Permit: T08BU00687
Permit Details
Apply Date:
04/09/2008
Applicant:
N/A
Description:
GRADING:2050CY CUT 2000 CY FILL
Contractors:
- G AND J DEVELOPMENT INC ,
Permit Reviews
Permit Number - T08BU00687
Permit Status: Final
Permit Description: GRADING:2050CY CUT 2000 CY FILL
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/09/2008 | PLANS OK TO SUBMIT - GRADING | 04/10/2008 | COMPLETED |
04/10/2008 | GRADING | 05/16/2008 | COMPLETED |
08/26/2008 | REVISION - GRADING | 08/26/2008 | COMPLETED |
10/09/2008 | RESUBMITTAL - GRADING ALL | 03/20/2009 | COMPLETED |
10/31/2008 | REVISION - GRADING | 10/31/2008 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T08BU00687
Permit Status: Final
Permit Description: GRADING:2050CY CUT 2000 CY FILL
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
04/09/2008 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T08BU00687
Permit Description: GRADING:2050CY CUT 2000 CY FILL
Total Completed Inspections - 7
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/22/2008 | ENGINEERING PRE-CONSTRUCTION | MAVERY | Approved | Complete pre-con meeting with Danny 440-7775. |
06/02/2008 | STORMWATER INSTALL OF CONTROLS | MAVERY | Approved | Contractor complete controls and provided first inspection. |
09/30/2008 | STORMWATER FOLLOW-UP INSP | JBRUCKME | Approved | ON SITE EVALUATION WITH ELIZABETH EBERBACH AND DAN/G&J CONST. REVIEWED REQUIREMENTS FOR C OF O FOR BUFFALO WILD WINGS. 1. COMPLETE ALL SITE WORK OUTSIDE OF CONSTRUCTION FENCE. 2. PROVIDE CONSTRUCTION FENCE ON UN-BUILT LOTS. 3. PROVIDE ALL SWPPP BMP'S FOR UN-BUILT LOTS. 4. GRADE STOCKPILE TO MAX. HEIGHT OF 6'. 5. PROVIDE SIGNAGE PER THE TRAFFIC PLAN. RIGHT TURN ONLY SIGN NEEDED UNTIL CONSTRUCTION OF MEDIAN ISLAND ON IRVINGTON. 6. PROVIDE DSMR FOR TRASH ENCLOSURE AT SOUTHWEST CORNER OF SITE. 7. CONSTRUCT A.D.A. RAMPS WITH TRUNCATED DOMES. 8. CONSTRUCT DRAINAGE SWALE WITH ROCK CHECK DAMS ON WEST PERIMETER. |
10/17/2008 | GRADING - INTERMEDIATE | MAVERY | Approved | Contractor placed rebar for trash enclosure pad. #4 on 12" Centers. |
11/07/2008 | LANDSCAPE INSPECTION | ACONNOR | Approved | |
06/09/2009 | GRADING - CHECK FOR ACTIVITY | ELEIBOLD | Approved | PER INSPECTION IN T08BU01954 - Approved DSMR # 09-14 referenced on plans for change in dimensions of Buffalo Wild Wings solid waste dumpster. See As-built approved 9JUN09. This as-built ("final grading plan") is intended to close out both T08BU00687 & T08BU01954. |
11/30/2009 | GRADING - FINAL | eleibol1 | Approved | Basin has been recontructed for positive drainage and inspected for acceptance. |