Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T08CM00514
Permit Details
Apply Date:
02/14/2008
Applicant:
METRO PERMIT EXPRESS, INC *C
Description:
NEW PARKING GARAGE
Contractors:
- LEDCOR CONSTRUCTION INC
Permit Reviews
Permit Number - T08CM00514
Permit Status: C of o
Permit Description: NEW PARKING GARAGE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/14/2008 | PLANS OK TO SUBMIT - 3RD PARTY | 03/05/2008 | COMPLETED |
03/05/2008 | 3RD PARTY REVIEW-COMMERCIAL | 05/01/2008 | COMPLETED |
05/01/2008 | POST 3RD PARTY REVIEW | 05/30/2008 | COMPLETED |
05/30/2008 | RESUBMITTAL | 05/30/2008 | COMPLETED |
09/08/2008 | 3RD PARTY REVIEW-REVISION/OTHER | 09/11/2008 | COMPLETED |
09/15/2008 | 3RD PARTY REVIEW-REVISION/OTHER-2ND | 10/20/2008 | COMPLETED |
10/15/2009 | REVISION - - 1ST | 10/15/2009 | COMPLETED |
10/24/2008 | 3RD PARTY REVIEW-REVISION/OTHER | 10/24/2008 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T08CM00514
Permit Status: C of o
Permit Description: NEW PARKING GARAGE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
02/14/2008 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T08CM00514
Permit Description: NEW PARKING GARAGE
Total Completed Inspections - 33
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/11/2008 | STEM WALL/RETAINING WALL | AQUIROZ | Approved | IVRS - Inspection :* 50' WEST OF G.L 1.0/A.0-0A |
10/15/2008 | ELECTRIC - UNDERGROUND | RHOLLAND | Approved | IVRS - Inspection :* OK 7-3/4", 1 - 1", 1 - 1 1/4" PVC CONDUITS SOUTH & WEST HALF |
10/30/2008 | EXCAVATION/LAYOUT REBAR & ZON | LHANLY | Approved | IVRS - Inspection :* |
10/31/2008 | BUILDING PRE-SLAB | GDABBS | Approved | IVRS - Inspection :* PEDESTRIAN BRIDGE FLOOR REINFORCMENT STEEL OK TO PLACE WHAT SPECIAL INSP. APPROVES |
11/05/2008 | REINFORCED MASONRY PRE-GROUT | AQUIROZ | Approved | 1ST LIFT OK |
11/18/2008 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection :* BLDG. DRAIN TO BLDG. SEWER CONNECTION MADE OK |
11/20/2008 | BUILDING - PROGRESS | AQUIROZ | Approved | IVRS - Inspection :* CANCELED |
11/20/2008 | PLUMBING - PROGRESS | BBENEDON | Approved | IVRS - Inspection :* |
12/18/2008 | ELECTRIC - INTERMEDIATE | RHOLLAND | Approved | IVRS - Inspection :* 1) PLEASE VERIFY RESISTANCE OF GROUNDING ELECTRODE PER 250.56 |
12/19/2008 | TEP CLEARANCE - AM | JWEATHER | Approved | TMPP CLEARED PER R. HOLLANDER |
09/16/2009 | OUTDOOR LIGHTING FINAL | DSANTACR | Approved | |
09/16/2009 | ELECTRIC - PROGRESS | DSANTACR | Approved | |
09/16/2009 | ELECTRIC - UFER | DSANTACR | Approved | |
09/16/2009 | ELECTRIC - OUTDOOR LIGHTING | DSANTACR | Approved | |
09/16/2009 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
09/24/2009 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | |
09/24/2009 | PLUMBING - PRE SLAB | RMYERS | Approved | |
09/24/2009 | PLUMBING - ROOF DRAINS | RMYERS | Approved | |
09/24/2009 | PLUMBING - YARD WTR LINE/TEST | RMYERS | Approved | |
09/24/2009 | PLUMBING - BACK WATER VALVE | RMYERS | Approved | |
09/24/2009 | PLUMBING - FINAL | RMYERS | Approved | 1) HANGERS TO BE INSTALLED WITHIN 18" EACH SIDE OF THE COUPLING 2) EXTEND VENT AT ELEVATOR SHAFT TO ABOVE PARAPET 3) HANGER MAY NOT BE INSTALLED ON COUPLING 4) RAISE CLEANOUTS HALF BURRIED IN ASPHALT 5) FLASH SYSTEM AND BREAK OFF RETAINING SCREW AT HOSE BIBBS 6) PROVIDE BACKFLOW CERT FOR RPPBP |
10/05/2009 | RIGHT OF WAY - FINAL | MOTERO | Approved | PER EMAIL |
10/05/2009 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | |
10/05/2009 | MECHANICAL - PROGRESS | MRAMBER | Approved | |
10/05/2009 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
10/05/2009 | SIGN - FINAL | JYBARRA | Approved | |
10/06/2009 | FIRE - FINAL | LTHOMAS | Approved | |
10/06/2009 | FIRE - ALARM FINAL | LTHOMAS | Approved | |
10/06/2009 | FIRE SPKLR - OH PIPING & HYDRO | LTHOMAS | Approved | |
12/02/2009 | ENGINEERING - FINAL | MRUSSO | Approved | |
12/29/2009 | BUILDING - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |
02/04/2010 | NPPO - FINAL | ACONNOR | Approved | |
02/04/2010 | LANDSCAPE - FINAL | ACONNOR | Approved |