Permit: T08CM00587
Permit Details
Apply Date:
02/20/2008
Applicant:
METRO PERMIT EXPRESS, INC *C
Description:
NEW OFFICE SHELL BLDG & COMMON AREAS REVISION ONE: STRUCTURAL LOADING ADJUSTMENTS AND W.C. ADDITION
Architects:
- EGLIN, EVAN SAR
Contractors:
- CHESTNUT CONSTRUCTION CORPORATIO
Permit Reviews
Permit Number - T08CM00587
Permit Status: Final
Permit Description: NEW OFFICE SHELL BLDG & COMMON AREAS
REVISION ONE: STRUCTURAL LOADING ADJUSTMENTS AND W.C. ADDITION
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/20/2008 | PLANS OK TO SUBMIT - 3RD PARTY | 02/28/2008 | COMPLETED |
| 02/24/2010 | REVISION - - 2ND | 03/05/2010 | COMPLETED |
| 02/28/2008 | 3RD PARTY REVIEW-COMMERCIAL | 09/04/2008 | COMPLETED |
| 09/04/2008 | POST 3RD PARTY REVIEW | 11/19/2008 | COMPLETED |
| 11/19/2008 | RESUBMITTAL | 12/24/2008 | COMPLETED |
| 12/15/2009 | REVISION - - 1ST | 12/24/2009 | COMPLETED |
| 12/24/2009 | REVISION - - 1ST | 12/31/2009 | COMPLETED |
| 12/31/2009 | REVISION - - 1ST | 12/31/2009 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T08CM00587
Permit Status: Final
Permit Description: NEW OFFICE SHELL BLDG & COMMON AREAS
REVISION ONE: STRUCTURAL LOADING ADJUSTMENTS AND W.C. ADDITION
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 02/20/2008 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T08CM00587
Permit Description: NEW OFFICE SHELL BLDG & COMMON AREAS
REVISION ONE: STRUCTURAL LOADING ADJUSTMENTS AND W.C. ADDITION
Total Completed Inspections - 43
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/14/2009 | PLUMBING - YARD WTR LINE/TEST | RMYERS | Approved | IVRS - Inspection :* 1) POST ADDRESS 2) 2 1/2" PVC YARDWATER INSTALLED OK 3) OK TO COVER |
| 12/17/2009 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection :* 1) TOILET ROOMS #107 AND 108 AND ASSOCIATED PIPING OK 2) WATER TEST TO 10 FEET OK 3) OK TO COVER |
| 12/17/2009 | ELECTRIC - UNDERGROUND | DSANTACR | Approved | IVRS - Inspection :* 1) OK 4" SECONDARY/DATA INTO ELECTRICAL ROOM FROM UTILITY |
| 12/21/2009 | FIRE SPKLR - UG, PIPING, HYDRO | LTHOMAS | Approved | |
| 12/22/2009 | STEM WALL/RETAINING WALL | JBURGE | Approved | IVRS - Inspection :* 1) ELEVATOR STEM WALLS AS PER DETAILS #107-108, PAGE S3.0-OK TO POUR |
| 12/24/2009 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | IVRS - Inspection :* 1) 3 COLUMN FOOTINGS (6 #5'S EACH WAY) SOUTHEAST AND MID STAIRS AREA-OK TO POUR FOOTINGS |
| 12/29/2009 | BUILDING PRE-SLAB | JBURGE | Approved | IVRS - Inspection :* 1) ALL AREAS EXCEPT FOR STAIRWAY ENTRY SLABS-OK TO POUR PROGRESS AREAS |
| 12/29/2009 | ELECTRIC - UFER | RMORENO | Approved | IVRS - Inspection :* 1) UFER AND ALL OK 2) STUBS FOR LIGHTS ALL OK |
| 12/30/2009 | PLUMBING - PRE SLAB | RMYERS | Approved | IVRS - Inspection :* 1) OK FOR CONCRETE |
| 04/07/2010 | ROOF NAILING | JBURGE | Approved | IVRS - Inspection :* OK TO DRY IN ROOF SYSTEM |
| 04/16/2010 | PLUMBING - ROOF DRAINS | RRICH | Approved | IVRS - Inspection :* |
| 04/20/2010 | PLUMBING - ABOVE CEILING | RMYERS | Approved | IVRS - Inspection :* |
| 04/20/2010 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection :* |
| 06/11/2010 | ELECTRIC - CONSTRUCTION POWER | DSANTACR | Approved | IVRS - Inspection :* |
| 06/11/2010 | ELECTRIC - CABLE DROP | DSANTACR | Approved | IVRS - Inspection :* |
| 07/15/2010 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
| 08/03/2010 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* 1) OK FINAL SHELL ONLY |
| 08/03/2010 | MECHANICAL - PROGRESS | JMILITEL | Approved | IVRS - Inspection :* |
| 08/03/2010 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
| 08/03/2010 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | |
| 08/03/2010 | PLUMBING - PROGRESS | RMYERS | Approved | IVRS - Inspection :* |
| 08/03/2010 | SITE - SEWER | RMYERS | Approved | IVRS - Inspection :* |
| 08/03/2010 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
| 08/03/2010 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* |
| 08/09/2010 | BUILDING - PROGRESS | JBURGE | Approved | IVRS - Inspection :* |
| 08/09/2010 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* |
| 08/09/2010 | U VALUE FOR WINDOW | JBURGE | Approved | IVRS - Inspection :* |
| 08/09/2010 | FRAMING | JBURGE | Approved | IVRS - Inspection :* |
| 08/09/2010 | EXT METAL CLIPS/EXT SHEATHING | JBURGE | Approved | IVRS - Inspection :* |
| 08/09/2010 | REINFORCED MASONRY PRE-GROUT | JBURGE | Approved | IVRS - Inspection :* |
| 08/10/2010 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection :* |
| 08/12/2010 | RIGHT OF WAY - FINAL | MOTERO | Approved | |
| 08/12/2010 | SIGN - FINAL | JYBARRA | Approved | |
| 08/18/2010 | OUTDOOR LIGHTING FINAL | DSANTACR | Approved | IVRS - Inspection :* |
| 08/18/2010 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
| 08/18/2010 | ELECTRIC - OUTDOOR LIGHTING | DSANTACR | Approved | IVRS - Inspection :* |
| 08/18/2010 | ELECTRIC - PROGRESS | DSANTACR | Approved | IVRS - Inspection :* |
| 08/19/2010 | NPPO - FINAL | MRUSSO | Approved | |
| 08/19/2010 | LANDSCAPE - FINAL | MRUSSO | Approved | |
| 08/23/2010 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
| 08/24/2010 | FIRE - FINAL | LTHOMAS | Approved | |
| 08/25/2010 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* 1) ALL TRADES AND FIRE FINALS ARE COMPLETE 2) SMOKE DETECTION TEST WERE COMPLETED ON 8/20/10 |
| 09/02/2010 | ENGINEERING - FINAL | MRUSSO | Approved |