Permit: T07CM04612
Permit Details
Apply Date:
12/11/2007
Applicant:
CARMAN LOPEZ
Description:
NEW A-ATLAS DISCOUNT STORAGE BLDG # 16 (OFFICE)
Contractors:
- SIERRA LAND SURVEYING AND DEVELO
Permit Reviews
Permit Number - T07CM04612
Permit Status: C of o
Permit Description: NEW A-ATLAS DISCOUNT STORAGE
BLDG # 16 (OFFICE)
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/15/2008 | POST 3RD PARTY REVIEW | 01/15/2008 | COMPLETED |
09/08/2008 | 3RD PARTY REVIEW-REVISION/OTHER | 09/15/2008 | COMPLETED |
12/11/2007 | PLANS OK TO SUBMIT - 3RD PARTY | 12/11/2007 | COMPLETED |
12/11/2007 | 3RD PARTY REVIEW-COMMERCIAL TI | 01/15/2008 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T07CM04612
Permit Status: C of o
Permit Description: NEW A-ATLAS DISCOUNT STORAGE
BLDG # 16 (OFFICE)
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
12/11/2007 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T07CM04612
Permit Description: NEW A-ATLAS DISCOUNT STORAGE
BLDG # 16 (OFFICE)
Total Completed Inspections - 41
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/11/2008 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | IVRS - Inspection :* |
04/01/2008 | BUILDING PRE-SLAB | JBURGE | Approved | IVRS - Inspection :* OK TO POUR |
04/01/2008 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | IVRS - Inspection :* CONTINUOUS FOOTING FOR OFFICE AND GARAGE OK TO POUR |
04/01/2008 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | IVRS - Inspection :* |
04/02/2008 | PLUMBING - PRE SLAB | RLEDONNE | Approved | IVRS - Inspection :* |
04/24/2008 | PLUMBING - SEWER HCS CONNECT | RRICH | Approved | IVRS - Inspection :* CONNECTION TO BLD AND CLEANOUT OK |
06/16/2008 | FRAMING | JBURGE | Approved | IVRS - Inspection :* AS PER PLANS |
06/16/2008 | ROOF NAILING | JBURGE | Approved | IVRS - Inspection :* OK TO DRY IN |
06/16/2008 | EXT METAL CLIPS/EXT SHEATHING | JBURGE | Approved | IVRS - Inspection :* OK TO COVER |
06/30/2008 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
06/30/2008 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* 1. PROVIDE BACKING FOR REGISTER BOX TO BATHROOM 2. INSULATE ALL TAPERED SIDE WALL REGISTER BOXES PRIOR TO SHEETROCK |
07/11/2008 | U VALUE FOR WINDOW | JBURGE | Approved | IVRS - Inspection :* U.VALUE @ .52 |
07/11/2008 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* OK TO COVER HARD LIDS THROUGHOUT |
07/11/2008 | PLUMBING - ABOVE CEILING | BBENEDON | Approved | IVRS - Inspection :* |
07/16/2008 | ELECTRIC - ABOVE CEILING | RJIROUDE | Approved | IVRS - Inspection :* |
07/16/2008 | ELECTRIC - INTERMEDIATE | RJIROUDE | Approved | IVRS - Inspection :* |
07/30/2008 | SHEET ROCK NAILING | GDABBS | Approved | IVRS - Inspection :* |
08/06/2008 | STUCCO MESH | JBURGE | Approved | IVRS - Inspection :* OK TO STUCCO |
09/16/2008 | PLUMBING - GAS PRESS TEST FNL | BBENEDON | Approved | IVRS - Inspection :* |
09/16/2008 | PLUMBING - GAS PRESSURE TEST | BBENEDON | Approved | IVRS - Inspection :* |
10/10/2008 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
10/10/2008 | PLUMBING - YARD WTR LINE/TEST | BBENEDON | Approved | IVRS - Inspection :* |
10/10/2008 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* |
10/10/2008 | SITE - SEWER | BBENEDON | Approved | IVRS - Inspection :* |
10/13/2008 | TEP CLEARANCE - AM | DSANTACR | Approved | TEC CLEARED FOR #16 PER D. SANTACRUZ-2ND TIME SENT TO TEP |
10/13/2008 | ELECTRIC - TEMP POWER FOR TEST | DSANTACR | Approved | IVRS - Inspection :* |
10/13/2008 | ELECTRIC - CABLE DROP | DSANTACR | Approved | IVRS - Inspection :* |
11/19/2008 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* PENDING FIRE FINAL |
11/19/2008 | ELECTRIC - UFER | RMORENO | Approved | |
11/19/2008 | ELECTRIC - FINAL | RMORENO | Approved | IVRS - Inspection :* OK BATH FIXTURE GROUNDED, WATER FITTINGS TIGHT, DISCONNECTS LABELED, GFI IN BACK OF DWELLING, ROOF - OK DISCONNECT, RANGE AND WALL AC INSTALLED. |
11/19/2008 | OUTDOOR LIGHTING FINAL | RMORENO | Approved | IVRS - Inspection :* |
11/19/2008 | ELECTRIC - OUTDOOR LIGHTING | RMORENO | Approved | IVRS - Inspection :* |
11/19/2008 | PLUMBING - FINAL | BBENEDON | Approved | IVRS - Inspection :* |
11/20/2008 | ENGINEERING - FINAL | JBRUCKME | Approved | NOT READY 1. COMPLETE ALL SITE WORK IN CONFORMANCE WITH THE FINAL APPROVED GRADING PLAN. 2. PROVIDE A LETTER OF CERTIFICATION AND REPORTS FROM THE ARIZONA REGISTERED P.E. THAT CERTIFYS THAT THE PROJECT IS CONSTRUCTED TO THE FINAL APPROVED GRADING PLAN. PER DEVELOPMENT STANDARD 11-01.16.0 3. COMPLETE ALL PEDESTRIAN AND VEHICLE ACCESS CONSTRUCTION, PAVEMENT,CURBS, SIDEWALKS, A.D.A. ACCESSABILITY AND DRAINAGE IMPROVEMENTS. |
11/20/2008 | FIRE - HYDRANTS | CSCHULTZ | Approved | APPROVED FOR OFFICE ONLY |
11/20/2008 | FIRE - FINAL | CSCHULTZ | Approved | TEMP C of O APPROVED |
11/21/2008 | NPPO - FINAL | ACONNOR | Approved | |
11/21/2008 | LANDSCAPE - FINAL | ACONNOR | Approved | |
02/26/2009 | RIGHT OF WAY - FINAL | PWHIDDON | Approved | PER EMAIL |
03/17/2009 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
03/18/2009 | PERMIT FINALED | LJACKSON | Approved |