Permit Details

Status:
C of o
Type:
MULTI FAMILY NEW
Address NEW:
407 W UTAH ST BLDG #02
Apply Date:
03/27/2006
Applicant:
GUILLERMO ANDRADE
Description:
NEW APARTMENTS BLDG#2 UNITS 2101, 2102, & 2103
Contractors:
  • GUILLERMO BUILDERS INC ,

Permit Reviews

Permit Number - T06CM01696
Permit Status: C of o
Permit Description: NEW APARTMENTS BLDG#2 UNITS 2101, 2102, & 2103
Start Date Submittal Complete Date Status  
03/08/2007 RESUBMITTAL 05/04/2007 COMPLETED Review Details
03/27/2006 PLANS OK TO SUBMIT - COMM 04/04/2006 COMPLETED Review Details
04/12/2006 COMMERCIAL NEW 03/08/2007 COMPLETED Review Details
08/27/2007 RESUBMITTAL 12/19/2007 COMPLETED Review Details
08/29/2008 REVISION - - 1ST 11/26/2008 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T06CM01696
Permit Status: C of o
Permit Description: NEW APARTMENTS BLDG#2 UNITS 2101, 2102, & 2103
Total Outstanding Activity Conditions - 1
Date Name
03/27/2006 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T06CM01696
Permit Description: NEW APARTMENTS BLDG#2 UNITS 2101, 2102, & 2103
Total Completed Inspections - 43
Date Description Inspector Results Comments
08/26/2008 EXCAVATION/LAYOUT REBAR & ZON LHANLY Approved IVRS - Inspection :*
08/26/2008 ELECTRIC - UFER DSANTACR Approved IVRS - Inspection :*
08/29/2008 STEM WALL/RETAINING WALL LHANLY Approved IVRS - Inspection :*
OK TO PLACE; NEED SEALED SK1 DRAWING FOR SLIDER
AND 2" OPENING
09/11/2008 PLUMBING - PRE SLAB RLEDONNE Approved IVRS - Inspection :*
09/11/2008 PLUMBING - ROUGH, SOIL RLEDONNE Approved IVRS - Inspection :*
09/12/2008 BUILDING PRE-SLAB MHENSON Approved IVRS - Inspection :*
BOLTS TO BE EPOXIED & SPECIAL INSPECTED DETAIL 10 (S9.1)
10/30/2008 FRAMING MHENSON Approved IVRS - Inspection :*
CANCELED BY CONTRACTOR
11/12/2008 REINFORCED MASONRY PRE-GROUT MHENSON Approved IVRS - Inspection :*
INTERIOR & EXTERIOR WALLS TOP OUT

1. SPECIAL INSPECTED
2. NON-COMPLIANT ISSUES RESOLVED
PER WIRA ENGINEER OF RECORD
12/16/2008 ROOF NAILING MHENSON Approved IVRS - Inspection :*
OK TO DRY IN
12/26/2008 BUILDING - PROGRESS MHENSON Approved IVRS - Inspection :*
1) OK TO POUR BALCONIES WESTERN TEC SPECIAL INSPECTED
01/12/2009 BUILDING ABOVE CEILING MHENSON Approved IVRS - Inspection :*
ALL HARD LIDS INSPECTED UNDER FRAMING
01/14/2009 PLUMBING - ABOVE CEILING RLEDONNE Approved IVRS - Inspection :*
01/28/2009 MECHANICAL - INTERMEDIATE MRAMBER Approved IVRS - Inspection :*
02/17/2009 SHEET ROCK NAILING MHENSON Approved IVRS - Inspection :*
03/03/2009 ELECTRIC - ABOVE CEILING DSANTACR Approved IVRS - Inspection :*
03/03/2009 ELECTRIC - INTERMEDIATE DSANTACR Approved IVRS - Inspection :*
03/12/2009 PLUMBING - INTERMEDIATE RLEDONNE Approved IVRS - Inspection :*
03/25/2009 PLUMBING - SEWER HCS CONNECT RLEDONNE Approved IVRS - Inspection :*
03/31/2009 PLUMBING - YARD WTR LINE/TEST RLEDONNE Approved IVRS - Inspection :*
04/20/2009 U VALUE FOR WINDOW MHENSON Approved IVRS - Inspection :*
05/19/2009 NPPO - FINAL ACONNOR Approved
05/20/2009 STUCCO MESH MHENSON Approved IVRS - Inspection :*
3 SMALL OVERHANGS
05/20/2009 EXT METAL CLIPS/EXT SHEATHING MHENSON Approved IVRS - Inspection :*
05/20/2009 RIGHT OF WAY - FINAL LLOPEZ Approved PER EMAIL
05/20/2009 PLUMBING - PROGRESS RLEDONNE Approved IVRS - Inspection :*
05/20/2009 SIGN - FINAL JYBARRA Approved
05/22/2009 TEP CLEARANCE - AM JWEATHER Approved TMPP CLEARED FOR BLDG 2, #2101, 2102 & 2103
06/10/2009 MECHANICAL - FINAL MHENSON Approved IVRS - Inspection :*
06/11/2009 LANDSCAPE - FINAL ACONNOR Approved
06/16/2009 PLUMBING - FINAL RLEDONNE Approved IVRS - Inspection :*
06/17/2009 ENGINEERING - FINAL MCARREON Approved ALL ITEMS ON PUNCH LIST HAVE BEEN ADDRESSED.
06/23/2009 OUTDOOR LIGHTING FINAL LHANLY Approved IVRS - Inspection :*
06/23/2009 ELECTRIC - OUTDOOR LIGHTING LHANLY Approved IVRS - Inspection :*
06/24/2009 FIRE - FINAL LTHOMAS Approved
06/24/2009 FIRE SPKLR - FINAL LTHOMAS Approved
07/02/2009 PERMIT FINALED LJACKSON Approved
07/02/2009 ELECTRIC - TEMP POWER FOR TEST LHANLY Approved
07/02/2009 ELECTRIC - CONSTRUCTION POWER LHANLY Approved
07/02/2009 ELECTRIC - TEMPORARY SERVICE LHANLY Approved
07/02/2009 ELECTRIC - TEMPORARY POLE LHANLY Approved
07/02/2009 ELECTRIC - UNDERGROUND LHANLY Approved
07/02/2009 BUILDING - FINAL MHENSON Approved IVRS - Inspection :*
1) PER PLAN REVIEW RESULTS #6 HC PARKING NOT REQUIRED PER DAVE MANN
07/02/2009 ELECTRIC - FINAL LHANLY Approved

Documents

File Name Document Type  
C OF O_07-02-2009.TIF CERT OF OCC VIEW
None DOCUMENTS VIEW