Permit Details

Status:
Final
Type:
COMMERCIAL OTHER
Address NEW:
2841 N COLUMBUS BL #01
Apply Date:
09/16/2005
Applicant:
DESERT STAR DESIGN AND CONSTRUCTION
Description:
INSTALL:HEAT PUMP:ELECTRIC PANEL 7 UNITS : # 11-17, 1- 1 STORY BUILDING = RELOCATE SINK R- 8/15/07 CONNECTING LAUNDRY TO UNIT 43
Contractors:
  • EWER CONSTRUCTION

Permit Reviews

Permit Number - T05CM04759
Permit Status: Final
Permit Description: INSTALL:HEAT PUMP:ELECTRIC PANEL 7 UNITS : # 11-17, 1- 1 STORY BUILDING = RELOCATE SINK R- 8/15/07 CONNECTING LAUNDRY TO UNIT 43
Start Date Submittal Complete Date Status  
08/15/2007 REVISION - - 1ST 08/15/2007 COMPLETED Review Details
09/16/2005 OTHER 09/26/2005 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T05CM04759
Permit Status: Final
Permit Description: INSTALL:HEAT PUMP:ELECTRIC PANEL 7 UNITS : # 11-17, 1- 1 STORY BUILDING = RELOCATE SINK R- 8/15/07 CONNECTING LAUNDRY TO UNIT 43
Total Outstanding Activity Conditions - 1
Date Name
09/16/2005 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: Final
Permit Number: T05CM04759
Permit Description: INSTALL:HEAT PUMP:ELECTRIC PANEL 7 UNITS : # 11-17, 1- 1 STORY BUILDING = RELOCATE SINK R- 8/15/07 CONNECTING LAUNDRY TO UNIT 43
Total Completed Inspections - 10
Date Description Inspector Results Comments
01/03/2006 MECHANICAL - INTERMEDIATE JMILITEL Approved IVRS - Inspection :*
1) SEE NOTES FROM 2821
2) RECALL FOR FINAL
09/27/2007 ELECTRIC - INTERMEDIATE RHOLLAND Approved IVRS - Inspection :*
1) OK 33 & 34 SUBJECT TO BLDG INSPECTOR VERIFYING DRILLING OF TRUSSES
2) OK 35 & 36
11/30/2007 TEP CLEARANCE - AM JWEATHER Approved TMPP CLEARED FOR #35 & #36 PER R. HOLLANDER
12/18/2007 MECHANICAL - FINAL JMILITEL Approved OK FOR FINAL UNITS 33, 34, 35 AND 36
12/20/2007 ELECTRIC - FINAL RHOLLAND Approved IVRS - Inspection :*
OK FINAL 33, 34, 35, 36 S.T.O.I
CHECK 30 & 39?
12/20/2007 PLUMBING - FINAL BBENEDON Approved IVRS - Inspection :*
CORRECT LEAKING HB ON SOUTH SIDE
UNITS 33, 34, 35 AND 36 FINAL APPROVED
12/20/2007 PLUMBING - INTERMEDIATE BBENEDON Approved IVRS - Inspection :*
12/21/2007 EXCAVATION/LAYOUT REBAR & ZON JBURGE Approved
12/21/2007 FRAMING JBURGE Approved
12/21/2007 BUILDING - FINAL JBURGE Approved IVRS - Inspection :*
1) UNITS 33-36 COMPLETED

Documents

File Name Document Type  
None DOCUMENTS VIEW
T05CM04759R_001.TIF CONSTRPLANS VIEW
None CONSTRPLANS VIEW