Permit: T08CM01436
Permit Details
Apply Date:
05/05/2008
Applicant:
N/A
Description:
TEMP POWER & CHILLED WATER PIPING FOR ROLL UP CHILLER PLANT REVISION 2: CHILL WATER LINE SUPPORT
Contractors:
- BECK
Permit Reviews
Permit Number - T08CM01436
Permit Status: Final
Permit Description: TEMP POWER & CHILLED WATER PIPING FOR ROLL UP CHILLER PLANT
REVISION 2: CHILL WATER LINE SUPPORT
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/05/2008 | OTHER | 05/05/2008 | COMPLETED |
| 06/05/2008 | OTHER | 06/05/2008 | COMPLETED |
| 06/05/2008 | RESUBMITTAL | 06/18/2008 | COMPLETED |
| 06/18/2008 | RESUBMITTAL | 07/22/2008 | COMPLETED |
| 07/22/2008 | REVISION - - 1ST | 08/18/2009 | COMPLETED |
| 08/18/2009 | REVISION - - 2ND | 09/15/2009 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T08CM01436
Permit Status: Final
Permit Description: TEMP POWER & CHILLED WATER PIPING FOR ROLL UP CHILLER PLANT
REVISION 2: CHILL WATER LINE SUPPORT
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 05/05/2008 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T08CM01436
Permit Description: TEMP POWER & CHILLED WATER PIPING FOR ROLL UP CHILLER PLANT
REVISION 2: CHILL WATER LINE SUPPORT
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/11/2008 | ELECTRIC - FINAL | RHOLLAND | Approved | IVRS - Inspection : The wiring is not complete or does not comply with code.| 245* EXTERIOR 1. A GROUNDING ELECTRODE SYSTEM IS NEEDED THERE ARE SEPARATE STRUCTURES 2. IDENTIFY GROUNDING EQUIPMENT CONDUCTORS AT LUGS 3. INSTALL ARC FAULT LABELING 4. SWITCHBOARDS ARE FOR 400A MAX GENERATOR INPUTS NOT FEED FOR TEMP EQUIPMENT -- NEED NRTL RECERTIFICATION IF CHANGED TO OUTPUT 5. NEED COPIES OF GFI TEST 6. NEED PLANS FOR OUTSIDE SWITCHBOARDS 7. HAVE BUILDING INSPECTOR VERIFY FIRE STOPPING |
| 08/04/2009 | MECHANICAL - HYDRONIC PIPING | MRAMBER | Approved | |
| 08/04/2009 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 09/23/2009 | ELECTRIC - INTERMEDIATE | LHANLY | Approved | IVRS - Inspection :* |