Permit: T06CM04846
Permit Details
Apply Date:
08/30/2006
Applicant:
VLADIMIR ZILBERMAN
Description:
TI: JAMBA JUICE
Contractors:
- PRESIDIO CONSTRUCTION COMPANY
Permit Reviews
Permit Number - T06CM04846
Permit Status: C of o
Permit Description: TI: JAMBA JUICE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/15/2007 | POST 3RD PARTY REVIEW | 03/19/2007 | COMPLETED |
03/19/2007 | RESUBMITTAL | 04/26/2007 | COMPLETED |
06/11/2007 | 3RD PARTY REVIEW-REVISION/OTHER | 06/21/2007 | COMPLETED |
08/07/2007 | 3RD PARTY REVIEW-REVISION/OTHER | 09/18/2007 | COMPLETED |
08/30/2006 | PLANS OK TO SUBMIT - 3RD PARTY | 08/30/2006 | COMPLETED |
08/30/2006 | 3RD PARTY REVIEW-COMMERCIAL TI | 03/15/2007 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T06CM04846
Permit Status: C of o
Permit Description: TI: JAMBA JUICE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
08/30/2006 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T06CM04846
Permit Description: TI: JAMBA JUICE
Total Completed Inspections - 27
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/25/2007 | FRAMING | AQUIROZ | Approved | IVRS - Inspection :* |
07/31/2007 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection :* |
07/31/2007 | PLUMBING - GAS PRESSURE TEST | RMYERS | Approved | IVRS - Inspection :* |
08/01/2007 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* CHECKED DRYER VENT IN WELL OK TO COVER SUPPLY & EXHAUST IN RESTROOMS OK TO COVER CONDENSATE DRAIN LINE OK TO COVER |
08/03/2007 | SHEET ROCK NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
08/22/2007 | BUILDING ABOVE CEILING | AQUIROZ | Approved | IVRS - Inspection :* |
08/23/2007 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection :* FLANGES OK OK TO COVER ALL AREAS |
08/23/2007 | PLUMBING - ABOVE CEILING | RMYERS | Approved | IVRS - Inspection :* |
08/24/2007 | ELECTRIC - TEMP POWER FOR TEST | CCLEMENS | Approved | IVRS - Inspection :* |
08/27/2007 | TEP CLEARANCE - AM | JWEATHER | Approved | TEC CLEARED FOR #121 PER C. CLEMENS |
08/28/2007 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* OK FOR CEILING TILES |
08/30/2007 | ELECTRIC - ABOVE CEILING | CCLEMENS | Approved | IVRS - Inspection :* INSTALL ALL J-BOXES (COVERS) TODAY BEFORE YOU LEAVE |
09/14/2007 | ENGINEERING - FINAL | JBRUCKME | Approved | |
09/14/2007 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* |
09/14/2007 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
09/17/2007 | RIGHT OF WAY - FINAL | MOTERO | Approved | PER EMAIL |
09/17/2007 | LANDSCAPE - FINAL | ACONNOR | Approved | N/A |
09/17/2007 | NPPO - FINAL | ACONNOR | Approved | N/A |
09/17/2007 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection :* CONTRACTOR TO INSTALL HAMMER ARRESTORS AT WASHER PLUMBING FINAL OK OK FOR C OF O |
09/17/2007 | PLUMBING - PRE SLAB | RMYERS | Approved | IVRS - Inspection :* |
09/17/2007 | PLUMBING - GAS PRESS TEST FNL | RMYERS | Approved | IVRS - Inspection :* |
09/20/2007 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
09/20/2007 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* 1) REMOVE THE WHITE WIRES FROM CONDENSOR DISCONNECTS REPLACE WITH A BLACK WIRE 2) EXTEND WATER HEATER VENT MIN. 2' ABOVE WALL ON ROOF 3) VENT ON CONDENSATE MUST BE DOWNSTREAM OF THE TRAP 4) PROVIDE MIN. 1" CLEARANCE TO COMBUSTIBLES AROUND ENTIRE WATER HEATER VENT THRU ROOF |
09/20/2007 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
09/20/2007 | FIRE - FINAL | LTHOMAS | Approved | |
09/21/2007 | BUILDING - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |
09/24/2007 | SIGN - FINAL | JYBARRA | Approved |