Permit: T08CM00587

Parcel: 122184340


Addresses:

3501 E SPEEDWAY BL

Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Date Description Inspector Results Comments
08/09/2010 EXCAVATION/LAYOUT REBAR & ZON Approved IVRS - Inspection :*
08/03/2010 EXCAVATION/LAYOUT REBAR & ZON Cancelled IVRS - RI canceled
05/25/2010 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) TRASH ENCLOSURE FOOTINGS-OK TO POUR PROGRESS AREAS
05/24/2010 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) STEM WALL FOOTINGS N.E., EAST, S.E. ALONG PROPERTY LINE-OK TO POUR PROGRESS AREAS EXCEPT: DO NOT POUR PORTION CONTAINING NEIGHBORING UTILITY LINES (SEWER LINES)
04/23/2010 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) SCREEN WALL FOOTING APPROX 75 L.F.; SE CORNER OF SITE OK TO POUR PROGRESS AREAS
04/09/2010 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) NORTH WEST PORTION OF SCREEN WALL FOOTINGS-OK TO POUR
04/07/2010 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
10 PIER WALL COLUMN FOOTINGS; APPROX. 110'
SCREEN WALL FOOTINGS OK TO POUR PROGRESS AREAS
03/30/2010 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) COMPRESSOR PAD ON ROOF PER DETAIL #260 ON REVISED SHELL BLDG PLANS-OK TO POUR PAD
02/18/2010 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) COLUMN FOOTINGS-DRY PACKED-15 COLUMNS (SE PORTION)
02/10/2010 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) 11 AT LIGHT POLE CAISSON FOOTINGS-DETAILS #A, A1 OK TO POUR FOOTINGS (PAGE E-7)
01/28/2010 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) COLUMN FOOTINGS (DRY-PACK) H 1-2.1; J/2-2.1, J/2-2.8 OK TO POUR FOOTINGS WHEN DRY
12/24/2009 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) 3 COLUMN FOOTINGS (6 #5'S EACH WAY) SOUTHEAST AND MID STAIRS AREA-OK TO POUR FOOTINGS
12/18/2009 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) ELEVATOR PIT AND SUMP PIT; DETAILS #108 & 109 PAGE S3.0 OK TO POUR PROGRESS AREAS
12/01/2009 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) COLUMN FOOTINGS GL 3/A-D; F/3-3.3; 3/F-G; G/2.7, A/1.1-2.2 (4) OK TO POUR PROGRESS AREAS
11/30/2009 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) COLUMN FOOTINGS: GL G.1/4; F2/C6; F2/C1; H/4; P/4-5.5; F2/C7 (3) OK TO POUR PROGRESS AREAS
11/25/2009 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) LINE 1/D-P; 3 F4/C1; 3 F3/C1; 1 F1/C5 FOOTINGS; LINE 3/L-N; 1-F4/C1, 1-F3/C1, LINE H.6/3.5 1 AT F3/C1; 1 AT F1/C5; LINE J/5 1 F5/C2; LINE 5/K-L 2 AT F4/C1 FOOTINGS; LINE H/6 1 AT F3/C1; LINE H.6/7-K/7 2 AT F3/C1 FOOTINGS-OK TO POUR PROGRESS AREAS
11/19/2009 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) COLUMN FOOTINGS C1/F4 (2) LINE K/2.1, L/2.1; C1/F4 LINE G.1/2.1; 4.1/2.1; C4 J.2/2.8-2.1 (2); C4 H.1/2.1 (1); C1/F3 LINE K/3 (1); C1/F3 LINE H.6/3.5 (1); F/8 FOOTING CONTAINS C4 FOOTINGS (3) OK TO POUR PROGRESS AREAS
11/18/2009 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) FOOTINGS AT LINES B/1-2.2; B/1.3; F6, F2; COLUMN FOOTINGS C1/F4 LINE C/2.1, F5/C1 LINE D/2.1; F5/C LINE E/2.1; FOOTING F6 LINES N/7-5.1; F2/C1 LINE N/4 OK TO POUR PROGRESS AREAS