOL HOUSE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
08/31/2009 | COMMERCIAL NEW | 09/21/2009 | COMPLETED |
09/21/2009 | RESUBMITTAL | 10/07/2009 | COMPLETED |
10/07/2009 | RESUBMITTAL | 10/16/2009 | COMPLETED |
10/16/2009 | RESUBMITTAL | 10/21/2009 | COMPLETED |
11/12/2009 | REVISION - - 1ST | 11/12/2009 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T09CM02318
Permit Status: C of o
Permit Description: NEW POOL HOUSE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
08/31/2009 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T09CM02318
Permit Description: NEW POOL HOUSE
Total Completed Inspections - 28
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/02/2009 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | IVRS - Inspection :* |
12/10/2009 | ELECTRIC - UNDERGROUND | RMORENO | Approved | IVRS - Inspection :* 1) UFER ALL OK |
12/10/2009 | EXCAVATION/LAYOUT REBAR & ZON | AQUIROZ | Approved | IVRS - Inspection :* |
12/11/2009 | PLUMBING - PRE SLAB | BBENEDON | Approved | IVRS - Inspection : See detailed listing on site.| 999* 1) PROVIDE A UPC APPROVED FLOOR DRAIN 2) (FHA) WITH A TRAP PRIMER OR (OTHER APPROVED METHOD) 3) WRAP CLOSET BEND |
12/11/2009 | PLUMBING - PRE SLAB | BBENEDON | Approved | IVRS - Inspection :* |
12/31/2009 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* 1) OK FOR SHEETROCK |
12/31/2009 | ELECTRIC - INTERMEDIATE | RMORENO | Approved | IVRS - Inspection :* 1) WALLS AND CEILINGS ALL OK |
12/31/2009 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection : See detailed listing on site.| 999* 1) NOT INSTALLED PER PLAN 2) DOES NOT MEET THE MINIMUM VENTING REQUIREMENTS PER UPC 904.1 3) SHOWER FAUCET AND DRAIN NOT PER PLAN SPECS 4) LAV CARRIER SPECIFIED 5) WH INSTALLED ON WOOD PLATFORM, WILL REQUIRE A PAN AND DRAIN |
12/31/2009 | BUILDING ABOVE CEILING | AQUIROZ | Approved | IVRS - Inspection :* |
12/31/2009 | FRAMING | AQUIROZ | Approved | IVRS - Inspection :* |
12/31/2009 | ROOF NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
12/31/2009 | ELECTRIC - ABOVE CEILING | RMORENO | Approved | IVRS - Inspection :* |
01/07/2010 | STUCCO MESH | AQUIROZ | Approved | IVRS - Inspection :* |
01/13/2010 | PLUMBING - YARD WTR LINE/TEST | BBENEDON | Approved | IVRS - Inspection :* 1) PROTECT ? FROM STUCCO AT WALL PENETRATION |
01/14/2010 | SHEET ROCK NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
02/10/2010 | ELECTRIC - CABLE DROP | RMORENO | Approved | IVRS - Inspection :* |
02/11/2010 | TEP CLEARANCE - AM | JWEATHER | Approved | INCR CLEARED PER R. MORENO |
05/10/2010 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
05/10/2010 | FIRE - FINAL | DSIWARSKI | Approved | Approved |
05/10/2010 | SIGN - FINAL | JYBARRA | Approved | |
05/10/2010 | ELECTRIC - FINAL | RMORENO | Approved | IVRS - Inspection :* |
05/11/2010 | RIGHT OF WAY - FINAL | MOTERO | Approved | |
05/13/2010 | PLUMBING - FINAL | BBENEDON | Approved | IVRS - Inspection :* |
05/14/2010 | BUILDING - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |
05/14/2010 | ENGINEERING - FINAL | JFEMLING | Approved | Grading permit re-newed, storm controls being placed, approved |
05/14/2010 | NPPO - FINAL | JFEMLING | Approved | Approved |
05/14/2010 | LANDSCAPE - FINAL | JFEMLING | Approved | Gradeing permit renewed, storm controls in place, approved |
05/17/2010 | SITE - SEWER | BBENEDON | Approved | PER PL FINAL |