Permit: T07CM01012
Permit Details
Apply Date:
03/12/2007
Applicant:
ING RUDOLF A
Description:
SITE AND NEW RETAIL BUILDING
Contractors:
- BARKER MORRISSEY CONTRACTING INC
Permit Reviews
Permit Number - T07CM01012
Permit Status: C of o
Permit Description: SITE AND NEW RETAIL BUILDING
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/30/2008 | RESUBMITTAL - SITE ALL | 03/05/2008 | COMPLETED |
02/26/2009 | REVISION - - 3RD | 02/26/2009 | COMPLETED |
03/12/2007 | PLANS OK TO SUBMIT - SITE | 03/13/2007 | COMPLETED |
03/13/2007 | SITE | 05/01/2007 | COMPLETED |
03/13/2009 | REVISION - SITE | 03/17/2009 | COMPLETED |
03/31/2008 | POST 3RD PARTY REVIEW | 04/04/2008 | COMPLETED |
04/04/2008 | POST 3RD PARTY REVIEW | 10/06/2008 | COMPLETED |
04/30/2009 | REVISION - SITE | 05/01/2009 | COMPLETED |
07/13/2007 | PLANS OK TO SUBMIT - 3RD PARTY | 07/13/2007 | COMPLETED |
07/13/2007 | 3RD PARTY REVIEW-COMMERCIAL | 03/31/2008 | COMPLETED |
08/07/2007 | RESUBMITTAL - SITE ALL | 09/07/2007 | COMPLETED |
10/31/2007 | RESUBMITTAL - SITE ALL | 01/30/2008 | COMPLETED |
11/03/2008 | 3RD PARTY REVIEW-REVISION/OTHER | 11/12/2008 | COMPLETED |
11/20/2008 | 3RD PARTY REVIEW-REVISION/OTHER | 12/02/2008 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T07CM01012
Permit Status: C of o
Permit Description: SITE AND NEW RETAIL BUILDING
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
03/12/2007 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T07CM01012
Permit Description: SITE AND NEW RETAIL BUILDING
Total Completed Inspections - 34
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/04/2008 | ELECTRIC - TEMP POWER FOR TEST | RHOLLAND | Approved | IVRS - Inspection : The wiring is not complete or does not comply with code.| 245* 1. GROUNDING ELECTRODE SYSTEMS TO BE AS PER 250.50 & 64 2. FINISH PREVIOUS ITEMS 3. TEMP POWER FOR TEST IS FOR FINISHED BUILDINGS ADD TEMP CONST. POWER |
09/16/2008 | SITE - SEWER | RMYERS | Approved | IVRS - Inspection :* 1. PLANS AND PERMITS TO BE ON SITE (AVAILABLE TO INSPECTOR) AT ALL TIMES. 2. OK TO COVER, SUBJECT TO APPROVED PLAN 3. WATER TEST OK |
10/07/2008 | REINFORCED MASONRY PRE-GROUT | AQUIROZ | Approved | IVRS - Inspection :* TRASH ENCLOSURE OK |
10/10/2008 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection :* |
11/20/2008 | PLUMBING - YARD WTR LINE/TEST | RLEDONNE | Approved | IVRS - Inspection :* |
11/21/2008 | EXCAVATION/LAYOUT REBAR & ZON | AQUIROZ | Approved | IVRS - Inspection :* 2 LIGHT POLE BASES |
11/21/2008 | ELECTRIC - UFER | RHOLLAND | Approved | IVRS - Inspection : The wiring is not complete or does not comply with code.| 245* OK PRIMARY CONDUITS OK 2 POLE BASE 1. NEED ENGINEERED PLANS FOR GROUNDING ELECTRODE SYSTEM - FOOTINGS POURED WITHOUT ELECTRICAL INSPECTION. |
11/21/2008 | ELECTRIC - UNDERGROUND | RHOLLAND | Approved | IVRS - Inspection :* |
11/26/2008 | PLUMBING - PRE SLAB | RMYERS | Approved | OK FOR CONCRETE |
12/12/2008 | BUILDING PRE-SLAB | AQUIROZ | Approved | IVRS - Inspection :* |
12/18/2008 | STEM WALL/RETAINING WALL | AQUIROZ | Approved | IVRS - Inspection :* INFO. ONLY |
01/20/2009 | FIRE - FINAL | LTHOMAS | Approved | |
01/28/2009 | RIGHT OF WAY - FINAL | MOTERO | Approved | PER EMAIL |
02/06/2009 | PLUMBING - PROGRESS | RMYERS | Approved | IVRS - Inspection :* OK TO COVER ALL AREAS |
02/24/2009 | PLUMBING - ROOF DRAINS | RMYERS | Approved | IVRS - Inspection :* 1. GAS NOT INSTALLED PER PLAN. NO REDLINES ON SITE. GAS COVERED WITHOUT INSPECTION. WILL CHECK REDLINES ON PRESSURE TEST FINAL 2. BACKWATER VALVE INSTALLED OK 3. ROOF DRAINS OK |
02/24/2009 | FRAMING | AQUIROZ | Approved | IVRS - Inspection :* |
02/24/2009 | PLUMBING - GAS PRESSURE TEST | RMYERS | Approved | IVRS - Inspection :* |
02/24/2009 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
02/27/2009 | PLUMBING - GAS PRESS TEST FNL | RMYERS | Approved | IVRS - Inspection :* CALL 02035 FOR PLUMBING AT PLANT STORAGE #114 OK FOR GAS, WILL LEAVE GAS CARD ON 03/02/09 |
03/09/2009 | ROOF NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
03/09/2009 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
03/10/2009 | TEP CLEARANCE - PM | BFLORES | Approved | TMPP PER R.HOLLANDER |
03/11/2009 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection :* PLUMBING IN #114 PLANT STORAGE OK TO COVER CLOSET FLANGES OK |
03/19/2009 | SHEET ROCK NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
03/23/2009 | SIGN - FINAL | JYBARRA | Approved | |
03/31/2009 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
04/01/2009 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection :* CONTRACTOR TO INSTALL VACUUM RELIEF AT WATER HEATER |
04/02/2009 | BUILDING - FINAL | AQUIROZ | Approved | IVRS - Inspection :* OK C OF O |
04/03/2009 | ELECTRIC - OUTDOOR LIGHTING | LHANLY | Approved | |
04/03/2009 | ELECTRIC - INTERMEDIATE | LHANLY | Approved | |
04/03/2009 | ELECTRIC - FINAL | AQUIROZ | Approved | |
05/27/2009 | ENGINEERING - FINAL | DROBERTS | Approved | ADA ACCESS QUESTIONALBE BUT APPROVED BY BLDG FINAL |
05/27/2009 | NPPO - FINAL | ACONNOR | Approved | |
05/27/2009 | LANDSCAPE - FINAL | ACONNOR | Approved |