Permit: T07CM03248
Permit Details
Apply Date:
08/02/2007
Applicant:
J G CONSTRUCTION L L C
Description:
NEW TOWNHOME
Contractors:
- J G CONSTRUCTION L L C
Permit Reviews
Permit Number - T07CM03248
Permit Status: C of o
Permit Description: NEW TOWNHOME
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/02/2007 | PLANS OK TO SUBMIT - RES | 08/07/2007 | COMPLETED |
| 08/07/2007 | RESIDENTIAL BLDG/ZONING/ENGINE/WWM | 09/04/2007 | COMPLETED |
| 09/14/2007 | RESUBMITTAL | 09/24/2007 | COMPLETED |
| 09/25/2007 | RESUBMITTAL | 09/26/2007 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T07CM03248
Permit Status: C of o
Permit Description: NEW TOWNHOME
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/02/2007 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T07CM03248
Permit Description: NEW TOWNHOME
Total Completed Inspections - 26
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/04/2007 | PLUMBING - SEWER HCS CONNECT | WNORTH | Approved | |
| 04/07/2008 | PLUMBING - ROUGH, SOIL | DQUINN | Approved | IVRS - Inspection :* |
| 04/15/2008 | BUILDING PRE-SLAB | DQUINN | Approved | IVRS - Inspection :* |
| 04/16/2008 | ELECTRIC - UFER | DQUINN | Approved | |
| 04/16/2008 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | IVRS - Inspection :* |
| 05/28/2008 | U VALUE FOR WINDOW | WNORTH | Approved | IVRS - Inspection :* |
| 05/28/2008 | ROOF NAILING | WNORTH | Approved | IVRS - Inspection :* |
| 05/28/2008 | EXT METAL CLIPS/EXT SHEATHING | WNORTH | Approved | IVRS - Inspection :* |
| 06/18/2008 | STUCCO MESH | DQUINN | Approved | IVRS - Inspection :* |
| 09/17/2008 | BUILDING - FINAL | LHANLY | Approved | VENT ALONG EAST WALL AT RAFTERS IS NOT ALLOWED FOR BUILDING ON PROPERTY LINE. 1 HOUR CONSTRUCTION REQUIRED WITH NO OPENINGS AND NO PROJECTIONS. ROOF DETAIL WITH 1" GAP IS INCORRECT! |
| 10/28/2008 | PLUMBING - YARD WTR LINE/TEST | WNORTH | Approved | |
| 10/28/2008 | PLUMBING - GAS PRESSURE TEST | WNORTH | Approved | IVRS - Inspection :* |
| 10/28/2008 | ELECTRIC - INTERMEDIATE | WNORTH | Approved | IVRS - Inspection :* |
| 12/04/2008 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | IVRS - Inspection :* |
| 12/04/2008 | ELECTRIC - TEMPORARY SERVICE | DQUINN | Approved | IVRS - Inspection :* |
| 12/04/2008 | ELECTRIC - CABLE DROP | DQUINN | Approved | IVRS - Inspection :* |
| 12/05/2008 | TEP CLEARANCE - AM | JWEATHER | Approved | ECO CLEARED PER D. QUINN |
| 12/09/2008 | PLUMBING - INTERMEDIATE | DQUINN | Approved | IVRS - Inspection :* |
| 12/09/2008 | FRAMING | DQUINN | Approved | IVRS - Inspection :* |
| 01/14/2009 | SHEET ROCK NAILING | WLAHR | Approved | IVRS - Inspection :* |
| 02/27/2009 | ASSURANCE | MCARREON | Approved | |
| 05/27/2009 | PLUMBING - FINAL | DQUINN | Approved | IVRS - Inspection :* |
| 05/27/2009 | OUTDOOR LIGHTING FINAL | DQUINN | Approved | IVRS - Inspection :* |
| 05/28/2009 | MECHANICAL - FINAL | DQUINN | Approved | IVRS - Inspection :* |
| 05/28/2009 | ELECTRIC - FINAL | DQUINN | Approved | IVRS - Inspection :* |
| 05/29/2009 | PERMIT FINALED | JWEATHER | Approved |