Permit: T05CM04385
Permit Details
Status:
C of o
Type:
COMMERCIAL NEW
Address:
2551 S COUNTRY CLUB RD 02
Address NEW:
2551 S COUNTRY CLUB RD 02
Apply Date:
08/23/2005
Applicant:
METRO PERMIT EXPRESS, INC *C
Description:
NEAVADA RAILROAD MATERIALS TIE-REHAB FACILITY
Contractors:
- 3 D CONTR
- NEVADA RAILROAD MATERIALS INC
Permit Reviews
Permit Number - T05CM04385
Permit Status: C of o
Permit Description: NEAVADA RAILROAD MATERIALS TIE-REHAB FACILITY
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/23/2005 | PLANS OK TO SUBMIT - 3RD PARTY | 08/25/2005 | COMPLETED |
| 08/25/2005 | 3RD PARTY REVIEW-COMMERCIAL TI | 09/22/2005 | COMPLETED |
| 09/22/2005 | POST 3RD PARTY REVIEW | 10/03/2005 | COMPLETED |
| 10/28/2005 | RESUBMITTAL | 10/28/2005 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T05CM04385
Permit Status: C of o
Permit Description: NEAVADA RAILROAD MATERIALS TIE-REHAB FACILITY
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/23/2005 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T05CM04385
Permit Description: NEAVADA RAILROAD MATERIALS TIE-REHAB FACILITY
Total Completed Inspections - 29
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/02/2005 | ELECTRIC - UNDERGROUND | RSUBA | Approved | IVRS - Inspection :*OK UNDERSLAB |
| 03/24/2006 | TEP CLEARANCE - AM | JWEATHER | Approved | TEC CLEARED PER D. SANTACRUZ |
| 04/03/2006 | EXT METAL CLIPS/EXT SHEATHING | LHANLY | Approved | IVRS - Inspection :* NOT APPLICABLE |
| 04/03/2006 | EXCAVATION/LAYOUT REBAR & ZON | LHANLY | Approved | IVRS - Inspection :* BY SPECIAL INSP. CONVERSATION WITH SP. INSP. & SPECIAL INSP REVIEW. |
| 04/03/2006 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
| 04/03/2006 | PLUMBING - FINAL | BBENEDON | Approved | IVRS - Inspection :* |
| 04/03/2006 | SITE - SEWER | BBENEDON | Approved | IVRS - Inspection :* |
| 04/03/2006 | PLUMBING - SEWER HCS CONNECT | BBENEDON | Approved | IVRS - Inspection :* |
| 04/03/2006 | PLUMBING - YARD WTR LINE/TEST | BBENEDON | Approved | IVRS - Inspection :* |
| 04/03/2006 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
| 04/03/2006 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* |
| 04/03/2006 | ELECTRIC - UFER | DSANTACR | Approved | IVRS - Inspection :* |
| 04/03/2006 | OUTDOOR LIGHTING FINAL | DSANTACR | Approved | IVRS - Inspection :* |
| 04/03/2006 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
| 04/03/2006 | ELECTRIC - OUTDOOR LIGHTING | DSANTACR | Approved | IVRS - Inspection :* |
| 04/03/2006 | ROOF NAILING | LHANLY | Approved | IVRS - Inspection :* |
| 04/03/2006 | BUILDING PRE-SLAB | LHANLY | Approved | IVRS - Inspection :* |
| 04/03/2006 | RIGHT OF WAY - FINAL | LLOPEZ | Approved | PER EMAIL |
| 07/14/2006 | FRAMING | LHANLY | Approved | |
| 07/14/2006 | BUILDING - FINAL | LHANLY | Approved | IVRS - Inspection :* OK C OF O |
| 07/17/2006 | ENGINEERING - FINAL | MAVERY | Approved | Contractor completed punch list. Loren Makus approved trash enclosure. |
| 07/19/2006 | FIRE SPKLR - UG PIPING FLUSH | LTHOMAS | Approved | |
| 07/19/2006 | FIRE SPKLR - OH PIPING & HYDRO | LTHOMAS | Approved | |
| 07/19/2006 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
| 07/19/2006 | FIRE - HYDRANTS | LTHOMAS | Approved | |
| 07/19/2006 | FIRE - FINAL | LTHOMAS | Approved | |
| 07/19/2006 | FIRE SPKLR - UG, PIPING, HYDRO | LTHOMAS | Approved | |
| 07/19/2006 | NPPO - FINAL | ACONNOR | Approved | |
| 07/19/2006 | LANDSCAPE - FINAL | ACONNOR | Approved |