Permit: T08CM02542
Permit Details
Apply Date:
07/22/2008
Applicant:
N/A
Description:
NEW OFFICE BUILDING
Architects:
- FENECK, JOHN
Contractors:
- STEADFAST STRUCTURES INC
Permit Reviews
Permit Number - T08CM02542
Permit Status: C of o
Permit Description: NEW OFFICE BUILDING
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/27/2009 | POST 3RD PARTY REVIEW | 04/09/2009 | COMPLETED |
04/09/2009 | 3RD PARTY REVIEW-REVISION/OTHER | 05/11/2009 | COMPLETED |
06/30/2009 | REVISION - - 1ST | 06/30/2009 | COMPLETED |
07/22/2008 | PLANS OK TO SUBMIT - COMM | 08/11/2008 | COMPLETED |
08/11/2008 | 3RD PARTY REVIEW-COMMERCIAL | 10/15/2008 | COMPLETED |
10/15/2008 | POST 3RD PARTY REVIEW | 10/30/2008 | COMPLETED |
10/30/2008 | 3RD PARTY REVIEW-COMMERCIAL TI | 12/15/2008 | COMPLETED |
12/15/2008 | POST 3RD PARTY REVIEW | 12/23/2008 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T08CM02542
Permit Status: C of o
Permit Description: NEW OFFICE BUILDING
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
07/22/2008 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T08CM02542
Permit Description: NEW OFFICE BUILDING
Total Completed Inspections - 38
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/19/2009 | RIGHT OF WAY - FINAL | LLOPEZ | Approved | PER EMAIL |
05/19/2009 | PLUMBING - ROUGH, SOIL | RLEDONNE | Approved | IVRS - Inspection :* POST ADDRESS |
05/20/2009 | PLUMBING - PRE SLAB | RLEDONNE | Approved | IVRS - Inspection :* |
05/20/2009 | ELECTRIC - UFER | RJIROUDE | Approved | IVRS - Inspection :* |
05/20/2009 | BUILDING PRE-SLAB | GDABBS | Approved | IVRS - Inspection :* |
07/10/2009 | PLUMBING - SEWER HCS CONNECT | RRICH | Approved | IVRS - Inspection :* |
07/14/2009 | ROOF NAILING | GDABBS | Approved | IVRS - Inspection :* |
07/14/2009 | EXT METAL CLIPS/EXT SHEATHING | GDABBS | Approved | IVRS - Inspection :* |
07/21/2009 | FRAMING | GDABBS | Approved | |
08/05/2009 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* 1) OK TO SHEETROCK HARD LIDS 2) PROVIDE BACKING AROUND CEILING BOX PRIOR TO SHEETROCK |
08/05/2009 | PLUMBING - ABOVE CEILING | RRICH | Approved | IVRS - Inspection :* |
08/05/2009 | PLUMBING - INTERMEDIATE | RRICH | Approved | IVRS - Inspection :* |
08/07/2009 | U VALUE FOR WINDOW | JBURGE | Approved | IVRS - Inspection :* 1) MANUFACTURES SPECS: WINDOWS AT 0.33 AND 0.37; ALUMINUM STORE FRONT IS AT 0.60 |
08/11/2009 | PLUMBING - YARD WTR LINE/TEST | RRICH | Approved | IVRS - Inspection :* |
08/12/2009 | SHEET ROCK NAILING | GDABBS | Approved | IVRS - Inspection :* |
08/27/2009 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* 1) OK FOR CEILING TILES 2) PROVIDE BEADED COLLARS ON ALL SUPPLY DIFFUSERS 3) WILL CHECK AT FINAL |
08/27/2009 | BUILDING ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* 1) OK FOR CEILING TILES |
08/27/2009 | ELECTRIC - INTERMEDIATE | RJIROUDE | Approved | IVRS - Inspection :* |
08/27/2009 | ELECTRIC - ABOVE CEILING | RJIROUDE | Approved | IVRS - Inspection :* |
09/02/2009 | TEP CLEARANCE - AM | JWEATHER | Approved | TEC CLEARED PER R. JIROUDEK |
09/17/2009 | OUTDOOR LIGHTING FINAL | RJIROUDE | Approved | IVRS - Inspection :* |
09/17/2009 | ELECTRIC - OUTDOOR LIGHTING | RJIROUDE | Approved | IVRS - Inspection :* |
09/17/2009 | OUTDOOR LIGHTING FINAL | RJIROUDE | Approved | IVRS - Inspection :* |
09/17/2009 | ELECTRIC - OUTDOOR LIGHTING | RJIROUDE | Approved | IVRS - Inspection :* |
09/17/2009 | ELECTRIC - CABLE DROP | RJIROUDE | Approved | IVRS - Inspection :* |
09/17/2009 | EXCAVATION/LAYOUT REBAR & ZON | GDABBS | Approved | IVRS - Inspection :* |
09/22/2009 | ELECTRIC - FINAL | RJIROUDE | Approved | IVRS - Inspection :* |
09/22/2009 | ELECTRIC - FINAL | RJIROUDE | Approved | IVRS - Inspection :* |
09/24/2009 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
09/24/2009 | FIRE - FINAL | LTHOMAS | Approved | |
09/30/2009 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* 1) OK FOR FINAL |
09/30/2009 | PLUMBING - FINAL | RRICH | Approved | IVRS - Inspection :* |
09/30/2009 | SITE - SEWER | RRICH | Approved | IVRS - Inspection :* |
10/01/2009 | BUILDING - FINAL | GDABBS | Approved | IVRS - Inspection :* |
11/04/2009 | ENGINEERING - FINAL | DROBERTS | Approved | THE DEVELOPER HAS HAD THE AS-BUILT DRAWINGS REVISED BY THE ENGINEER OF RECORD SO THAT IT MEET THE CURRENT CONDITIONS. THERE IS A PLAN THAT IS BEING DRAWN FOR THE SITE THAT WILL CHANGE IT TO A FULL STOCKPILE SITE OF CONSTRUCTION MATERIALS. |
11/10/2009 | NPPO - FINAL | JLINVILLE | Approved | |
11/10/2009 | LANDSCAPE - FINAL | JLINVILLE | Approved | |
11/12/2009 | ELECTRIC - TEMP POWER FOR TEST | RJIROUDE | Approved |