Permit: T07BU00324
Permit Details
Apply Date:
02/09/2007
Applicant:
METRO PERMIT EXPRESS, INC *C
Description:
GRADING AIRPORT PROJECT
Contractors:
- J R TUTTLE CO
Permit Reviews
Permit Number - T07BU00324
Permit Status: Expired
Permit Description: GRADING AIRPORT PROJECT
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/01/2008 | REVISION - GRADING | 04/17/2008 | COMPLETED |
| 02/09/2007 | PLANS OK TO SUBMIT - GRADING | 02/09/2007 | COMPLETED |
| 02/09/2007 | GRADING | 03/30/2007 | COMPLETED |
| 04/17/2008 | REVISION - GRADING | 01/14/2009 | COMPLETED |
| 04/18/2007 | RESUBMITTAL - GRADING ALL | 06/26/2007 | COMPLETED |
| 07/06/2007 | RESUBMITTAL - GRADING ALL | 02/01/2008 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T07BU00324
Permit Status: Expired
Permit Description: GRADING AIRPORT PROJECT
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 02/09/2007 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Outstanding Inspections
Permit Status: Expired
Permit Number: T07BU00324
Permite Description: GRADING AIRPORT PROJECT
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| LANDSCAPE INSPECTION | N/A | Not Inspected | ||
| 08/13/2007 | GRADING - FINAL | N/A | Partial Approval | Met on site with Mike (J.R. Tuttle) and Carlos (SWPPP Contractor) went over wattle installation (over lap and 2" channel) and wash outs needed for site. Asked Mike to call for inspection when controls are installed. |
| 11/05/2007 | STORMWATER FOLLOW-UP INSP | N/A | Partial Approval | No SWPPP concerns at this time. Building is 3" high. Spoke to Mike site super about it effecting the HC parking and HC ramps. |
Completed Inspections
Permit Status: Expired
Permit Number: T07BU00324
Permit Description: GRADING AIRPORT PROJECT
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/21/2007 | STORMWATER INSTALL OF CONTROLS | MAVERY | Approved | Contractor installed controls. Contractor needs to over lap ends of wattle. Install stakes every 3' to 4'. Spoke to Mike site super in regards to items. |
| 08/24/2007 | ENGINEERING PRE-CONSTRUCTION | MAVERY | Approved | See grading entry 7/27/07 |
| 08/24/2007 | NPPO PRE PERMIT INSPECTION | ACONNOR | Approved |