Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Approved
Inspection History: GRADING - INTERMEDIATE
| Date |
Description |
Inspector |
Results |
Comments |
| 06/09/2009 |
GRADING - INTERMEDIATE |
|
Approved |
PER INSPECTION IN T08BU01954 - Approved DSMR # 09-14 referenced on plans for change in dimensions of Buffalo Wild Wings solid waste dumpster. See As-built approved 9JUN09. This as-built ("final grading plan") is intended to close out both T08BU00687 & T08BU01954. |
| 02/04/2009 |
GRADING - INTERMEDIATE |
|
Partial Approval |
Contractor graded area t stop standing water on northeast side. Engineer wants to install bleeder pipe in basin area. Will need to submit revision to EL. |
| 10/17/2008 |
GRADING - INTERMEDIATE |
|
Partial Approval |
Contractor placed rebar for trash enclosure pad. #4 on 12" Centers. |
| 09/25/2008 |
GRADING - INTERMEDIATE |
|
Partial Approval |
Met on site with Danny site super in regards to trash enclosures. OK to place concrete for footer. |
| 09/22/2008 |
GRADING - INTERMEDIATE |
|
Partial Approval |
Met with Danny site super in regards to Trash enclosures. Contractor needs to build per DS. Contractor work off plan that is not approved, all work at risk. |
| 09/19/2008 |
GRADING - INTERMEDIATE |
|
Partial Approval |
Met with Danny on site. Contractor wants to open Pad 1 for business before site is complete. I told Danny he needs to speck to EE down at 201 N. Stone. |
| 09/15/2008 |
GRADING - INTERMEDIATE |
|
Partial Approval |
Met on site with Danny site super. Contractor needs to maintain 24' PAALs for two way traffic. If PAALs are less then 24' contractor will need to obtain DSMR. |
| 08/19/2008 |
GRADING - INTERMEDIATE |
|
Correction Required |