Permit: T06CM03163
Permit Details
Apply Date:
05/26/2006
Applicant:
DESIGN BUILD FIRM LLC
Description:
TI: SCHOOL
Architects:
- DESIGN BUILD FORUM
Contractors:
- 4 DIAMOND BUILDERS
Permit Reviews
Permit Number - T06CM03163
Permit Status: C of o
Permit Description: TI: SCHOOL
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
05/26/2006 | SITE | 08/18/2006 | COMPLETED |
06/21/2006 | PLANS OK TO SUBMIT - 3RD PARTY | 06/21/2006 | COMPLETED |
06/22/2006 | 3RD PARTY REVIEW-COMMERCIAL TI | 08/01/2006 | COMPLETED |
08/01/2006 | POST 3RD PARTY REVIEW | 08/18/2006 | COMPLETED |
11/07/2006 | 3RD PARTY REVIEW-REVISION/OTHER | 11/09/2006 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T06CM03163
Permit Status: C of o
Permit Description: TI: SCHOOL
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
05/26/2006 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T06CM03163
Permit Description: TI: SCHOOL
Total Completed Inspections - 27
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/25/2006 | PLUMBING - ROUGH, SOIL | RLEDONNE | Approved | IVRS - Inspection :* CHECK #129 REDLINE ARE ON DRAWINGS OK TO COVER |
08/25/2006 | PLUMBING - PRE SLAB | RLEDONNE | Approved | IVRS - Inspection :* |
10/12/2006 | FRAMING | AALEGRIA | Approved | IVRS - Inspection :* |
10/19/2006 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* OK NORTH WALLS. AT BLD. CAFETERIA |
11/07/2006 | SHEET ROCK NAILING | AALEGRIA | Approved | IVRS - Inspection :* |
11/20/2006 | PLUMBING - GAS PRESS TEST FNL | RLEDONNE | Approved | IVRS - Inspection :* |
11/20/2006 | PLUMBING - GAS PRESSURE TEST | RLEDONNE | Approved | |
11/21/2006 | EXCAVATION/LAYOUT REBAR & ZON | AALEGRIA | Approved | IVRS - Inspection :* IN COMPLIANCE WITH SPECIAL INSPECTOR REPORT, EPOXY OBSERVATION - DETAILS ON SHEET S2.1 |
12/01/2006 | BUILDING ABOVE CEILING | AALEGRIA | Approved | IVRS - Inspection :* INCLUDE BOTH SIDES OF FIREWALL IN COMPLIANCE WITH PROPER SEALANT ON ALL PENETRATIONS AND 2 LAYER OF DRYWALL. |
12/21/2006 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
12/21/2006 | FIRE - ALARM FINAL | LTHOMAS | Approved | |
12/28/2006 | BUILDING - FINAL | AALEGRIA | Approved | IVRS - Inspection : See detailed listing on site.| 999* 1) NOTE: PROVIDE ALL SPECIAL INSPECTIONS REPORTS FOR NEW MASONRY IN EXISTING MASONRY WALL OPENING, WELDING 3/16 ON ROOF OPENING FRAME, CANOPY SHOP FABRICATIONS FOR WELD REPORTS & EPOXY CONNECTIONS REPORT, PROVIDE AND COMPLETE GRAB BARS ON ADA RESTROOMS, PROVIDE PARKING SIGNS 84" AT BOTTOM OF SIGN FROM FINISH FLOOR, PROVIDE SEALANT ON CRACK ON ACCESS ROUTE TO HAVE FEATURES FOR PEOPLE USING WHEEL CHAIRS OR OTHER MOBILITY AIDS SHALL COMPLY AND COMPLETE ALL CORRECTIONS LEFT FOR ELECTRICAL, PLUMBING, MECHANICAL PLUS FIRE APPROVAL |
12/28/2006 | ENGINEERING - FINAL | MAVERY | Approved | Contractor needs to: 1- Install trucated domes on HC ramp. 2- Install bicycle parking. 3- Complete all over head work. (front of building) 4- Remove port-a-potty. 5- Sweep mud from rear of building. 6- Need to permit or remove mini storage units. 7- Install signage for HC parking. |
12/28/2006 | PLUMBING - FINAL | RRICH | Approved | IVRS - Inspection :* |
12/28/2006 | PLUMBING - YARD WTR LINE/TEST | RRICH | Approved | IVRS - Inspection :* |
12/28/2006 | PLUMBING - INTERMEDIATE | RRICH | Approved | IVRS - Inspection :* |
12/29/2006 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
12/29/2006 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection : See detailed listing on site.| 999* 1) LABEL INSTA-HOTS FOR DISCONNECTING MEANS IN CEILING 2) SUPPORT CONDUITS, MC AT #56 OFFICE-REPLACE MC CABLE (DAMAGED) 3) ADDRESS EXSISTING BREAKER PANEL AT SOUTH WEST CORNER OF BLDG TIE OFF BATH ENDS OF CEILING WIRES USED FOR SUPPORT. ROOM D-26 REPLACE DAMAGED MC CABLE SCREW DOWN FIXTURE IN GRID OR BEND OUT TABS SO THEY ARE EFFECTIVE. CLOSE UP J-BOXES, PANELS 4) NO GFCI'S ON ROOF, NO PANEL SCHEDULES 5) A REINSPECTION FEE WILL BE ASSESSED NEXT INSPECTION IF NO COMPLIANCE |
01/04/2007 | FIRE - FINAL | LTHOMAS | Approved | |
01/05/2007 | RIGHT OF WAY - FINAL | LLOPEZ | Approved | PER EMAIL |
01/05/2007 | NPPO - FINAL | ACONNOR | Approved | |
01/05/2007 | LANDSCAPE - FINAL | ACONNOR | Approved | |
01/09/2007 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
01/10/2007 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | |
02/01/2007 | PERMIT FINALED | LJACKSON | Approved | |
02/01/2007 | ROOF NAILING | AALEGRIA | Approved | IVRS - Inspection :* |
02/01/2007 | BUILDING PRE-SLAB | AALEGRIA | Approved | IVRS - Inspection :* |