Permit: T09CM00692
Permit Details
Apply Date:
03/27/2009
Applicant:
N/A
Description:
CONVENIENCE STORE
Architects:
- COLE, BENJAMIN WILLIAM
Contractors:
- LANG WYATT CONSTRUCTION ,
Permit Reviews
Permit Number - T09CM00692
Permit Status: C of o
Permit Description: CONVENIENCE STORE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/26/2010 | REVISION - - 3RD | 03/26/2010 | COMPLETED |
| 03/27/2009 | PLANS OK TO SUBMIT - COMM | 03/27/2009 | COMPLETED |
| 03/27/2009 | COMMERCIAL NEW | 05/12/2009 | COMPLETED |
| 05/27/2009 | RESUBMITTAL | 06/11/2009 | COMPLETED |
| 06/11/2009 | RESUBMITTAL | 06/26/2009 | COMPLETED |
| 08/31/2009 | REVISION - - 1ST | 08/31/2009 | COMPLETED |
| 10/27/2009 | REVISION - - 2ND | 03/26/2010 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T09CM00692
Permit Status: C of o
Permit Description: CONVENIENCE STORE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 03/27/2009 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T09CM00692
Permit Description: CONVENIENCE STORE
Total Completed Inspections - 41
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/24/2009 | ELECTRIC - UFER | RHOLLAND | Approved | IVRS - Inspection :* 1) OK 3/0 TO REBAR |
| 10/02/2009 | PLUMBING - ROUGH, SOIL | RLEDONNE | Approved | IVRS - Inspection :* |
| 10/23/2009 | EXCAVATION/LAYOUT REBAR & ZON | MHENSON | Approved | IVRS - Inspection :* PARTIAL FOOTING FOR EAST & WEST 12" RETAINING WALLS |
| 10/27/2009 | STEM WALL/RETAINING WALL | MHENSON | Approved | IVRS - Inspection :* |
| 10/28/2009 | PLUMBING - SEWER HCS CONNECT | RLEDONNE | Approved | IVRS - Inspection :* |
| 10/30/2009 | REINFORCED MASONRY PRE-GROUT | MHENSON | Approved | IVRS - Inspection :* |
| 11/06/2009 | PLUMBING - PROGRESS | RLEDONNE | Approved | IVRS - Inspection :* 1) STREET SEWER TIE IN TO BLDG OK |
| 11/17/2009 | PLUMBING - PRE SLAB | RLEDONNE | Approved | IVRS - Inspection :* |
| 12/18/2009 | ROOF NAILING | MHENSON | Approved | IVRS - Inspection :* 1) PROVIDE SPECIALS FOR WELDING |
| 12/18/2009 | PLUMBING - INTERMEDIATE | RLEDONNE | Approved | IVRS - Inspection :* 1) PROVIDE MINIMUM 10 PSI TEST ON ALL GAS PIPING 2) CALL BACK FOR CLOSET FLANGES |
| 12/18/2009 | ELECTRIC - UNDERGROUND | RHOLLAND | Approved | IVRS - Inspection :* 1) OK PVC AT SIGNS AND AIR STATION 2) OK SOFFIT AT CASHIER 3) OK BATHROOM CANS |
| 12/18/2009 | PLUMBING - ABOVE CEILING | RLEDONNE | Approved | IVRS - Inspection :* |
| 12/21/2009 | PLUMBING - GAS PRESSURE TEST | RLEDONNE | Approved | IVRS - Inspection :* |
| 12/22/2009 | BUILDING - PROGRESS | MHENSON | Approved | IVRS - Inspection :* 1) EXTERIOR DENSGLASS OK |
| 12/22/2009 | ELECTRIC - INTERMEDIATE | RHOLLAND | Approved | IVRS - Inspection :* 1) OK FRONT STORE INTERIOR WALL |
| 12/22/2009 | ELECTRIC - PROGRESS | RHOLLAND | Approved | IVRS - Inspection :* |
| 12/22/2009 | FRAMING | MHENSON | Approved | IVRS - Inspection :* |
| 12/24/2009 | SHEET ROCK NAILING | MHENSON | Approved | IVRS - Inspection :* |
| 01/21/2010 | TEP CLEARANCE - AM | JWEATHER | Approved | TMPP CLEARED PER R. HOLLANDER |
| 02/04/2010 | BUILDING ABOVE CEILING | MHENSON | Approved | IVRS - Inspection :* |
| 02/05/2010 | FIREWALL/FIREBARRIER/FIRESTOP | MHENSON | Approved | IVRS - Inspection :* |
| 02/08/2010 | PLUMBING - GAS PRESS TEST FNL | RLEDONNE | Approved | IVRS - Inspection :* |
| 02/08/2010 | PLUMBING - YARD WTR LINE/TEST | RLEDONNE | Approved | IVRS - Inspection :* |
| 02/12/2010 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
| 03/08/2010 | FIRE SPKLR - UG, PIPING, HYDRO | DSIWARSKI | Approved | |
| 03/08/2010 | FIRE SPKLR - FINAL | DSIWARSKI | Approved | Approved |
| 03/16/2010 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 03/19/2010 | FIRE - FINAL | DRamirez | Approved | Approved 3/19/10 |
| 03/22/2010 | RIGHT OF WAY - FINAL | LLopez | Approved | |
| 05/07/2010 | NPPO - FINAL | MCARREON | Approved | PER INSP CARD |
| 05/07/2010 | LANDSCAPE - FINAL | MCARREON | Approved | PER INPS CARD |
| 05/07/2010 | ENGINEERING - FINAL | MCARREON | Approved | PER INSP CARD |
| 05/07/2010 | OUTDOOR LIGHTING FINAL | RHOLLAND | Approved | |
| 05/07/2010 | ELECTRIC - OUTDOOR LIGHTING | RHOLLAND | Approved | |
| 05/07/2010 | ELECTRIC - TEMP POWER FOR TEST | RHOLLAND | Approved | |
| 05/07/2010 | ELECTRIC - CABLE DROP | RHOLLAND | Approved | |
| 05/07/2010 | ELECTRIC - ABOVE CEILING | RHOLLAND | Approved | |
| 06/17/2010 | PLUMBING - FINAL | RLEDONNE | Approved | IVRS - Inspection :* |
| 06/22/2010 | BUILDING - FINAL | LHANLY | Approved | |
| 06/22/2010 | ELECTRIC - FINAL | LHANLY | Approved | ETL LISTING FOR AIR MACHINE ACCEPTED. WINDOW SHUTTERS ACCEPTED AS CODE COMPLIANT WITHOUT FURTHER LISTINGS. |
| 06/24/2010 | SIGN - FINAL | JYBARRA | Approved |