Permit: T07CM04612

Parcel: 133369680

Inspection Status: Approved

Inspection History: ENGINEERING - FINAL

Permit Number - T07CM04612

Inspection Description - ENGINEERING - FINAL

Inspection Status - Approved

Date Description Inspector Results Comments
03/12/2009 ENGINEERING - FINAL Approved SEE T07BU00756 FOR AP 1. COMPLETE ALL SITE WORK IN CONFORMANCE WITH THE FINAL APPROVED GRADING PLAN.
SEE T07BU00756 FOR AP 2. PROVIDE A LETTER OF CERTIFICATION AND REPORTS FROM THE ARIZONA REGISTERED P.E. THAT CERTIFYS THAT THE PROJECT IS CONSTRUCTED TO THE FINAL APPROVED GRADING PLAN. PER DEVELOPMENT STANDARD 11-01.16.0
ALL WORK CP- H/C PKNG SIGN HAS BEEN RAISED TO 7' 3. COMPLETE ALL PEDESTRIAN AND VEHICLE ACCESS CONSTRUCTION, PAVEMENT,CURBS, SIDEWALKS, A.D.A. ACCESSABILITY AND DRAINAGE IMPROVEMENTS.
11/20/2008 ENGINEERING - FINAL Denied NOT READY
1. COMPLETE ALL SITE WORK IN CONFORMANCE WITH THE FINAL APPROVED GRADING PLAN.
2. PROVIDE A LETTER OF CERTIFICATION AND REPORTS FROM THE ARIZONA REGISTERED P.E. THAT CERTIFYS THAT THE PROJECT IS CONSTRUCTED TO THE FINAL APPROVED GRADING PLAN. PER DEVELOPMENT STANDARD 11-01.16.0
3. COMPLETE ALL PEDESTRIAN AND VEHICLE ACCESS CONSTRUCTION, PAVEMENT,CURBS, SIDEWALKS, A.D.A. ACCESSABILITY AND DRAINAGE IMPROVEMENTS.