Inspection History Details
Inspection Status: Approved
Inspection History: ELECTRIC - INTERMEDIATE
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/23/2009 | ELECTRIC - INTERMEDIATE | Approved | IVRS - Inspection :* | |
| 06/19/2009 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) MET WITH ENGINEER ADAM BAGBE AND JASON JAWORSKY, IT WAS DETERMINED THAT THE SWITCHBOARDS ARE IN COMPLIANCE 2) LABELING IS CONFUSING, SO LABELING NEEDS TO BE CHANGED FOR CLARIFICATION 3) RECALL FOR FINAL |
|
| 02/13/2009 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 07/29/2008 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* ALL CORRECTIONS MADE |
|
| 07/28/2008 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1. SUPPORT CABLES UP OFF OF PIPING 2. SUPPORT & PROTECT FROM PHYSICAL DAMAGE CABLES OUTSIDE 3. BOND BUSHING AT CONCENTRIC ABOVE 250V -- 250.97 4. SECURE CABLE IN JUNCTION BOX FOR STRAIN RELIEF 5. BONDING JUMPER TO BE SIZED PER 250.122 6. A GROUNDING ELECTRODE SYSTEM IS NEEDED - 250.30 |