Permit Details

Status:
Final
Type:
COMMERCIAL NEW
Apply Date:
04/12/2006
Applicant:
TRANSMARK CO
Description:
SHELL BUILDING FOR MED OFFICE
Contractors:
  • SPECTRUM CONSTRUCTION INC ,

Permit Reviews

Permit Number - T06CM02092
Permit Status: Final
Permit Description: SHELL BUILDING FOR MED OFFICE
Start Date Submittal Complete Date Status  
04/10/2007 3RD PARTY REVIEW-REVISION/OTHER 04/11/2007 COMPLETED Review Details
04/12/2006 SITE 05/18/2006 COMPLETED Review Details
05/09/2006 PLANS OK TO SUBMIT - 3RD PARTY 05/09/2006 COMPLETED Review Details
05/09/2006 3RD PARTY REVIEW-COMMERCIAL 06/21/2006 COMPLETED Review Details
05/18/2006 RESUBMITTAL - SITE 05/19/2006 COMPLETED Review Details
05/19/2006 RESUBMITTAL - SITE 07/13/2006 COMPLETED Review Details
06/21/2006 POST 3RD PARTY REVIEW 07/13/2006 COMPLETED Review Details
12/04/2006 3RD PARTY REVIEW-REVISION/OTHER 12/06/2006 COMPLETED Review Details

Completed Inspections

Permit Status: Final
Permit Number: T06CM02092
Permit Description: SHELL BUILDING FOR MED OFFICE
Total Completed Inspections - 37
Date Description Inspector Results Comments
08/17/2006 PLUMBING - ROUGH, SOIL RMYERS Approved IVRS - Inspection :*
- STILL NO ADDRESS POSTED!
- FITTING COVERED BEFORE INSPECTION
- PAPER WORK VERIFIES THAT PROPER FITTING IS INSTALLED
UNDERGROUND
- OK TO FINISH COVERING.
08/17/2006 PLUMBING - PRE SLAB RMYERS Approved IVRS - Inspection :*
1. I GAVE THE G.C PIMA COUNTY ADDRESSING REQUIREMENTS
2. FEMALE PVC THREADED FITTINGS NOT PERMITTED.
11/15/2006 REINFORCED MASONRY PRE-GROUT AQUIROZ Approved IVRS - Inspection :*
TOP OUT 3.1 3B.5, 3A, 2F 2.75-2.10, 1H 1-1 2.4
24 H - 2-F 16'8"
12/10/2006 PLUMBING - ROOF DRAINS RMYERS Approved IVRS - Inspection :*
ABS SHALL NOT BE DIRECTLY EMBEDDED IN CONCRETE OR MASONRY
12/14/2006 BUILDING PRE-SLAB LHANLY Approved IVRS - Inspection :*
DECK WELDS OK
YOU MUST BLOCK OUT NORTHSIDE OF STAIR 4' WIDE AND
ADD #4 DOWELS 16" O.C
12/14/2006 ELECTRIC - INTERMEDIATE CCLEMENS Approved IVRS - Inspection :*
OK TO COVER SITE LIGHTING UNDERGROUND RACEWAYS
OK TO POUR POLE BASES (5) CLOSEST TO STRUCTURE.

NOTE: HAVE PLANS ON SITE FOR INSPECTIONS.
12/14/2006 BUILDING PRE-SLAB AALEGRIA Approved IVRS - Inspection :*
12/14/2006 EXCAVATION/LAYOUT REBAR & ZON AALEGRIA Approved IVRS - Inspection :*
12/14/2006 ELECTRIC - UNDERGROUND CCLEMENS Approved IVRS - Inspection :*
12/27/2006 FRAMING LHANLY Approved IVRS - Inspection :*
12/27/2006 ROOF NAILING LHANLY Approved IVRS - Inspection :*
12/27/2006 FRAMING JWEATHER Approved
12/27/2006 ROOF NAILING JWEATHER Approved CANCELLED BY CONTRACTOR
02/14/2007 TEP CLEARANCE - AM JWEATHER Approved TEC CLEARED FOR PANEL H.P. ONLY PER C. CLEMENS
04/16/2007 BUILDING - FINAL AQUIROZ Approved IVRS - Inspection :*
04/16/2007 BUILDING - PROGRESS AQUIROZ Approved IVRS - Inspection :*
04/16/2007 SHEET ROCK NAILING AQUIROZ Approved IVRS - Inspection :*
04/16/2007 U VALUE FOR WINDOW AQUIROZ Approved IVRS - Inspection :*
05/31/2007 ELECTRIC - CABLE DROP RMAJUTA Approved
05/31/2007 ELECTRIC - PROGRESS RMAJUTA Approved
05/31/2007 ELECTRIC - OUTDOOR LIGHTING RMAJUTA Approved
05/31/2007 OUTDOOR LIGHTING FINAL RMAJUTA Approved
05/31/2007 ELECTRIC - UFER RMAJUTA Approved
05/31/2007 ELECTRIC - FINAL RMAJUTA Approved IVRS - Inspection :*
ITEM #6 COMPLIES WITH NEC 2002 230.40 EXCEPTION #2
07/05/2007 PLUMBING - PROGRESS RMYERS Approved IVRS - Inspection :*
07/05/2007 SEPTIC - SYSTEM RMYERS Approved IVRS - Inspection :*
07/05/2007 PLUMBING - INTERMEDIATE RMYERS Approved IVRS - Inspection :*
07/20/2007 PLUMBING - FINAL RMYERS Approved IVRS - Inspection :*
SHELL ONLY OK FOR LETTER OF COMPLETION
07/20/2007 PLUMBING - YARD WTR LINE/TEST RMYERS Approved IVRS - Inspection :*
07/26/2007 RIGHT OF WAY - FINAL MOTERO Approved PER EMAIL
07/26/2007 NPPO - FINAL ACONNOR Approved
07/26/2007 SIGN - FINAL JSONKIN Approved IVRS - Inspection :*
07/31/2007 FIRE SPKLR - FINAL LTHOMAS Approved
07/31/2007 FIRE - FINAL LTHOMAS Approved
08/30/2007 LANDSCAPE - FINAL ACONNOR Approved
09/18/2007 ENGINEERING - FINAL MRUSSO Approved
03/04/2008 PERMIT FINALED LJACKSON Approved