Permit: T09CM02186
Permit Details
Status:
C of o
Type:
COMMERCIAL ADDITION
Address:
2222 S CRAYCROFT RD
Address NEW:
2222 S CRAYCROFT RD
Apply Date:
08/17/2009
Applicant:
N/A
Description:
ADDITION:STORAGE BLDG (S2)
Contractors:
- GILES CONSTRUCTION INC ,
Permit Reviews
Permit Number - T09CM02186
Permit Status: C of o
Permit Description: ADDITION:STORAGE BLDG (S2)
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/16/2010 | 3RD PARTY REVIEW-REVISION/OTHER | 02/22/2010 | COMPLETED |
| 04/13/2010 | REVISION - SITE | 04/13/2010 | COMPLETED |
| 05/18/2010 | 3RD PARTY REVIEW-REVISION/OTHER | 05/24/2010 | COMPLETED |
| 06/09/2010 | REVISION - - 1ST | 06/09/2010 | COMPLETED |
| 08/17/2009 | PLANS OK TO SUBMIT - 3RD PARTY | 08/18/2009 | COMPLETED |
| 08/17/2009 | PLANS OK TO SUBMIT - SITE | 08/18/2009 | COMPLETED |
| 08/18/2009 | SITE | 09/21/2009 | COMPLETED |
| 08/18/2009 | 3RD PARTY REVIEW-COMMERCIAL | 10/29/2009 | COMPLETED |
| 10/05/2010 | REVISION - SITE | 10/05/2010 | COMPLETED |
| 10/23/2009 | RESUBMITTAL - SITE ALL | 11/06/2009 | COMPLETED |
| 10/29/2009 | POST 3RD PARTY REVIEW | 11/06/2009 | COMPLETED |
| 11/12/2009 | RESUBMITTAL - SITE | 11/19/2009 | COMPLETED |
| 11/19/2009 | RESUBMITTAL | 12/03/2009 | COMPLETED |
| 12/03/2009 | POST 3RD PARTY REVIEW | 12/11/2009 | COMPLETED |
| 12/11/2009 | RESUBMITTAL | 12/11/2009 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T09CM02186
Permit Status: C of o
Permit Description: ADDITION:STORAGE BLDG (S2)
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/17/2009 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T09CM02186
Permit Description: ADDITION:STORAGE BLDG (S2)
Total Completed Inspections - 39
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/03/2010 | PLUMBING - PRE SLAB | RRICH | Approved | IVRS - Inspection :* |
| 03/03/2010 | ELECTRIC - UFER | RJIROUDE | Approved | IVRS - Inspection :* |
| 05/21/2010 | PLUMBING - YARD WTR LINE/TEST | RMYERS | Approved | 1) POST YOUR ADDRESS |
| 06/08/2010 | FIRE SPKLR - UG PIPING FLUSH | LTHOMAS | Approved | |
| 06/08/2010 | FIRE SPKLR - UG, PIPING, HYDRO | LTHOMAS | Approved | |
| 08/24/2010 | TEP CLEARANCE - AM | JWEATHER | Approved | TEC CLEARED PER D. SANTACRUZ |
| 09/02/2010 | PLUMBING - ROUGH, SOIL | RRICH | Approved | IVRS - Inspection :* 1) WATER TEST DWV UNDERGROUND AND THRU ROOF AT (4) STOOL (2) LAV RESTROOM OK 03035-DWV TEST STILL REQUIRED ON (S-1 EMPLOYEE LOUNGE) AND MAINTANCE TOILET. THRU ROOF ONLY |
| 09/07/2010 | FRAMING | JBURGE | Approved | IVRS - Inspection :* 1) OK TO SHEETROCK |
| 09/08/2010 | EXCAVATION/LAYOUT REBAR & ZON | GDABBS | Approved | IVRS - Inspection :* 1) 2 NORTH EXTERIOR CMU COLUMNS FROM 12' TO 16' TOP OUT OK |
| 09/14/2010 | ELECTRIC - INTERMEDIATE | RJIROUDE | Approved | IVRS - Inspection :* |
| 09/15/2010 | PLUMBING - PROGRESS | RRICH | Approved | IVRS - Inspection :* 1) DEMO CAPS UNDER SLAB OK |
| 09/15/2010 | ROOF NAILING | GDABBS | Approved | IVRS - Inspection :* |
| 09/17/2010 | SHEET ROCK NAILING | GDABBS | Approved | IVRS - Inspection :* |
| 09/17/2010 | EXT METAL CLIPS/EXT SHEATHING | GDABBS | Approved | IVRS - Inspection :* |
| 09/23/2010 | PLUMBING - ROOF DRAINS | RRICH | Approved | IVRS - Inspection :* |
| 09/23/2010 | PLUMBING - INTERMEDIATE | RRICH | Approved | IVRS - Inspection :* |
| 09/30/2010 | BUILDING ABOVE CEILING | GDABBS | Approved | IVRS - Inspection :* |
| 09/30/2010 | ELECTRIC - ABOVE CEILING | RJIROUDE | Approved | IVRS - Inspection :* |
| 10/01/2010 | MECHANICAL - ABOVE CEILING | RRICH | Approved | IVRS - Inspection :* |
| 10/01/2010 | PLUMBING - FINAL | RRICH | Approved | IVRS - Inspection :* |
| 10/01/2010 | PLUMBING - ABOVE CEILING | RRICH | Approved | IVRS - Inspection :* |
| 10/04/2010 | FIRE - FINAL | LTHOMAS | Approved | |
| 10/04/2010 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
| 10/04/2010 | FIRE - FINAL | LTHOMAS | Approved | |
| 10/05/2010 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
| 10/05/2010 | MECHANICAL - PROGRESS | JMILITEL | Approved | IVRS - Inspection :* |
| 10/05/2010 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
| 10/05/2010 | SIGN - FINAL | LHANLY | Approved | |
| 10/05/2010 | ELECTRIC - FINAL | RJIROUDE | Approved | IVRS - Inspection :* |
| 10/05/2010 | ELECTRIC - PROGRESS | RJIROUDE | Approved | IVRS - Inspection :* |
| 10/05/2010 | NPPO - FINAL | JFEMLING | Approved | Approved |
| 10/05/2010 | LANDSCAPE - FINAL | JFEMLING | Approved | Approved |
| 10/05/2010 | ENGINEERING - FINAL | JFEMLING | Approved | Approved |
| 10/05/2010 | RIGHT OF WAY - FINAL | P.Whiddon | Approved | |
| 10/06/2010 | PLUMBING - SEWER HCS CONNECT | RRICH | Approved | |
| 10/06/2010 | BUILDING PRE-SLAB | LHANLY | Approved | |
| 10/06/2010 | BUILDING - PROGRESS | LHANLY | Approved | |
| 10/06/2010 | STUCCO MESH | LHANLY | Approved | |
| 10/06/2010 | BUILDING - FINAL | LHANLY | Approved |