Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Final
Type:
COMMERCIAL NEW
Address NEW:
3945 E FORT LOWELL RD
Apply Date:
11/06/2007
Applicant:
RIO WEST DEVELOPMENT AND CONSTRU
Description:
NEW SHELL BUILDING:2 STORY OFFICE
Architects:
  • CHAVEZ, MARIO SALAS
Contractors:
  • RIO WEST DEVELOPMENT AND CONSTRU

Permit Reviews

Permit Number - T07CM04289
Permit Status: Final
Permit Description: NEW SHELL BUILDING:2 STORY OFFICE
Start Date Submittal Complete Date Status  
01/09/2008 RESUBMITTAL 01/10/2008 COMPLETED Review Details
02/12/2008 3RD PARTY REVIEW-REVISION/OTHER 02/13/2008 COMPLETED Review Details
04/04/2008 3RD PARTY REVIEW-REVISION/OTHER 04/08/2008 COMPLETED Review Details
07/03/2008 3RD PARTY REVIEW-REVISION/OTHER 07/07/2008 COMPLETED Review Details
11/06/2007 PLANS OK TO SUBMIT - 3RD PARTY 11/06/2007 COMPLETED Review Details
11/06/2007 3RD PARTY REVIEW-COMMERCIAL 12/03/2007 COMPLETED Review Details
11/13/2008 3RD PARTY REVIEW-REVISION/OTHER 11/17/2008 COMPLETED Review Details
11/21/2008 3RD PARTY REVIEW-REVISION/OTHER-2ND 11/21/2008 COMPLETED Review Details
12/03/2007 POST 3RD PARTY REVIEW 01/03/2008 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T07CM04289
Permit Status: Final
Permit Description: NEW SHELL BUILDING:2 STORY OFFICE
Total Outstanding Activity Conditions - 1
Date Name
11/06/2007 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: Final
Permit Number: T07CM04289
Permit Description: NEW SHELL BUILDING:2 STORY OFFICE
Total Completed Inspections - 47
Date Description Inspector Results Comments
01/28/2008 STEM WALL/RETAINING WALL JBURGE Approved IVRS - Inspection :*
STEM WALLS @ 24" - BLDG 3E & 3W
02/07/2008 SITE - SEWER BBENEDON Approved IVRS - Inspection :*
02/07/2008 PLUMBING - PRE SLAB BBENEDON Approved IVRS - Inspection :*
02/07/2008 PLUMBING - ROUGH, SOIL BBENEDON Approved IVRS - Inspection :*
03/07/2008 EXCAVATION/LAYOUT REBAR & ZON JBURGE Approved IVRS - Inspection :*
04/04/2008 BUILDING PRE-SLAB JBURGE Approved IVRS - Inspection :*
2ND FLOOR BLDG 3 WEST & PASSAGEWAY
LINES A-D, 1-4; OK TO POUR
05/30/2008 REINFORCED MASONRY PRE-GROUT JBURGE Approved IVRS - Inspection :*
MASONRY WORK COMPLETE (ELEVATOR UTILITY ROOM)
06/05/2008 FRAMING JBURGE Approved IVRS - Inspection :*
2ND FLOOR WEST, SHEAR WALL, PARAPET WALL; 1ST FLOOR ELEVATOR CANOPY
06/12/2008 PLUMBING - SEWER HCS CONNECT BBENEDON Approved IVRS - Inspection :*
ADEQ PO65807
06/12/2008 FIRE SPKLR - UG PIPING FLUSH LTHOMAS Approved
06/12/2008 FIRE SPKLR - UG, PIPING, HYDRO LTHOMAS Approved
06/19/2008 SHEET ROCK NAILING JBURGE Approved IVRS - Inspection :*
07/23/2008 MECHANICAL - INTERMEDIATE JMILITEL Approved IVRS - Inspection :*
CHECKED REFER LINES. OK TO COVER.
PROVIDE BUSHINGS IN METAL STUDS.
WILL CHECK ON FINAL.
07/23/2008 ELECTRIC - INTERMEDIATE DSANTACR Approved IVRS - Inspection :*
OK SOFFIT EXTERIOR ROUGH
07/25/2008 EXT METAL CLIPS/EXT SHEATHING JBURGE Approved IVRS - Inspection :*
OK TO COVER (EAST & WEST BUILDINGS)
07/31/2008 ROOF NAILING JBURGE Approved ROOFING SYSTEM COMPLETE - OK TO COVER (BLDG. 3 WEST)
08/13/2008 U VALUE FOR WINDOW JBURGE Approved IVRS - Inspection :*
BLDGS. 4 EAST & WEST
08/14/2008 STUCCO MESH JBURGE Approved IVRS - Inspection :*
BLDG #8 WEST & ELEVATOR SHAFT
08/14/2008 PLUMBING - ROOF DRAINS BBENEDON Approved IVRS - Inspection :*
08/19/2008 FIRE SPKLR - OH PIPING & HYDRO LTHOMAS Approved
09/11/2008 ELECTRIC - UNDERGROUND RJIROUDE Approved IVRS - Inspection :*
1. NEED TO POST ADDRESS
2. OK U.G RACEWAYS FROM TEP XFMR TO SES LOCATION
3. OK U.G FOR TELEPHONE
4. INSTALL WARNING RIBBON PER NEC 300.5
5. NEED TO REVISE PLANS FOR CHANGES IN SERVICE TO "3B"
09/11/2008 ELECTRIC - CABLE DROP RJIROUDE Approved IVRS - Inspection :*
09/24/2008 PLUMBING - YARD WTR LINE/TEST BBENEDON Approved IVRS - Inspection :*
09/24/2008 SIGN - FINAL JYBARRA Approved
10/06/2008 MECHANICAL - PROGRESS JMILITEL Approved IVRS - Inspection :*
CHECKED DRY WELLS & RELATED CONDENSATE PIPING
10/15/2008 MECHANICAL - FINAL JMILITEL Approved IVRS - Inspection :*
10/20/2008 ELECTRIC - UFER DSANTACR Approved IVRS - Inspection :*
OK GROUND RODS, WATER BOND
10/29/2008 ELECTRIC - CONSTRUCTION POWER RJIROUDE Approved IVRS - Inspection :*
11/07/2008 ELECTRIC - TEMP POWER FOR TEST RJIROUDE Approved IVRS - Inspection :*
1) STILL NEED TO BOND SPRINKLER AND BLDG STEEL
2) NEED LOAD REVISIONS FOR HOUSE PANEL #2 BLDG 3A
3) NEED 22 KAIC BREAKERS IN HOUSE PANEL PER PLANS
11/07/2008 ELECTRIC - PROGRESS RJIROUDE Approved IVRS - Inspection :*
11/12/2008 TEP CLEARANCE - AM JWEATHER Approved TEC CLEARED FOR "OWNERS PANEL 2" PER R. JIROUDEK
11/13/2008 RIGHT OF WAY - FINAL PWHIDDON Approved
11/13/2008 NPPO - FINAL ACONNOR Approved
11/13/2008 LANDSCAPE - FINAL ACONNOR Approved
11/20/2008 PLUMBING - FINAL BBENEDON Approved IVRS - Inspection :*
REMOVE GALV NIPPLES AT HB's
INSTALL NON-FERROUS PIPE NIPPS ON COPPER PIPING SYSTEMS
11/20/2008 PLUMBING - INTERMEDIATE BBENEDON Approved IVRS - Inspection :*
11/20/2008 PLUMBING - PROGRESS BBENEDON Approved IVRS - Inspection :*
11/20/2008 PLUMBING - BACK WATER VALVE BBENEDON Approved IVRS - Inspection :*
11/24/2008 FIRE - ALARM FINAL LTHOMAS Approved
11/24/2008 FIRE SPKLR - FINAL LTHOMAS Approved
11/24/2008 FIRE - FINAL LTHOMAS Approved
11/26/2008 BUILDING - FINAL JBURGE Approved IVRS - Inspection :*
1) TRADES AND FIRE FINALS COMPLETE-ELEVATORS CERTIFIED
11/26/2008 BUILDING - PROGRESS JBURGE Approved IVRS - Inspection :*
12/04/2008 OUTDOOR LIGHTING FINAL RJIROUDE Approved IVRS - Inspection :*
CANCELED BY CONTRACTOR
12/04/2008 ELECTRIC - FINAL RJIROUDE Approved IVRS - Inspection :*
CANCELED BY CONTRACTOR
12/04/2008 ELECTRIC - OUTDOOR LIGHTING RJIROUDE Approved IVRS - Inspection :*
CANCELED BY CONTRACTOR
12/18/2008 ENGINEERING - FINAL JFEMLING Approved OK for shell, chk for bike parking on final for TI