Permit Details

Status:
C of o
Type:
COMMERCIAL NEW
Address NEW:
9685 E BROADWAY BL 16
Apply Date:
12/11/2007
Applicant:
CARMAN LOPEZ
Description:
NEW A-ATLAS DISCOUNT STORAGE BLDG # 16 (OFFICE)
Contractors:
  • SIERRA LAND SURVEYING AND DEVELO

Permit Reviews

Permit Number - T07CM04612
Permit Status: C of o
Permit Description: NEW A-ATLAS DISCOUNT STORAGE BLDG # 16 (OFFICE)
Start Date Submittal Complete Date Status  
01/15/2008 POST 3RD PARTY REVIEW 01/15/2008 COMPLETED Review Details
09/08/2008 3RD PARTY REVIEW-REVISION/OTHER 09/15/2008 COMPLETED Review Details
12/11/2007 PLANS OK TO SUBMIT - 3RD PARTY 12/11/2007 COMPLETED Review Details
12/11/2007 3RD PARTY REVIEW-COMMERCIAL TI 01/15/2008 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T07CM04612
Permit Status: C of o
Permit Description: NEW A-ATLAS DISCOUNT STORAGE BLDG # 16 (OFFICE)
Total Outstanding Activity Conditions - 1
Date Name
12/11/2007 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T07CM04612
Permit Description: NEW A-ATLAS DISCOUNT STORAGE BLDG # 16 (OFFICE)
Total Completed Inspections - 41
Date Description Inspector Results Comments
03/11/2008 PLUMBING - ROUGH, SOIL BBENEDON Approved IVRS - Inspection :*
04/01/2008 BUILDING PRE-SLAB JBURGE Approved IVRS - Inspection :*
OK TO POUR
04/01/2008 EXCAVATION/LAYOUT REBAR & ZON JBURGE Approved IVRS - Inspection :*
CONTINUOUS FOOTING FOR OFFICE AND GARAGE OK TO POUR
04/01/2008 EXCAVATION/LAYOUT REBAR & ZON JBURGE Approved IVRS - Inspection :*
04/02/2008 PLUMBING - PRE SLAB RLEDONNE Approved IVRS - Inspection :*
04/24/2008 PLUMBING - SEWER HCS CONNECT RRICH Approved IVRS - Inspection :*
CONNECTION TO BLD AND CLEANOUT OK
06/16/2008 FRAMING JBURGE Approved IVRS - Inspection :*
AS PER PLANS
06/16/2008 ROOF NAILING JBURGE Approved IVRS - Inspection :*
OK TO DRY IN
06/16/2008 EXT METAL CLIPS/EXT SHEATHING JBURGE Approved IVRS - Inspection :*
OK TO COVER
06/30/2008 MECHANICAL - ABOVE CEILING JMILITEL Approved IVRS - Inspection :*
06/30/2008 MECHANICAL - INTERMEDIATE JMILITEL Approved IVRS - Inspection :*
1. PROVIDE BACKING FOR REGISTER BOX TO BATHROOM
2. INSULATE ALL TAPERED SIDE WALL REGISTER BOXES
PRIOR TO SHEETROCK
07/11/2008 U VALUE FOR WINDOW JBURGE Approved IVRS - Inspection :*
U.VALUE @ .52
07/11/2008 BUILDING ABOVE CEILING JBURGE Approved IVRS - Inspection :*
OK TO COVER HARD LIDS THROUGHOUT
07/11/2008 PLUMBING - ABOVE CEILING BBENEDON Approved IVRS - Inspection :*
07/16/2008 ELECTRIC - ABOVE CEILING RJIROUDE Approved IVRS - Inspection :*
07/16/2008 ELECTRIC - INTERMEDIATE RJIROUDE Approved IVRS - Inspection :*
07/30/2008 SHEET ROCK NAILING GDABBS Approved IVRS - Inspection :*
08/06/2008 STUCCO MESH JBURGE Approved IVRS - Inspection :*
OK TO STUCCO
09/16/2008 PLUMBING - GAS PRESS TEST FNL BBENEDON Approved IVRS - Inspection :*
09/16/2008 PLUMBING - GAS PRESSURE TEST BBENEDON Approved IVRS - Inspection :*
10/10/2008 MECHANICAL - FINAL JMILITEL Approved IVRS - Inspection :*
10/10/2008 PLUMBING - YARD WTR LINE/TEST BBENEDON Approved IVRS - Inspection :*
10/10/2008 PLUMBING - INTERMEDIATE BBENEDON Approved IVRS - Inspection :*
10/10/2008 SITE - SEWER BBENEDON Approved IVRS - Inspection :*
10/13/2008 TEP CLEARANCE - AM DSANTACR Approved TEC CLEARED FOR #16 PER D. SANTACRUZ-2ND TIME SENT TO TEP
10/13/2008 ELECTRIC - TEMP POWER FOR TEST DSANTACR Approved IVRS - Inspection :*
10/13/2008 ELECTRIC - CABLE DROP DSANTACR Approved IVRS - Inspection :*
11/19/2008 BUILDING - FINAL JBURGE Approved IVRS - Inspection :*
PENDING FIRE FINAL
11/19/2008 ELECTRIC - UFER RMORENO Approved
11/19/2008 ELECTRIC - FINAL RMORENO Approved IVRS - Inspection :*
OK BATH FIXTURE GROUNDED, WATER FITTINGS TIGHT, DISCONNECTS LABELED, GFI IN BACK OF DWELLING,
ROOF - OK DISCONNECT, RANGE AND WALL AC INSTALLED.
11/19/2008 OUTDOOR LIGHTING FINAL RMORENO Approved IVRS - Inspection :*
11/19/2008 ELECTRIC - OUTDOOR LIGHTING RMORENO Approved IVRS - Inspection :*
11/19/2008 PLUMBING - FINAL BBENEDON Approved IVRS - Inspection :*
11/20/2008 ENGINEERING - FINAL JBRUCKME Approved NOT READY
1. COMPLETE ALL SITE WORK IN CONFORMANCE WITH THE FINAL APPROVED GRADING PLAN.
2. PROVIDE A LETTER OF CERTIFICATION AND REPORTS FROM THE ARIZONA REGISTERED P.E. THAT CERTIFYS THAT THE PROJECT IS CONSTRUCTED TO THE FINAL APPROVED GRADING PLAN. PER DEVELOPMENT STANDARD 11-01.16.0
3. COMPLETE ALL PEDESTRIAN AND VEHICLE ACCESS CONSTRUCTION, PAVEMENT,CURBS, SIDEWALKS, A.D.A. ACCESSABILITY AND DRAINAGE IMPROVEMENTS.
11/20/2008 FIRE - HYDRANTS CSCHULTZ Approved APPROVED FOR OFFICE ONLY
11/20/2008 FIRE - FINAL CSCHULTZ Approved TEMP C of O APPROVED
11/21/2008 NPPO - FINAL ACONNOR Approved
11/21/2008 LANDSCAPE - FINAL ACONNOR Approved
02/26/2009 RIGHT OF WAY - FINAL PWHIDDON Approved PER EMAIL
03/17/2009 SIGN - FINAL JYBARRA Approved IVRS - Inspection :*
03/18/2009 PERMIT FINALED LJACKSON Approved